Pregunta 1
Pregunta
Victor, the project manager, has several impulsive people on the project team and he knows that it will be important to establish clear expectations regarding acceptable behavior by project team members. A Develop Project Team tool or technique that he has decided to use is most likely:
A Ground rules.
B Interpersonal skills.
C Team building activities.
D Colocation.
Explanation:
Ground rules (Choice A) establish clear expectations regarding acceptable behavior by project team members. PMBOK® 9.3.2.4, pg 277
Pregunta 2
Pregunta
Which Project Management Process Group regularly measures progress and identifies variances from the project plan?
Pregunta 3
Pregunta
Lisa is the project manager for a new clothing line project. She has just learned that the workers at the sewing company her company usually contracts with have just gone on strike. She knows that, as a result, the only available sewing resources with another sewing company are extremely limited. Thankfully, Lisa and her manager have just decided to purchase a new project management software tool that will enable Lisa to manage her project with the latest technology. Lisa and her team should:
Respuesta
-
A Hire a consultant.
-
B Increase the duration of the project by 15% to account for the limited resources.
-
C Consider using the critical chain method of schedule network analysis.
-
D Fast track the project.
Pregunta 4
Pregunta
Sharon, the project manager, realizes her group of stakeholders is unable, at this early stage of the project, to define the scope more precisely. She tells the group, "Let's stop for now. We can come back to this later when we know more of the details." Sharon's decision is based on what project characteristic?
Pregunta 5
Pregunta
John decides to raise the grade level of the product of his project. He is affecting:
Pregunta 6
Pregunta
There is a new project at an automobile manufacturing company that requires input from many stakeholders in eight countries. Clearly, the project manager (Ananya) is going to require the support of these stakeholders. On top of that, if she doesn’t manage their expectations, the project will experience difficulties. Which of the following BEST addresses what Ananya will need to do?
Respuesta
-
A Communicate with the stakeholders constantly and consistently throughout the project life cycle; update the stakeholders on the status of all project changes
-
B Minimize resistance by recognizing stakeholders at monthly meetings; provide regular project status updates
-
C Communicate through email often, record issues and manage expectations so stakeholders will not be disappointed and then disrupt the project
-
D Have the stakeholders periodically review the list of project requirements to 1) make sure their expectations are included, and 2) minimize the number of change requests
Pregunta 7
Pregunta
A bar chart in which each bar represents a variable, and the height shows the frequency, is called a:
Respuesta
-
A Frequency chart.
-
B Control chart.
-
C Flowchart.
-
D Histogram.
Pregunta 8
Pregunta
Scott, one of your team members, needs to know when other team members will be in the office so he can schedule a meeting. What project document might help him?
Pregunta 9
Pregunta
Which of the following is NOT an objective of the Control Risks process?
Respuesta
-
A Determine if project assumptions are still valid
-
B Determine if analysis shows an assessed risk has changed or can be retired
-
C Determine if risk management policies are being followed
-
D Determine methods to eliminate all residual risks
Pregunta 10
Pregunta
When Gale left the company, Anna replaced her as project manager. The project deliverables include a system to track medical paperwork through the billing process. Anna is from the information technology department and is not familiar with some of the medical terminology used by her teams. Where should she look for definitions of these terms?
Pregunta 11
Pregunta
Which of the following statements about requested changes is true?
Respuesta
-
A They are processed for review and disposition through the Perform Integrated Change Control process
-
B They are an input to the Validate Scope process
-
C They are necessary to complete Validate Scope
-
D They are rarely used because the scope on every project remains relatively constant
Pregunta 12
Pregunta
Which of these statements related to the Conduct Procurements process is FALSE?
Respuesta
-
A Analytical techniques can help organizations identity the readiness of a vendor to provide the desired end state.
-
B On complex procurements, where source selection will be made based on seller responses to previously defined weighted criteria, a formal evaluation review process will be defined by the buyers procurement policies.
-
C Advertising in trade publications is a good place to start to build a list of potential sellers.
-
D Procurement negotiations conclude with a contract document that can be executed by both buyer and seller.
Pregunta 13
Pregunta
Which of the following is an input to the Direct and Manage Project Work process?
Respuesta
-
A Approved change requests
-
B Project management information system
-
C Work performance information
-
D Implemented preventive actions
Pregunta 14
Pregunta
A structured, independent review to determine whether project activities comply with organizational and project policies, processes and procedures is called a:
Respuesta
-
A Quality audit.
