1/ Which part of the Building Regulations deals with the energy efficient installation of central heating systems in domestic properties?
Respuesta
  • a) Part G
  • b) Part L1
  • c) Part L2
  • d) Part M

Pregunta 2

Pregunta
2/ Details of the heat output requirement for a particular radiator can be found in which of the following documents?
Respuesta
  • a) British Standards
  • b) Water Regulations
  • c) Building Regulations
  • d) Manufacturer’s brochure

Pregunta 3

Pregunta
3/ What is the likely outcome of rigidly fixing central heating pipework to the notched sections in timber first floor joists?
Respuesta
  • a) Rupture of the pipework
  • b) A reduction in energy efficiency
  • c) Corrosion of the pipework
  • d) Expansion and contraction noise

Pregunta 4

Pregunta
4/ The main disadvantage of using a one pipe circuit to the radiators in a central heating system is that –
Respuesta
  • a) The last radiator on the circuit will be fed with water at a lower temperature than the first
  • b) The first radiator on the circuit will be fed with water at a lower temperature than the last
  • c) Pipework feeding all radiators must be 22mm in diameter
  • d) The circuit cannot be pumped, gravity circulation must be used

Pregunta 5

Pregunta
5/ Which fully pumped central heating system control component is missing from ` the following diagram?
Respuesta
  • a) Pump
  • b) Cylinder thermostat
  • c) Room thermostat
  • d) Mid-position valve

Pregunta 6

Pregunta
6/ What is the minimum size of open vent pipe to a fully pumped central heating system in a small domestic property?
Respuesta
  • a) 10mm
  • b) 15mm
  • c) 22mm
  • d) 28mm

Pregunta 7

Pregunta
7/ Which one of the following additional components will require to be installed when replacing a single feed indirect cylinder with a double feed indirect cylinder?
Respuesta
  • a) Frost thermostat
  • b) Feed and expansion cistern
  • c) Cold water storage cistern
  • d) Automatic bypass valve

Pregunta 8

Pregunta
What would be the main effect on the central heating system if the circulator was installed in the position shown in this diagram?
Respuesta
  • a. The system would be under negative pressure
  • b. The system would be mostly under negative pressure
  • c. The system would be pumping over the open vent
  • d. The neutral position would be at the base of the open vent.

Pregunta 9

Pregunta
The feed and expansion cistern in an open vented central heating system should be capable of receiving what percentage volume of water from the heating system when heated –
Respuesta
  • a) 2%
  • b) 4%
  • c) 8%
  • d) 16%

Pregunta 10

Pregunta
The recommended vertical height from floor level to the position of a room thermostat is –
Respuesta
  • a) 1.0m
  • b) 1.5m
  • c) 2.0m
  • d) 2.5m

Pregunta 11

Pregunta
Which air separator port in the following diagram is the flow pipe from the boiler connected to?
Respuesta
  • a) Port 1
  • b) Port 2
  • c) Port 3
  • d) Port 4

Pregunta 12

Pregunta
Which of the following statements is correct in relation to the installation of thermostatic radiator valves?
Respuesta
  • a) Thermostatic radiator valves may only be fitted to ground floor radiators in a property
  • b) Thermostatic radiator valves may only be fitted to first floor radiators in a property
  • c) All radiators in a property should be fitted with thermostatic radiator valves
  • d) At least one radiator in a property should be fitted without a thermostatic radiator valve

Pregunta 13

Pregunta
Which pipe connects to the AB port of the mid-position valve in the following diagram?
Respuesta
  • a) Open vent pipe
  • b) Flow pipe to the cylinder
  • c) Return pipe from the cylinder
  • d) Flow pipe from the pump

Pregunta 14

Pregunta
Which of the following components is fitted at the high points in pipework in central heating systems?
Respuesta
  • a) Automatic air vent
  • b) Non-return valve
  • c) Automatic bypass valve
  • d) Drain valve

Pregunta 15

Pregunta
Central heating systems with metallic pipework materials are normally soundness tested to what test pressure?
Respuesta
  • a) 0.5 times the maximum operating pressure
  • b) The maximum operating pressure
  • c) 1.5 times the maximum operating pressure
  • d) Twice the maximum operating pressure

Pregunta 16

Pregunta
Which of the following is part of the commissioning procedure for a new central heating system?
Respuesta
  • a) Hot flushing to assist with flux removal
  • b) Disinfecting the system with chlorine
  • c) Removing the feed & expansion cistern during filling
  • d) Lubricating the circulating pump with oil

Pregunta 17

Pregunta
When replacing a radiator and its associated valves sited on the first floor of a property which is the most efficient way of draining the water to undertake the work?
Respuesta
  • a) Turn off the valves and drain down the radiator
  • b) Completely drain the whole system
  • c) Drain the system to below the first floor
  • d) Isolate the cistern and empty its contents

Pregunta 18

Pregunta
The safest method of ensuring that the electrical controls in a central heating system cannot be re-activated during temporary decommissioning work is to –
Respuesta
  • a) Isolate the system from the supply at the consumer unit and get on with the work
  • b) Switch off the supply to the system at the fused spur, retain the fuse and check for safe isolation
  • c) Switch off the supply to the system at the fused spur and check for safe isolation
  • d) Switch off the fused spur remove the wires from its outlet and tape up the ends

Pregunta 19

Pregunta
What is the likely problem arising from a bypass not being fitted to an open vented close-coupled fully pumped heating system controlled by 2 x two port valves on the heating and hot water circuits?
Respuesta
  • a) ‘Sucking down’ and ‘pumping over’ the open vent pipe
  • b) Blockage occurring in the cold feed pipe
  • c) Rapid pinhole corrosion of the radiators
  • d) No cool water from the f & e cistern if the system overheats

Pregunta 20

Pregunta
Which of the following central heating components may contain a replaceable packing gland?
Respuesta
  • a) Circulating pump
  • b) Automatic air vent
  • c) Thermostatic radiator valve
  • d) Room thermostat
Mostrar resumen completo Ocultar resumen completo

Similar

formulas físicas basica
michelkiss25
Cómo Escribir texto en inglés
maya velasquez
Mapa conceptual de la materia._1
gaby271975
Italiano-B1.1-verbi
Diego Borghetto
Alemán Básico
Virginia León
Concepto y funciones del área de Recursos Humanos
Erika Caro
LITERATURA MEDIEVAL
sanzjavier14
MATEMÁTICAS: ARITMÉTICA...
Ulises Yo
Análisis de una Pintura
Diego Santos
MAPA CONCEPTUAL DE NETIQUETA
Hayler Narvaez
UNIDAD 1-2-3. CONSTRUCTOS TEORICOS DEL APRENDIZAJE - PARADIGMAS DEL APRENDIZAJE-PSICOLOGIA Y APRENDIZAJE
veronica marin herrera