Pregunta 1

Pregunta
The reason the Scrum Master is at the Daily Scrum is:
Respuesta
  • To make sure everyone answers the three questions in order of seniority
  • He or she does not have to be there; he or she only has to ensure the Team has a Daily Scrum
  • To write down any changes to the Sprint Backlog, including adding new items, and tracking progress on the burndown.
  • So he or she knows what to report to management

Pregunta 2

Pregunta
The timebox for a Daily Scrum is?
Respuesta
  • The same time of day every day.
  • Two minutes per person.
  • 4 hours.
  • 15 minutes.

Pregunta 3

Pregunta
Since no new work can be added to a Sprint, what is the appropriate characteristic of the Sprint Backlog during the Sprint?
Respuesta
  • The Sprint backlog never changes.
  • The Sprint Backlog can only change with the approval of the Product Owner.
  • The Sprint Backlog is defined based on the work necessary to build the selected Product Backlog items.
  • The Sprint Backlog is created during the Sprint Planning meeting and should not need to be changed afterward

Pregunta 4

Pregunta
An organization has decided to adopt Scrum, but management want to change the terminology to fit with terminology already used. What will likely happen if they do so?
Respuesta
  • Without a new vocabulary as a reminder of the change, very little change may actually happen.
  • The organization may not understand what has changed within Scrum and the benefits of Scrum may be lost.
  • Management may feel more anxious.
  • All answers apply.

Pregunta 5

Pregunta
Is Sprint a PDCA Cycle?
Respuesta
  • True
  • False

Pregunta 6

Pregunta
Frank is the Scrum Master and decided to cancel the Sprint. What should be the PO response?
Respuesta
  • Nothing
  • Do not accept cancellation as this is your prerogative
  • Agree with Scrum Master

Pregunta 7

Pregunta
What event does development team present the work and receives feedback(product)?
Respuesta
  • Planning
  • Daily
  • Review
  • Retro

Pregunta 8

Pregunta
The product owner can not participate in the planning, what should we do?
Respuesta
  • Nothing
  • Do not accept
  • do not do the planning and wait for the availability of the product owner to schedule a new date
  • B + C

Pregunta 9

Pregunta
) HOW CAN PRODUCT OWNER HELP TIME DELIVER VALUE ON EACH SPRINT?
Respuesta
  • Prioritizing Business Value Relevance
  • defining dev team tasks
  • acting effectively on the daily
  • All

Pregunta 10

Pregunta
Your product does not have a product owner, what would be the criteria you would use to choose?
Respuesta
  • Age
  • Communication skills and product knowledge
  • Project Manager
  • a developer

Pregunta 11

Pregunta
During the review the Product Owner rejected two user stories. Should we increase the size of the current sprint?
Respuesta
  • True
  • False

Pregunta 12

Pregunta
When should a sprint be canceled?
Respuesta
  • when the goal does not make any sense
  • when the deadline is insufficient
  • when the staff asks for the cancellation
  • All

Pregunta 13

Pregunta
What is planning poker?
Respuesta
  • The method
  • a path where the development team estimates the effort to build user stories
  • The framework
  • All

Pregunta 14

Pregunta
What is not part of the product backlog?
Respuesta
  • administrative tasks
  • meetings
  • detailed tasks
  • All

Pregunta 15

Pregunta
What best defines the role of Scrum Master?
Respuesta
  • auditor
  • manager
  • Project manager
  • facilitator

Pregunta 16

Pregunta
What main activity should the product owner perform in a Scrum team?
Respuesta
  • delegate tasks
  • build the product
  • prioritize sprint backlog items
  • maximize the value of the product

Pregunta 17

Pregunta
What is the purpose of product backlog refinement?
Respuesta
  • delete items
  • include new items
  • organize, detail and reprioritize backlog items
  • All

Pregunta 18

Pregunta
After identifying that a user story does not have enough details to enter the next sprint, what should the product owner do?
Respuesta
  • inserts the story anyway
  • Do not insert the story.
  • cancel sprint
  • All

Pregunta 19

Pregunta
During the sprint, a dev team member has a question. When requesting help from the product owner, you receive the following response: "I am not available". How can Scrum Master help?
Respuesta
  • Scrum Master can not help
  • the Scrum Master explains to the product owner that he needs to clarify the doubts of the team, and helps the product owner find the time.
  • The Scrum Master says that the doubt is not important
  • none of the answers

Pregunta 20

Pregunta
During the retrospective, what is the role of the product owner?
Respuesta
  • Participate actively, after all he is part of the scrum team
  • he does not participate
  • just as a listener
  • none of the answers

Pregunta 21

Pregunta
The product backlog needs to be fully detailed?
Respuesta
  • True
  • False

Pregunta 22

Pregunta
During planning is the sprint backlog fully identified?
Respuesta
  • True
  • False

Pregunta 23

Pregunta
The product owner did not detail the items for the next sprint, can we start this way?
Respuesta
  • True
  • False

Pregunta 24

Pregunta
How can Scrum Master help the product owner?
Respuesta
  • Supporting the process of refining the product backlog and removing the impediments of dev team
  • He will not help
  • Estimating user stories
  • All

Pregunta 25

Pregunta
What does not happen in part 1 of the planning?
Respuesta
  • set the goal
  • item estimation
  • Dev has been breaking down the stories into tasks
  • none of the answers

Pregunta 26

Pregunta
In a one-month sprint, what is the Daily timebox?
Respuesta
  • 15 minutes
  • 30 minutes
  • 60 minutes
  • 45 minutes

Pregunta 27

Pregunta
When does the daily end?
Respuesta
  • 15 minutes maximum
  • depends on the size of the sprint
  • When Scrum Master sets
  • All

Pregunta 28

Pregunta
Why cancel a sprint?
Respuesta
  • When the goal does not make any sense
  • When you do not end the sprint backlog
  • Whenever the CEO decides
  • All

Pregunta 29

Pregunta
Can the Product Owner question an estimate of the Dev Team?
Respuesta
  • True
  • False

Pregunta 30

Pregunta
Can the Sprint backlog be changed by the product owner at what time?
Respuesta
  • When the product owner needs it, he must inform the team and negotiate the new item
  • Can not change
  • Can only be changed in case of cancellation
  • Scrum Master must authorize
Mostrar resumen completo Ocultar resumen completo

Similar

Phrasal Verbs
GoConqr suporte .
Phrasal Verbs II
GoConqr suporte .
Apresentação em Inglês
GoConqr suporte .
Todos os verbos irregulares em inglês com tradução
Luiz Fernando
English General Quiz
Luiz Fernando
Simulado Inglês
Marina Faria
Study Planning: English
Wilza França
LINKING WORDS
Gabi Borba
Linking Words
Raíza Da Cunha
Français-Anglais: Salutation / Prèsentation / Politesse
Fátima Menezes