Pregunta 1

Pregunta
Crashing differs from fast tracking because crashing:
Respuesta
  • a. Usually increases value.
  • b. Usually increases the cost.
  • c. Usually saves more time
  • d. Usually saves more money.

Pregunta 2

Pregunta
Crashing in time management is:
Respuesta
  • a. A schedule compression technique includes reducing schedule activity durations and increasing the assignment of resources to schedule activities.
  • b. A schedule compression technique in which phases or activities that normally would be done in sequence are performed in parallel.
  • c. The timely input of data to calculate the critical path.
  • d. Equivalent to minimizing float.

Pregunta 3

Pregunta
Bar charts are useful in determining:?
Respuesta
  • a. The level of effort of an activity.
  • b. Activity start and end dates, as well as expected durations.
  • c. Availability of resources assigned to perform an activity.
  • d. Relative priority of activities.

Pregunta 4

Pregunta
An example of a “soft logic” dependency, is:?
Respuesta
  • a. Project A, the company’s participation in a Industry trade show, depends on the successful completion of Project B, which is building the prototype of the product that is going to be displayed.
  • b. To install the plumbing and electrical work at the same time family is living in a house.
  • c. Finished software before training program.
  • d. To schedule the final testing activity of a computer before the manual is finish.

Pregunta 5

Pregunta
Analogous duration estimating is:?
Respuesta
  • a. Bottom-up estimating.
  • b. Frequently used to estimate project duration when there is a limited amount of detailed information.
  • c. Similar to multiple duration estimating.
  • d. Deductive estimating.

Pregunta 6

Pregunta
All of the following are true about resource leveling EXCEPT:?
Respuesta
  • a. Can be used to keep selected resource usage at a constant level during specific time periods.
  • b. Offer results in a projected duration for the project that is longer than the preliminary project schedule.
  • c. Is sometimes called the resource-based method.
  • d. Is used to develop a meaningful WBS.

Pregunta 7

Pregunta
An organization uses a desktop scheduling software for project scheduling. What would this software be considered as??
Respuesta
  • a. Project management office.
  • b. Enterprise environmental factor.
  • c. Organizational process asset.
  • d. Integrated change control system.

Pregunta 8

Pregunta
All of the following choices represent inputs to the Estimate Activity Resources EXCEPT:?
Respuesta
  • a. Organizational process assets.
  • b. Activity cost estimates.
  • c. The actual final cost of the last project.
  • d. Risk register

Pregunta 9

Pregunta
As one of the tools and techniques of Sequence Activities, a lead:?
Respuesta
  • a. Directs a delay in the successor activity.
  • b. Could be accomplished by a finish-to-start relationship with a delay time.
  • c. Means the successor activity cannot start until after the predecessor is completed.
  • d. Allows an acceleration of the successor activity.

Pregunta 10

Pregunta
A schedule compression technique to determine how to obtain the greatest amount of compression for the least incremental cost is called:?
Respuesta
  • a. Crashing.
  • b. PERT.
  • c. Precedence Diagram Method - PDM.
  • d. Fast tracking.
Mostrar resumen completo Ocultar resumen completo

Similar

Mejores Sistemas Educativos del Mundo
Diego Santos
PROCESADORES DE TEXTO
rm-asociados
Ecuaciones diferenciales lineales de segundo orden
Juan Beltran
Independencia de los paises latinoamericanos
Estefani Tretto
Test Primera Guerra Mundial
juanmadj
Conceptos Generales De Robótica
Diego Santos
Homeostasis
Nicolas Veneri
MAPAS CONCEPTUALES DIGITALES
Ana Maria Orozco
Historia del Arte Universal
maya velasquez
EXAMENES UNAM
ROSA MARIA ARRIAGA
Fichas Evaluación de las actividades de la vida Diaria
ELSY DEL CARMEN QUEVEDO TEJERO