Pregunta 1

Pregunta
Who is responsible for Quality and GMP in the University of Manchester cleanroom facility?
Respuesta
  • Quality Assurance Manager
  • Qualified Person (QP)
  • Professor Sue Kimber
  • Production Manager
  • Everyone who works in this area

Pregunta 2

Pregunta
What is the abbreviation IMP used for?
Respuesta
  • Inner Membrane Protein
  • Inosine Monophosphate
  • Investigational Medicinal Product

Pregunta 3

Pregunta
How do you ascertain that a piece of equipment in the cleanroom is ready for use?
Respuesta
  • Review its cleaning record
  • Review its calibration record/status
  • Review its validation record/status
  • Review its performance qualification
  • All of the above

Pregunta 4

Pregunta
The definition of GMP is ‘a quality system (a) - - - - - - - that products are (b) - - - - - - - - manufactured to a (c) - - - - - - - appropriate to their intended use’.
Respuesta
  • (a) assuring, (b) correctly, (c) system
  • (a) ensuring, (b) consistently, (c) quality
  • (a) checking, (b) properly, (c) scheme

Pregunta 5

Pregunta
The drug which made a large contribution to the necessity to set up the Medicines Act was Thalidomide. True or false?
Respuesta
  • True
  • False

Pregunta 6

Pregunta
The primary concern of the MHRA and other regulators is to ensure .......
Respuesta
  • that they visit every pharmaceutical manufacturer once a year.
  • that foreign drugs do not enter the UK market.
  • patient safety.
  • that they thoroughly check all manufacturing and cleaning records.

Pregunta 7

Pregunta
Quality Risk Management is described in ....
Respuesta
  • ICH guideline Q9
  • ICH guideline Q2
  • ICH guideline Q8

Pregunta 8

Pregunta
If you make an error when entering information on to a GMP document, what should you do?
Respuesta
  • Use Tippex to erase the entry, then write on top of it once dry.
  • Use pencil for all entries so you can easily rub it out and re-write it.
  • Use a single line to cross through the original entry, then enter the correct information as close as possible to the original entry. Sign and date the amendment with a brief explanation for the change.
  • Use a line of crosses so the original entry can no longer be seen, then enter the correct information as close as possible to the original entry, sign and date this change.

Pregunta 9

Pregunta
What should happen to rejected materials?
Respuesta
  • They should be put in a suitable waste bin as soon as possible.
  • They should be labelled as rejected and stored with other materials.
  • They should be clearly labelled as rejected and stored separately in a restricted area.
  • They should be saved and used as material in experimental work.

Pregunta 10

Pregunta
For GMP outsourcing, what documentation must be in place between a contract giver and contract acceptor, e.g. for contract manufacturing or analysis?
Respuesta
  • All the information necessary to manufacture or test in accordance with the Marketing Authorisation, CTA or IND.
  • A fully signed contract between both parties.
  • A technical/quality agreement.
  • A list of responsibilities.
  • All of the above.

Pregunta 11

Pregunta
If you have an approved recall SOP, it is not necessary to test your recall process. True or false?
Respuesta
  • True
  • False

Pregunta 12

Pregunta
A 30 page batch manufacturing record must include the batch number on every page. True or false?
Respuesta
  • True
  • False

Pregunta 13

Pregunta
If you record a weight using a thermal printer and this is securely attached to the batch manufacturing record, it is not necessary to perform any further action. True or false?
Respuesta
  • True
  • False

Pregunta 14

Pregunta
How long should it take to fully sign off a deviation?
Respuesta
  • One week
  • 3 months
  • 28 days
  • 48 hours

Pregunta 15

Pregunta
Following GMP is guidance. True or false?
Respuesta
  • True
  • False

Pregunta 16

Pregunta
Who can release a pharmaceutical product for use in a clinical trial?
Respuesta
  • The principal investigator of the clinical trial.
  • The Quality Assurance (QA) Manager.
  • A Qualified Person (QP).
  • The university professor responsible for the clinical trial.

Pregunta 17

Pregunta
What types of licence may be required for working in the University of Manchester cleanroom facility?
Respuesta
  • Human Tissue Authority (HTA) licence.
  • MHRA Manufacturer Investigational Medicinal Products (MIAIMP).
  • MHRA Wholesale Dealer Licence (WL).
  • Human Fertilisation and Embryology Authority (HFEA) Research Licence.

Pregunta 18

Pregunta
A GMP requirement for Quality Control (QC) is .......
Respuesta
  • test methods are the latest available.
  • testing methods are environmentally friendly.
  • test methods are validated.

Pregunta 19

Pregunta
GMP stands for Good Medicines Practice. True or false?
Respuesta
  • True
  • False

Pregunta 20

Pregunta
A Quality Risk Management System should ensure that .......
Respuesta
  • the evaluation of the risk to quality is based on scientific knowledge, experience with the process and ultimately links to the protection of the patient.
  • the level of effort, formality and documentation of the quality risk management process is commensurate with the level of risk.
  • it effectively replaces direct communications between industry and regulators.
  • All of the above.
Mostrar resumen completo Ocultar resumen completo

Similar

Fórmulas Geométricas (Áreas)
Diego Santos
42 Frases de Cine
Diego Santos
Test Cuerpos Geométricos
Ruth Pérez Sánchez
La Primera Guerra Mundial
juanmadj
Fechas clave de la Historia de España
maya velasquez
Biomoleculas
Saul Herrera
Recursos de Biología para Selectividad
Diego Santos
Músculos del hombro
Nadim Bissar
Examen Parcial de Derecho de Familia
Jonas Nomas
Composición de la pintura
cog1824
Mapa mental de Responsabilidad Social Empresarial RSE
Rosmunda Pierri