-
B Management review.
-
C Process analysis.
-
D Status meeting.
Pregunta 15
Pregunta
The development of requirements begins with an analysis of information contained in the:
Respuesta
-
A Project charter and stakeholder register.
-
B Project management plan and requirements traceability matrix.
-
C Project charter and organizational process assets.
-
D Project management plan and change requests.
Pregunta 16
Pregunta
Fran is a project manager who is validating her systems analyst's Define Scope work products. Which of the following work products should Fran expect to see?
Respuesta
-
A Project constraints, project objectives, and a prioritized list of risks
-
B Project exclusions and acceptance criteria
-
C Project boundaries, a project scope description and scope baseline
-
Project scope statement, project cost requirements and a project team list
Pregunta 17
Pregunta
You are ready to build a list of stakeholders for your project. Which of the following statements is FALSE?
Respuesta
-
A Customers and buyers must be considered
-
B Those positively impacted by the project need little attention
-
C The state transportation department is a stakeholder for the city that is planning concrete sidewalks along a local highway
-
D The head of the PMO who is always interfering with your project work and slowing things down will be a stakeholder on your list
Pregunta 18
Pregunta
By actively managing the contract and carefully wording the terms and conditions, what can be avoided?
Respuesta
-
A Schedule rework
-
B Spelling errors
-
C Project risks
-
D Change requests
Pregunta 19
Pregunta
In context of the Project Time Management Knowledge Area, which of the following processes would be the first to be executed?
A Estimate Activity Resources
B Sequence Activities
C Develop Schedule
D Estimate Activity Durations
Explanation:
The Sequence Activities process is the third of the seven processes that make up Project Time Management, but the first in the choices provided. PMBOK® 6, pg 143
Pregunta 20
Pregunta
Your team is working on a project to produce the next generation of cell phones. The marketing department contacts you to begin the advertising campaign. You know the technical risks are very high for this product. You should:
Respuesta
-
A Help design the campaign.
-
B Monitor risks closely and keep marketing informed.
-
C Ask marketing to wait until the risk is at an acceptable level.
-
D Tell your sponsor.
Pregunta 21
Pregunta
Estimates at completion (EAC) are typically based on an estimate to complete (ETC) the remaining work plus __________.
Respuesta
-
A Earned value (EV)
-
B Planned value (PV)
-
C Actual costs (AC)
-
D Cost variance (CV)
Pregunta 22
Pregunta
Decomposition is a technique used during Define Activities. It subdivides the project work packages into smaller, more manageable components called schedule __________.
Respuesta
-
A Deliverables
-
B Units
-
C Activities
-
D Milestones
Pregunta 23
Pregunta
A chart with points plotted for values of two potentially related variables is called a:
Respuesta
-
A Scatter diagram.
-
B Control chart.
-
C Flowchart.
-
D Histogram.
Pregunta 24
Pregunta
Which of the following is an example of an organizational process asset that may be an input to the project charter?
Pregunta 25
Pregunta
A group of unrelated projects that are grouped together to facilitate effective management to meet strategic business objectives could be called a __________.
Respuesta
-
A Project
-
B Portfolio
-
C Program
-
D Strategic plan
Pregunta 26
Pregunta
__________ is the realized cost incurred for the work performed on an activity during a specific time period.
Respuesta
-
A Planned value (PV)
-
B Actual cost (AC)
-
C Cost variance (CV)
-
D Earned value (EV)
Pregunta 27
Pregunta
What process must precede Manage Communications?
Respuesta
-
A Project Communications Management
-
B Control Communications
-
C Control Stakeholder Engagement
-
D Plan Communications Management
Pregunta 28
Pregunta
What is the unique and verifiable product, result or capability to perform a service that is identified in planning and must be produced to complete the project work?
Pregunta 29
Pregunta
Which Project Management Process Group defines and refines objectives, and plans the course of action required to attain the objectives?
Respuesta
-
A Planning
-
B Closing
-
C Initiating
-
D Executing
Pregunta 30
Pregunta
All of the following are inputs to the Identify Stakeholders process EXCEPT:
Pregunta 31
Pregunta
In a virtual team environment, __________ becomes increasingly important.
Respuesta
-
A Quality control
-
B Communication planning
-
C Cost planning
-
D Scope planning
Pregunta 32
Pregunta
During Plan Stakeholder Management, expert judgment can be obtained through all of the following EXCEPT:
Pregunta 33
Pregunta
All of the following can be updated as a result of Control Quality EXCEPT:
.
