Pregunta 1
Pregunta
Which of the following are a purpose of an Issue Report?
1. Document an off-specification
2. Record an issue resolution
3. Capture all problems or concerns within the project
4. Capture recommendations for handling a request for change
Pregunta 2
Pregunta
Which product establishes the baseline against which the project's actual performance is compared?
Pregunta 3
Pregunta
Which is NOT identified when creating a product breakdown structure?
Respuesta
-
Products to be created by internal resources
-
Products to be modified
-
Resources required to produce the products
-
Products to be created by an external third party
Pregunta 4
Pregunta
Which statement regarding a project's outputs, outcomes and benefits is correct?
Respuesta
-
All outputs have tangible benefits
-
Outcomes are the long term results of benefits
-
Outputs are changes in the way the project's products are used
-
Benefits are improvements resulting from project outcomes
Pregunta 5
Pregunta
What process covers the acceptance and execution of project work by external suppliers?
Pregunta 6
Pregunta
Which is NOT a PRINCE2 integrated element?
Pregunta 7
Pregunta
What is the goal of the 'Identify context' step within the recommended risk management procedure?
Respuesta
-
Identify responses to risks identified in the Business Case
-
Understand the specific objectives that are at risk
-
Gather information about risks for inclusion in Highlight Reports to the Project Board
-
Identify the threats and opportunities that may affect the project's objectives
Pregunta 8
Pregunta
Which is a purpose of the Project Product Description?
Respuesta
-
Defines the reporting structure to be used by the project
-
Provides information on what the project is about and how it is to be managed
-
Describes what the project has to produce to obtain customer acceptance
-
Provides input to creation of the project mandate
Pregunta 9
Pregunta
Which defines the sequence in which the products of a plan should be developed?
Pregunta 10
Pregunta
If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform The Project Manager?
Pregunta 11
Pregunta
What process enables an organisation to understand the work that needs to be done to deliver a project's products before it is approved?
Respuesta
-
Directing a Project
-
Initiating a Project
-
Starting up a Project
-
Controlling a Stage
Pregunta 12
Pregunta
Which is a purpose of Controlling a Stage process?
Respuesta
-
Agree, perform and deliver project work
-
Draft a plan for the next stage
-
Agree stage tolerances
-
Take action to make sure that the stage remains within tolerance
Pregunta 13
Pregunta
Which of the following roles can the Project Manager also perform?
1. Change Authority
2. Project Assurance
3. Project Support
4. Team Manager
Pregunta 14
Pregunta
Which is a responsibility of the Project Assurance role?
Respuesta
-
Inform the Project Manager about the status of the project's products
-
Document the Project Board's reporting needs
-
Ensure the Project Manager is aware of the need to use any existing corporate standards
-
Inform corporate or programme management about the project's status
Pregunta 15
Pregunta
When is it confirmed if a project's objectives have been achieved?
Respuesta
-
During the Closing a Project process
-
During the final end stage assessment
-
During the Controlling a Stage process
-
During the Managing Product Delivery process
Pregunta 16
Pregunta
Which is a definition of a risk cause?
Respuesta
-
The impact of a risk on the stage and project tolerance
-
The source of a risk
-
The overall effect of a risk on the Business Case
-
How likely a risk is to occur in a given project situation
Pregunta 17
Pregunta
When would the Team Manager be required to produce a Checkpoint Report?
Respuesta
-
When a Work Package is being negotiated
-
At the frequency agreed in the Work Package
-
On completion of the quality -checking activities for each product
-
When reviewing how a stage is progressing
Pregunta 18
Pregunta
Which is a recommended quality review team role?
Respuesta
-
Project Manager
-
Presenter
-
Project Support
-
Producer
Pregunta 19
Pregunta
What PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?
Pregunta 20
Pregunta
In which situation might the Controlling a Stage process be used?
Respuesta
-
Managing a long initiation stage of a complex product
-
Managing the activities of a complex programme
-
Managing support activities following the handover of the products to the operational environment
-
Creating an Exception Plan to replace the current Stage Plan
Pregunta 21
Pregunta
Which is a responsibility of the business representative on the Project Board?
Respuesta
-
Setting tolerance levels for the project
-
Ensuring the project represents value for money
-
Confirming the project delivers the required functionality
-
Checking the required quality levels are achieved by the project's products
Pregunta 22
Pregunta
Which Statement correctly describes the relationship between Project Assurance and Quality Assurance?
