Pregunta 1

Pregunta
Which of the following statements about contract termination is FALSE?
Respuesta
  • A Early terminations are handled in the Close Project or Phase process.
  • B Contract termination may result from mutual agreement to terminate the contract.
  • C Termination conditions should be documented in the contract.
  • D Contract termination may result from default of one party.

Pregunta 2

Pregunta
Which of these statements about contracts is FALSE?
Respuesta
  • A A contract is a mutually binding legal agreement.
  • B A contract can include change request handling.
  • C Contracts are used only for complex procurements.
  • D A contract is a legal relationship subject to remedy in the courts.

Pregunta 3

Pregunta
Greg needs a good understanding of planned work to determine project purchases. What document will be the most helpful?
Respuesta
  • A WBS
  • B WBS dictionary
  • C Project scope statement
  • D Procurement management plan

Pregunta 4

Pregunta
An independent estimate used when conducting procurements is sometimes used to:
Respuesta
  • A Establish a budget estimate.
  • B Serve as a benchmark of proposed responses.
  • C Build an order of magnitude estimate.
  • D Confuse prospective sellers.

Pregunta 5

Pregunta
Which of the following is an objective of the Control Procurements process?
Respuesta
  • A Set limitations of liability
  • B Assess and invoke penalties
  • C Monitor contract performance
  • D Issue individual performance reports

Pregunta 6

Pregunta
Which of the following statements about selecting a seller is TRUE?
Respuesta
  • A Project teams should select the lowest cost seller.
  • B The selection process should produce one seller for each product.
  • C Selection criteria can be limited to price if the item is available from multiple sellers.
  • D The project manager selects the sellers.

Pregunta 7

Pregunta
What is a structured review of the seller's progress to deliver project scope and quality, within cost and on schedule?
Respuesta
  • A Inspection
  • B Procurement performance review
  • C Walkthrough
  • D Audit

Pregunta 8

Pregunta
Which of the following terms indicates that the buyer will evaluate the response based on technical factors?
Respuesta
  • A Bid
  • B Quote
  • C Tender
  • D Proposal

Pregunta 9

Pregunta
Inputs to Conduct Procurements include all of the following EXCEPT:
Respuesta
  • A Make-or-buy decisions.
  • B Source selection criteria.
  • C Procurement documents.
  • D Selected sellers list.

Pregunta 10

Pregunta
The Project Procurement Management Knowledge Area includes all of the following processes EXCEPT:
Respuesta
  • A Plan Procurement Management.
  • B Control Procurements.
  • C Identify Risks.
  • D Conduct Procurements.

Pregunta 11

Pregunta
Outputs of the Conduct Procurements process do NOT include:
Respuesta
  • A Selected sellers.
  • B Qualified sellers.
  • C Agreements
  • D Resource calendar.

Pregunta 12

Pregunta
Where can Baird look to find a qualified sellers list?
Respuesta
  • A Yellow pages
  • B Project management plan
  • C Procurement management plan
  • D Organizational process assets

Pregunta 13

Pregunta
Which of the following is a TRUE statement?
Respuesta
  • A T&M contracts are for a fixed amount
  • B T&M contracts can be open-ended
  • C T&M contracts do not reimburse costs
  • D T&M contracts are unilateral

Pregunta 14

Pregunta
Which of the following is NOT an organizational process assets update associated with the Close Procurement process?
Respuesta
  • A Procurement management plan
  • B Procurement file as a complete set of indexed contract documentation including the closed contract
  • C Deliverable acceptance
  • D Lessons learned documentation

Pregunta 15

Pregunta
Which of the following is NOT usually included in a procurement document?
Respuesta
  • A Description of need
  • B Response instructions
  • C Price
  • D Preferred contract type

Pregunta 16

Pregunta
Company policy requires you to advertise contract needs in your local paper. How does this benefit your project?
Respuesta
  • A It can expand the list of potential sellers
  • B It speeds up the source selection process
  • C It makes it easier to contact vendors
  • D It is always a legal requirement

Pregunta 17

Pregunta
CPFF is the abbreviation for:
Respuesta
  • A Cost Plus Fixed Fund.
  • B Contract Plus Fixed Fee.
  • C Cost Plus Floating Fee.
  • D Cost Plus Fixed Fee.

Pregunta 18

Pregunta
Which of the following is NOT a tool or technique used with the Close Procurements process?
Respuesta
  • A Procurement audits
  • B Performance reporting
  • C Records management system
  • D Procurement negotiations

Pregunta 19

Pregunta
Your sponsor wants to know if your contractor has finished a set of deliverables. Where will you find that information?
Respuesta
  • A Procurement management plan
  • B Performance reports
  • C Approved change requests
  • D Contract

Pregunta 20

Pregunta
Which of the following is NOT an input to the Conduct Procurements process?
Respuesta
  • A Source selection criteria
  • B Seller proposals
  • C Procurement contract award
  • D Procurement documents
Mostrar resumen completo Ocultar resumen completo

Similar

Inglés - Verbos Compuestos I (Phrasal Verbs)
maya velasquez
Fórmulas Física
Diego Santos
tipos de herramientas
arturo.garrido_2
Biología Celular
maya velasquez
Fechas clave de la Historia de España
maya velasquez
Animales vertebrados: clasificación y características
Reyna Isabel Mayorga
Plantilla del Plan de Estudio de 5 Minutos
Diego Santos
PRESENT CONTINUOS
fapn
Tema 4, Los paisajes de España
Mercedes Graves
MÚSCULOS DE MIEMBRO INFERIOR
sarai palque santos
COSTAS E RÍOS
Nuria Prado Álvarez