Pregunta 34
Pregunta
Jeanette developed the project's communications management plan as one of the first deliverables in her project. Now, six months into the project, it seems like there is a lot of confusion about who needs what information about the project. It has gotten to the point that Jeanette's new boss and her latest project sponsor act like they don't even understand the project. What do you think Jeanette could have done differently?
.
Respuesta
-
A Organizational changes should have been anticipated and logged in the risk register.
-
B Jeanette should have stopped the project when the sponsor changed, in order to give the new sponsor a chance to learn about the project.
-
C The communications management plan should have been reviewed regularly throughout the project and revised as needed to ensure it is still useful
-
D Jeanette should have re-planned the project.
Pregunta 35
Pregunta
Triangular distribution and beta distribution are two formulas used with :
Respuesta
-
A Parametric estimating.
-
B Analogous estimating.
-
C Three-point estimates.
-
D Bottom-up estimating.
Pregunta 36
Pregunta
As the project manager of one of your team members, you inadvertently overhear a discussion in the lunch room between her and her boss. They are having a discussion about your team member's performance. You are shocked to hear that the manager suggests to her that her performance assessment would improve if she would consider updating her wardrobe to more trendy, snugger fitting clothes. What should you do?
Respuesta
-
A You should do nothing. He was probably joking and didn't really mean it.
-
B You should call the manager afterwards to express your disappointment in his behavior.
-
C You should immediately report the incident to a human resources representative and to the manager's manager.
-
D You should pretend you didn't hear the conversation, as you were not supposed to overhear that discussion.
Pregunta 37
Pregunta
Most often, a format to document team member roles and responsibilities falls into these types EXCEPT:
Respuesta
-
A Text-oriented.
-
B Matrix.
-
C Hierarchical.
-
D Three dimensional.
Pregunta 38
Pregunta
An __________ is the expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.
Pregunta 39
Pregunta
Sanjay, the project manager for a new "green" product development effort, is unable to complete a detailed decomposition since a major product component will not be fully designed for another year. Given this, he decides it is best to use:
Respuesta
-
A Critical path method.
-
B Contingency planning.
-
C Rolling wave planning.
-
D Idea/Mind mapping.
Pregunta 40
Pregunta
All of the following are processes involved in Project Time Management EXCEPT:
Pregunta 41
Pregunta
One of your fellow project managers won a trip around the world. You agreed to move her project forward while she was gone. Her notes direct you to start assembling the team for a Define Activities session. In an email to the team, you describe the meeting as:
Respuesta
-
A Identifying the specific actions to be performed to produce the project deliverables.
-
B Identifying all of the deliverables required to complete the project.
-
C Identifying and documenting dependencies among schedule activities.
-
D Estimating the number of work periods that will be needed to complete the individual schedule activities.
Pregunta 42
Pregunta
An intentional activity to modify a nonconforming product or product component is the definition for which output of the Direct and Manage Project Work process?
Respuesta
-
A Implemented change requests
-
B implemented preventive actions
-
C Change requests covering defect repair
-
D Implemented corrective actions
Pregunta 43
Pregunta
A project team is beginning to identify risks for the project. The customer declines the invitation to the risk identification session. He says talking about risk is planning to fail. The project manager should:
Pregunta 44
Pregunta
__________ includes managing communications to satisfy the needs of, and resolve issues with, project stakeholders.
Pregunta 45
Pregunta
Which of the following is an input to Develop Schedule?
Pregunta 46
Pregunta
During a bidder conference, the project manager's role is:
.
Pregunta 47
Pregunta
Which of the following enterprise environmental factors should Sam focus on when planning stakeholder management?
Respuesta
-
A Organizational culture
-
B Local politics
-
C Relationships
-
D Interpersonal skills
Pregunta 48
Pregunta
__________ is the process of tracking identified risks, monitoring residual risks, identifying new risks, executing risk register plans, and evaluating their effectiveness during the project life cycle.
Pregunta 49
Pregunta
Question 50 of 100 (Scope) Go to Question:
An output of Collect Requirements is:
Respuesta
-
A Work breakdown structure.
-
B Project management plan.
-
C Project scope statement.
-
D Requirements traceability matrix.
Pregunta 50
Pregunta
The project manager's authority is moderate to high in a __________ organization.
