Pregunta 1

Pregunta
One potential disadvantage of a matrix organization is:
Respuesta
  • a. Highly visible project objectives.
  • b. Rapid responses to contingencies.
  • c. Team members must report to more than one boss.
  • d. The matrix organization creates morale problems

Pregunta 2

Pregunta
Team building is primarily the responsibility of?
Respuesta
  • a. The project team.
  • b. The project manager.
  • c. Senior management.
  • d. The project sponsor.

Pregunta 3

Pregunta
A Responsibility Assignment Matrix would eliminate which of the following??
Respuesta
  • a. Confusion on how long the tasks are
  • b. Confusion on who is on the team
  • c. Confusion on what order tasks come in
  • d. Confusion on who is responsible for doing what

Pregunta 4

Pregunta
Resource management encompasses:
Respuesta
  • a. Plan Resource Management, Staff Acquisition, Performance Reporting, Develop Team, Manage Team Control Resources
  • b. Plan Resource Management, Estimate Team Activity Resources, Acquire Resources, Manage Team, Control Human Resources
  • c. Plan Human Resource Management, Staff Acquisition, Develop Project Team, Manage Project Team, Control Resources
  • d. Plan Resource Management, Estimate Activity Resources, Acquire Project Team, Develop Project Team, Manage Project Team, Control Resources

Pregunta 5

Pregunta
Joe Johnson has signed the charter for the project after evaluating the need for the project. He did this because he will pay for the project, and know the expected benefit of the project. What is his role on this project??
Respuesta
  • a. Senior Management
  • b. Project Management
  • c. Functional Management
  • d. Sponsor

Pregunta 6

Pregunta
A tailoring consideration related with resources management that would be done by the Project Manager is:
Respuesta
  • a. The provider of the raw materials
  • b. If the team resources will be full-time or part-time on the project
  • c. The data gathering tools that will use to identify stakeholders
  • d. The metrics that will be used to report quality

Pregunta 7

Pregunta
Kaizen and Just-In-Time (JIT) are examples of:
Respuesta
  • a. Staffing Management plan methods
  • b. Trends and practices in project resources management
  • c. Capabilities of the project team
  • d. Responsibility Assignment Matrix

Pregunta 8

Pregunta
The resources management plan:?
Respuesta
  • a. Must be created by the human resources department
  • b. Provides guidance on how project resources should be categorized, allocated, managed an released. Includes team an physical resources management.
  • c. Is a tool of team development management plan.
  • d. Is an output of the Manage Team process

Pregunta 9

Pregunta
A war room is an example of:
Respuesta
  • a. A way to develop a focus group
  • b. A type of interviews
  • c. A type of reports
  • d. Colocation

Pregunta 10

Pregunta
In which process, for a medical research project running in to two different regions, are the human resources assigned to their responsibilities?
Respuesta
  • a. Storming
  • b. Acquire Resources
  • c. Develop Team
  • d. Team charter development
Mostrar resumen completo Ocultar resumen completo

Similar

Creando una Ficha
Diego Santos
Examen Primer trimestre
jorgeluisparedes
Vocabulario Inglés - Tema 2
tanianicolasizqu
Fichas Verbos inglés presente, pasado y participio (131)
JOWANI BELLO MELO
Conditionals
martarodru99
Anatomía Humana
dorydan01
ANÁLISIS DE DATOS EN LA INVESTIGACIÓN CUALITATIVA
Johanna Morales Genecco
Didáctica de la expresión escrita
Estibalitz Etxaide
PRESENT SIMPLE 1
Silvia Francisco Llorente
PRESENT SIMPLE 2 MULTIPLE CHOICE
Silvia Francisco Llorente
Organizadores Gráficos
Eunice Sabaján