Respuesta
-
Project Assurance provides assurance to the project's stakeholders whereas quality assurance provides assurance to the wider Corporate or Programme organisation.
-
They are both the responsibility of the Project Board, but Project Assurance may be delegated.
-
They are both independent of the project
-
Project Assurance and quality assurance are both the responsibility of corporate or programme management
Pregunta 23
Pregunta
Which of the following assists the Project Board in assessing the project viability at certain points as defined in the Project Plan?
Respuesta
-
Receiving regular Checkpoint Reports
-
Authorising one stage at a time
-
Creating Exception Reports when tolerances are threatened
-
Authorising project closure
Pregunta 24
Pregunta
Which is a purpose of the Change Theme?
Respuesta
-
Prevent change to anything agreed in the Project Initiation Documentation
-
Ensure any potential changes to base-lined products are controlled
-
Assess and control uncertainty
-
Assess changes to only the specialist products
Pregunta 25
Pregunta
What product would confirm the version numbers of all products being developed within a given stage.
Pregunta 26
Pregunta
Which is a benefit of using PRINCE2?
Respuesta
-
Stakeholders are kept out of planning and decision-making
-
Participants understand each other's roles and needs
-
Stakeholder are not involved in assuring the project work
-
All problems are escalated to all stakeholders
Pregunta 27
Pregunta
In what product would a product's quality tolerance be defined?
Pregunta 28
Pregunta
When should the Managing a Stage Boundary process be undertaken?
Respuesta
-
Close to the end of a management stage
-
After the completion of each management stage
-
At the end of the final stage
-
At the end of project start-up
Pregunta 29
Pregunta
Which is a purpose of a risk budget?
Respuesta
-
To fund risk management activities defined in the risk management procedure
-
To fund the cost of analysing requests foe change while executing a Work Package
-
Funds set aside from the project budget to cover the costs of implementing risk responses
-
Funds sets aside from the project budget to cover the costs of identifying risks to the project
Pregunta 30
Pregunta
Which role is part of the project team?
Pregunta 31
Pregunta
Identify the missing word in the following sentence.
PRINCE2 management stages relate to the [?], which is a factor that differentiates them from technical stages.
Respuesta
-
use a particular set of technical skills
-
use a specific set of Team Managers
-
Authorisation from corporate or programme management
-
Commitment of resources
Pregunta 32
Pregunta
What principle is supported by the Project Product Description?
Pregunta 33
Pregunta
Identify the missing word(s) in the following sentence.
Quality planning provides the definition of the required products with their [?] as a foundation for Project Board agreement.
Pregunta 34
Pregunta
Which is a definition for risk probability?
Respuesta
-
Scale of the risk should it occur
-
Probable effect on the project delivering its objectives
-
Probable timeframe within which the risk may occur
-
A measure of the likelihood of the risk occurring
Pregunta 35
Pregunta
Which is NOT an event-driven control?
Pregunta 36
Pregunta
Identify the missing words in the following sentence.
The Project Board will allocate tolerances [?] to the Project Manager.
Pregunta 37
Pregunta
Which is NOT a purpose of a Product Description?
Respuesta
-
Define the time and cost needed to produce the product
-
Define the quality skills required to check the product
-
Define the function and appearance of the product
-
Define the development skills required to produce the product
Pregunta 38
Pregunta
Which is a purpose of a Communication Management Strategy?
Respuesta
-
Ensuring the project team can use the required reporting tools
-
Producing reports for the Project Board
-
Defining the Communication method between the Project Board and corporate or programme management
-
Ensuring stakeholders are aware of their responsibilities
Pregunta 39
Pregunta
Identify the missing word(s) in the following sentence.
During the Controlling a Stage process , the [?] us checked for any new or revised threats and their possible impact on the Business Case.
Respuesta
-
Benefits Review Plan
-
End Stage Report
-
Risk Register
-
Risk Management Strategy
Pregunta 40
Pregunta
In what plan should project closure activities be planned?
Pregunta 41
Pregunta
Which role is ultimately in charge of the project?
Pregunta 42
Pregunta
What is the recommended frequency for Project Board meetings during a delivery stage to check progress?
Pregunta 43
Pregunta
In the event of the Project Manager being given conflicting instructions, whose instruction should he or she follow?
Respuesta
-
The Executive's as chair of the Project Board
-
The Senior User's, as the role responsible for delivering the benefits
-
The Senior Supplier's, as the role responsible for ensuring that the project is achievable
-
Property Assurance's, as the role responsible for checking the running of the Project
Pregunta 44
Pregunta
In the activity 'Authorise Initiation', which of the following would the Project Board use to support its decision on whether to go ahead and start the project?