Respuesta
-
A Functional
-
B Projectized
-
C Strong matrix
-
D Balanced matrix
Pregunta 51
Pregunta
All of the following are tools or techniques for Control Costs EXCEPT:
Respuesta
-
A Funding limit reconciliation.
-
B To-complete performance index.
-
C Earned value management.
-
D Performance reviews.
Pregunta 52
Pregunta
Stacy needs to develop a communications management plan for her project. Which of the following is a tool or technique that will help her with that task?
Respuesta
-
A Communications management plan
-
B Communications requirements analysis
-
C Project scope statement
-
D Work performance reports
Pregunta 53
Pregunta
The risk of failing to achieve a project's objectives is greatest __________.
Respuesta
-
A At the start of the project
-
B In the middle of the project
-
C Near the end of the project
-
D After the project is completed
Pregunta 54
Pregunta
Which of the following statements is TRUE?
Respuesta
-
A Organizations should fund 100% of the project budget at initiation.
-
B Funding usually occurs at the end of the project.
-
C Funding usually occurs in incremental amounts during the life of the project.
-
D Management reserves are the responsibility of the project manager.
Pregunta 55
Pregunta
You have 232 stakeholders on your project. You also have a lot of project information that changes on a daily basis. It just so happens that you have access to a company website. What communication method will support you the best in terms of making your information available to the masses?
Pregunta 56
Pregunta
All of the following are outputs of the Control Stakeholder Engagement process EXCEPT:
Pregunta 57
Pregunta
Tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance are all a part of:
Respuesta
-
A Control Quality.
-
B Develop Project Team.
-
C Acquire Project Team.
-
D Manage Project Team.
Pregunta 58
Pregunta
Root cause analysis is used with:
Respuesta
-
A Control charts.
-
B Quality audits.
-
C Process analysis.
-
D Botanical projects.
Pregunta 59
Pregunta
Your colleague insists that working with stakeholders is easy. You have worked on many projects during your career, and know differently based on experience. One of the practices you use to help you effectively manage stakeholders is to classify them. You decide to use the salience model. Which of the answer choices lists stakeholder groupings you are likely to be using?
Respuesta
-
A Power, influence
-
B Influence, impact
-
C Power, legitimacy, urgency
-
D Keep satisfied, manage closely, monitor, keep informed
Pregunta 60
Pregunta
The quality management plan relates to the Plan Quality Management process in what way?
Pregunta 61
Pregunta
When the Control Communications process identifies changes, what process will be triggered?
Respuesta
-
A Plan Communications Management
-
B Perform Integrated Change Control
-
C Control Quality
-
D Project Scope Management
Pregunta 62
Pregunta
Andre's project team has finished their last major deliverable and the customer has accepted it. His team consisted of five local employees and fifteen contract team members. What is the next logical process?
Respuesta
-
A Control Procurements
-
B Close Procurements
-
C Conduct Procurements
-
D Close Project or Phase
Pregunta 63
Pregunta
You have been assigned as the project manager for the parking lot resurfacing at a very prestigious, top quality health facility in Arizona. The project is moving along better than expected and you are feeling quite confident that you will be finished 2 days ahead of schedule. During your daily morning walk-over of the completed work, you notice that in one area, the concrete appears to be "popping" leaving what looks like little pock marks on the surface. You immediately suspect that there is a defect in the concrete that was used in that section. Which organizational process asset would you reference first to help you determine your BEST course of action?
Respuesta
-
A Project files from prior projects
-
B Issue and defect management database
-
C Communication requirements
-
D Process measurement database
Pregunta 64
Pregunta
The process of obtaining the human resources needed to complete the project is:
.
Pregunta 65
Pregunta
__________ provide documentation about current project status compared to project forecasts.
Respuesta
-
A Work performance reports
-
B Project organization charts
-
C Project staff assignments
-
D Individual performance assessments
Pregunta 66
Pregunta
Comparing the cost of quality management activities against the cost of likely rework is called __________.
Respuesta
-
A Benchmarking
-
B Design of Experiments
-
C Cost of quality (COQ)
-
D Cost-benefit analysis
Pregunta 67
Pregunta
A cost management plan may contain:
Respuesta
-
A Control thresholds, reporting formats, and units of measure.
-
B Level of accuracy, organizational procedure links, and cost forecasts.
-
C Rules of performance measurement, control thresholds, and reserve analysis.
-
D Units of measure, process descriptions, and activity cost estimates.
Pregunta 68
Pregunta
EV/AC is the formula for:
).
