1

Resumen del Recurso

Pregunta 1

Pregunta
An essential auxillary in a gas turbine system is
Respuesta
  • regenerator
  • starting motor
  • intercooler
  • waste heat boiler
  • combustor

Pregunta 2

Pregunta
A gas turbine is started in the following sequence of operation 1. air is heated in the combustor 2. air is drawn into the compressor 3. exhaust gases expand through the turbine 4. air is exhausted to atmosphere or hrsg
Respuesta
  • 1,2,3,4
  • 2,1,3,4
  • 4,2,3,1
  • 2,4,1,3
  • 3,1,2,4

Pregunta 3

Pregunta
Air choking in the high pressure end of the compressor is also termed:
Respuesta
  • sputtering
  • back-firing
  • choking
  • surging
  • dead-heading

Pregunta 4

Pregunta
When starting a gas turbine in manual mode, what would be the first step
Respuesta
  • start the starting motor
  • engage the ignitors
  • load the power turbine
  • engage the turning gear
  • start the auxillary systems

Pregunta 5

Pregunta
Water washing and adding chemicals to fuels that contain sodium or vanadium is primarily for
Respuesta
  • reducing deposits on turbine blades
  • reduce blade erosion
  • lower exhaust gas temperatures
  • reduce turbine blade erosion
  • lower NOX emmisions

Pregunta 6

Pregunta
Major overhauls are performed on a gas turbine:
Respuesta
  • annualy
  • when performance is poor
  • monthly
  • according to the manufacturers specifications
  • during off-peak hours

Pregunta 7

Pregunta
Which of the following components will reduce noise pollution from a gas turbine system: 1. inlet silencers 2. exhaust silencers 3. acoustic insulation 3. using axial air compressors
Respuesta
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4

Pregunta 8

Pregunta
Which interlocks need to be in the start position to start a gas turbine 1. oil pressure normal 2. dampers and ducting open 3. controls circuits energized 4. governer in start position
Respuesta
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4

Pregunta 9

Pregunta
Minor servicing carried out on a gas turbine:
Respuesta
  • is done monthly
  • is done annualy
  • may only allow some adjusting to the combustor unit
  • will include power turbine blade replacement
  • will include compressor balancing and mechanical maintenance

Pregunta 10

Pregunta
when inspecting the flame tube of a gas turbine during a turnaround the operator should check for
Respuesta
  • distortion
  • proper ignition
  • air flow restrictions
  • scaling
  • corrosion salts

Pregunta 11

Pregunta
combustion unit inspections and maintenance includes 1. cleaning 2. ignition checks 3. adjusting fuel flows 4. igniters and retraction gear tested
Respuesta
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4

Pregunta 12

Pregunta
The lubrication system on a gas turbine for be checked for: 1. leaks 2. water 3. dirt 4. metal particles
Respuesta
  • 1,2
  • 2,3,4
  • 1,2,4
  • 1,2,3
  • 1,2,3,4
Mostrar resumen completo Ocultar resumen completo

Similar

¿Qué sabes de Roma antígua? - EDUpunto.com
EDUpunto Por: Ernesto De Frías
Test de historia de España S. XVIII, XIX y XX.
Diego Santos
Miembro Superior - Anatomía
Ivan Salas
Inglés Exani II - Verbos Irregulares
Gastón Amato
Algunos desafíos de la educación básica en el umbral de nuevo milenio César Coll
dayana.marisol13
Organizador Gráfico
r2p2casa
SOSTENIBILIDAD
Carlos Párraga
Introducción a los Derechos Humanos
Fernanda Tellechea
Roles en la educación inclusiva
Alejandro Villamizar
HINDUISMOA 6B_ANE
Ane Núñez Escudero