Pregunta 1

Pregunta
In a turbine circuit, feed heaters and dearators serve to:
Respuesta
  • use up excess steam
  • Increase efficiency
  • Provide load during low demand periods
  • Increase turbine output

Pregunta 2

Pregunta
The high-pressure oil system of a typical turbine supplies oil to
Respuesta
  • Bearings
  • Gears
  • Emergency stop valves
  • The oil purifier
  • The auxillary oil pump

Pregunta 3

Pregunta
When starting a condensing or extraction turbine, the extraction (condensate)pump is started ______ the _____ 1. before 2. after 3. air ejector 4. jacking oil pump 5. condenser circulating water pump
Respuesta
  • 1,3
  • 2,3
  • 1,4
  • 1,5
  • 2,5

Pregunta 4

Pregunta
When starting an extraction turbine, sealing steam to the turbine glands is admitted _____ is put in operation
Respuesta
  • Before the extraction pump
  • Before the condenser circulating water pump
  • After the air ejector
  • After the extraction pump
  • After the throttle valve is open

Pregunta 5

Pregunta
The jacking oil pump is shut down when the turbine reaches a speed of approximately _____ rpm
Respuesta
  • 5-10
  • 20-30
  • 40-50
  • 50-60
  • 0-80

Pregunta 6

Pregunta
The overspeed trip a turbine is usually set to trip the mechanism when it reaches ____ of operating speed
Respuesta
  • 100%
  • 105%
  • 110%
  • 115%
  • 120%

Pregunta 7

Pregunta
Lubricating oil for a turbine may: 1. Lubricate bearings 2. Lubricate gears. 3. Operate throttle valves. 4. Be supplied to a governor.
Respuesta
  • 1,2
  • 3,4
  • 1,2,3
  • 2,3,4
  • 1,2,3,4

Pregunta 8

Pregunta
When a hydraulic overspeed trip operates 1. High pressure oil forces the main steam valve shut. 2. High pressure oil supply is shut off 3. The stop valve oil cylinder drain is closed. 4. The stop valve oil cylinder drain is opened 5. A spring closes the main steam valve 6. The pilot drain is closed
Respuesta
  • 1,3,6
  • 2,4,5
  • 3,4,6
  • 2,4,6
  • 3,4,5

Pregunta 9

Pregunta
The warm up time required of a turbine is dependant on
Respuesta
  • How quickly the turbine is required
  • The manufacturers instructions
  • The size of the turbine
  • The type of turbine
  • Whether the steam is dry or wet

Pregunta 10

Pregunta
Overload governing is used on ______ turbines
Respuesta
  • Small
  • Impulse
  • Low pressure
  • Reaction
  • Impulse and Reaction
Mostrar resumen completo Ocultar resumen completo

Similar

Comunidades Autónomas de España y sus Capitales
maya velasquez
Animales y sus Características
Diego Santos
Matemáticasen la VidaCotidiana
Diego Santos
7 Claves para un Comentario de Texto de Selectividad de 10
Diego Santos
VOCALES. Diptongo o Hiato...
JL Cadenas
Marketing Digital
Diego Santos
Grupos funcionales (Bioquímica)
Nadim Bissar
Beneficios de la Planeación
sinadep.snte
GEOGRAFÍA MUNDIAL I...
Ulises Yo
¿COMO HACER UN CUADRO SINOPTICO?
luisa valentina castaño acuña
UNIDAD 1-2-3. CONSTRUCTOS TEORICOS DEL APRENDIZAJE - PARADIGMAS DEL APRENDIZAJE-PSICOLOGIA Y APRENDIZAJE
veronica marin herrera