Respuesta
-
A Cost performance index (CPI).
-
B Schedule variance (SV).
-
C Cost variance (CV).
-
D Schedule performance index (SPI
Pregunta 69
Pregunta
You are the project manager for a project that is co-developing a product with another company. You know that if you add a feature to the product of your project, the stock price of your client has a very high probability of rising. With this information, you suggest to your team to consider adding the feature. In addition, you are thinking about purchasing some of the stock. Should you buy the stock?
Respuesta
-
A No, because you don't work for that company
-
B No, because buying the stock would represent a conflict of interest, and could possibly be considered Insider Trading
-
C Yes, because it is a great opportunity
-
D Yes, because no one has to know
Pregunta 70
Pregunta
Jose's company has just won three contracts to install and configure its best-selling software system at three new client sites. Jose decides that he can manage the three project teams, at separate sites, concurrently. If he does, is Jose deviating from the PMBOK®?
Respuesta
-
A No, because he can manage all three at once.
-
B Yes, because the endeavors are not projects since they are not unique.
-
C Yes. He is making a big mistake trying to manage three projects at once.
-
D No, because his software is best-selling, so the clients will want the systems sooner.
Pregunta 71
Pregunta
Those processes required to establish the scope of the project are part of the:
.
Respuesta
-
A Executing Process Group
-
B Initiating Process Group.
-
C Planning Process Group.
-
D Monitoring and Controlling Process Group.
Pregunta 72
Pregunta
Chen has a set of very complex proposals to evaluate. His project needs a contracted real-time inventory management solution. What is his next BEST action?
Pregunta 73
Pregunta
Work performance data is an important Control Risks input. Which of the following will you NOT find in work performance data?
Pregunta 74
Pregunta
While preparing your status report, you discover that a task has an SPI value of 0.75. You realize that the task was underestimated and needs more resources. What should you prepare?
Pregunta 75
Pregunta
Your team has planned their risk management approach, identified 50 risks and prioritized them. What is the BEST next step?
Respuesta
-
A Perform qualitative analysis to rank risks
-
B Prepare risk responses
-
C Write a risk management plan
-
D Perform Quantitative Risk Analysis to determine risk impacts
Pregunta 76
Pregunta
Fred has been asked by Nancy, the project's executive sponsor, to obtain the project stakeholders' formal acceptance of the completed project scope and associated deliverables. Fred has arranged a session to review which of the following with the stakeholders?
Pregunta 77
Pregunta
You have been assigned as the project manager of a project that will deliver templates and procedures for the development of a manufacturing process used by an external customer. Which of the following would be an input to developing the project charter?
Pregunta 78
Pregunta
Why is it important to document requested contract changes?
Respuesta
-
A To establish a record of non-compliance
-
B To maintain project records
-
C To update the contract
-
D Change requests can lead to a contract dispute
Pregunta 79
Pregunta
Bill is a project manager for a construction design project. He and his team have completed the project's schedule network diagram and are currently determining which resources are needed for the project. Bill has learned that his stakeholders would like to incorporate a new material that the manufacturing department has invented for the foundation. He checks his budget and sees that he cannot afford to send any of his design team members to training or to hire an outside consultant. Bill's BEST option is to:
.
Respuesta
-
A Tell the stakeholders that the new material cannot be used unless the budget is increased
-
B Identify a person from manufacturing who has knowledge about the new material, and add her to the project team.
-
C Add a 20% buffer to the schedule to account for the additional risk.
-
D Use a more inexpensive material for the windows.
Pregunta 80
Pregunta
You are managing a large multinational project. Most of the team members live in a country that observes siesta in the early afternoon. That time of day equates to early morning for your time zone. When do you plan status conference calls?
Respuesta
-
A Early morning, your time
-
B Early afternoon, their time
-
C Later afternoon, their time
-
D Alternate early morning your time and early afternoon their time
Pregunta 81
Pregunta
What is the aspect of project management that includes collecting, measuring, and distributing performance information, and assessing measurements and trends to effect process improvements?
Respuesta
-
A Performance collecting
-
B Monitoring
-
C Process assessment
-
D Project planning
Pregunta 82
Pregunta
Peter has collected a list of resolved issues regarding one of the vendors. This list of resolved issues was sent to the project sponsor as directed by the communication plan. What was Peter doing?
Respuesta
-
A Change management
-
B Project Risk Management
-
C Project Procurement Management
-
D The Control Communications process
Pregunta 83
Pregunta
Which of the following addresses typical cost and staffing levels of the generic life cycle structure?