Pregunta 45
Pregunta
In which activity would the Project Board instruct the Project Manager to shut down the project prematurely, should that be necessary?
Pregunta 46
Pregunta
Which role is responsible for approving the Project Brief?
Pregunta 47
Pregunta
In which PRINCE2 process are the members of the Project Board appointed?
Pregunta 48
Pregunta
Which of the following is NOT an objective of the process Directing a Project? To ensure that:
Respuesta
-
There's authority to initiate the Project.
-
There's authority to deliver the project's products.
-
Corporate or programme management has an interface to the project.
-
The products being produced by the teams are delivered to expectations.
Pregunta 49
Pregunta
What is the final phrase in the following purpose statement. To enable the Project Board to be accountable for the project's success by making key decisions and exercising overall control while:
Respuesta
-
Maintaining a low degree of risk exposure
-
Ensuring that the benefits specified in the Business Case can be delivered
-
Authorising spending only within the agreed financial tolerances (limits)
-
Delegating day-to-day management of the project to the Project Manager
Pregunta 50
Pregunta
Which of the following is NOT an input into the activity 'Give ad hoc direction'?
Respuesta
-
Highlight Report (the progress report from the Project Manager to the Board)
-
Exception Report (referral of something projected to go beyond the Project Manager's Authority)
-
Issue Report (a report setting down the detail of an issue being referred to the board)
-
End Stage Report (a report giving the board details such as the final cost of a stage just finishing)
Pregunta 51
Pregunta
Which of the following does NOT form part of the Project Initiation Documentation (PID).
Pregunta 52
Pregunta
Which of the following strategies defines how change control will be carried out?
Respuesta
-
Risk Management Strategy
-
Quality Management Strategy
-
Configuration Management Strategy
-
Communication Management Strategy
Pregunta 53
Pregunta
Which of the following is an accurate definition of a stakeholder in PRINCE2?
Respuesta
-
someone who's a member of the Project's Project Board
-
Someone who can affect, or be affected by, the project
-
Someone with financial responsibility for the project
-
Someone who's responsible for the delivery of business benefits
Pregunta 54
Pregunta
Which of the following is used in PRINCE2 to record when business benefits will be measured?
Respuesta
-
Benefits Register
-
Business Case
-
Benefits Review Plan
-
Project Cashflow
Pregunta 55
Pregunta
Which of the following options name plans which are created in the process Initiating a project?
Respuesta
-
Project Plan and Benefits Review Plan
-
Project Plan together with all Stage Plans
-
Project Plan and Business Plan
-
Benefits Review Plan and Team Plan
Pregunta 56
Pregunta
Which of the following does PRINCE2 include as a section in the full Business Case?
Pregunta 57
Pregunta
Which role is responsible for producing the Project Initiation Documentation (PID)?
Respuesta
-
Executive
-
Senior User
-
Sponsor
-
Project Manager
Pregunta 58
Pregunta
What's the name of the progress report produced by the Project Manager in the Process Controlling a Stage?
Respuesta
-
Stage Process Report
-
Highlight Report
-
Checkpoint Report
-
Stage Control Report
Pregunta 59
Pregunta
Which of the following phrases is part of the purpose statement for the process Initiating a Project?
Respuesta
-
To establish a clear organisation structure for the project
-
To produce a Stage Plan for each delivery stage to determine total cost
-
To ensure that all risks in the project have been identified and their management planned
-
To establish solid foundations for the project
Pregunta 60
Pregunta
Progress reports, produced during each stage, are sent to Project Board members. What does the Project Manager check to see whether a copy should be sent to anyone else?
Pregunta 61
Pregunta
Which of the following is NOT used as an input to the activity Prepare the Risk Management Strategy?
Respuesta
-
Project Mandate
-
Project Brief
-
Lessons Log
-
Daily Log
Pregunta 62
Pregunta
Why does the Project Manger check the Benefits Review Plan from time to time during a delivery stage?
Respuesta
-
To update it with benefits achieved to date
-
To record who is responsible for specifying benefits
-
To enter details of dis-benefits identified in the Initiation Stage
-
To see whether any benefits reviews are due and, if so, arrange them
Pregunta 63
Pregunta
Which of the following products are created in the process Initiating a Project?
1. Risk Register
2. Issue Register
3. Project Plan
4. Project Product Description