.
.
Respuesta
-
A Cost and staffing levels are high during planning and execution, and start to taper off when project documents are archived.
-
B Cost and staffing levels steadily rise throughout project initiation and planning, and plateau during execution and closing
-
C Cost and staffing levels steadily rise throughout project execution, and then drop quickly after deliverables are accepted
-
D Cost and staffing levels steadily rise through project initiation and organizing and preparing, plateau during execution, and then drop quickly after deliverables are accepted.
Pregunta 84
Pregunta
Before considering the project closed, which activity is performed by the project manager to ensure the objectives have been met?
Respuesta
-
A Comparison of project costs against the project management plan
-
B Comparison of customer acceptance documentation against change requests
-
C Review of the scope baseline to ensure completion
-
D Comparison of the project management plan baseline against the project management plan
Pregunta 85
Pregunta
Your internal customer wants the best website possible in order to attract the most customers. Your sponsor insists on using internal resources (who have never developed web pages) to save money. What is the BEST thing for you to do?
Pregunta 86
Pregunta
A portion of the project scope that will be included in a contract is a:
.
Pregunta 87
Pregunta
Your company has issued a request for proposal (RFP) for a project, and your husband's company has responded to the bid.
Respuesta
-
A Tell your management about the relationship.
-
B Inform management about the relationship and excuse yourself from the vendor selection activities.
-
C Provide information to the selection team.
-
D Inform PMI®.
Pregunta 88
Pregunta
Outputs of the Acquire Project Team process include:
Respuesta
-
A Human resource management plan, enterprise environmental factors and organizational process assets.
-
B Pre-assignment, negotiation, acquisition and virtual teams.
-
C Roles and responsibilities, project organization charts and staffing management plan.
-
D Project staff assignments, resource calendars and project management plan updates.
Pregunta 89
Pregunta
Why is Project Procurement Management necessary?
Pregunta 90
Pregunta
An output of Control Scope is:
Pregunta 91
Pregunta
Project cost control searches out causes of __________ variances.
Respuesta
-
A Positive
-
B Positive and negative
-
C Negative
-
D Earned value (EV)
Pregunta 92
Pregunta
Which of the following statements about Control Scope is false?
Respuesta
-
A Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline
-
B Control Scope assures all requested changes and recommended corrective actions are processed through the Perform Integrated Change Control process
-
C The Control Scope process is rarely needed, because changes are fairly uncommon
-
D Control Scope is used to manage the actual changes when they occur
Pregunta 93
Pregunta
You are a senior project manager, who is responsible for mentoring a new project manager. You are both present in a project team meeting when one of the team members becomes frustrated. You approach the team member after the meeting and ask if there is any support that you can provide. The team member informs you that he is concerned about the level of trust other team members have with the project's third party partner. Later, in a one-on-one meeting with the new project manager, you inform her of the interaction, and ask her if she believes this is important to address. Her proper response would be:
Respuesta
-
A It is important to ensure that everyone on the team does not feel intimidated.
-
B It is not important, because the team will likely not need to work with the third party partner ever again.
-
C It is important to improve feelings of trust and agreement among team members in order to raise morale, lower conflict, and increase teamwork.
-
D It is not important, because the team members will get the work done regardless of how they feel.
Pregunta 94
Pregunta
During negotiations, your contract administrator tells a salesperson that they are stupid because they come from a rural part of the world. You should first:
Pregunta 95
Pregunta
One of your team members is responsible for updating the earned value analysis report. You notice that the SPI for a task is always greater than 1.0, even though the delivery date keeps slipping. What should you do?
Pregunta 96
Pregunta
You are halfway through phase one of a multiphase project. Your SPI is 1.03 and your CPI is 0.87. Your sponsor suggests that you review the current risk register with your primary stakeholders, as the nature of the risks may have changed. You remember seeing a description of this technique in the PMBOK® Guide. What was the technique called?
Pregunta 97
Pregunta
Andy takes his project notebook to every project meeting. This is an example of a/an:
Pregunta 98
Pregunta
Your PMO buys software that will simulate project execution by computing duration and cost many times, varying the outcomes using statistics. What technique does this software employ?
Respuesta
-
A Monte Carlo analysis
-
B Taguchi analysis
-
C Network analysis
-
D Gantt analysis
Pregunta 99
Pregunta
A diagram used to identify causes of risks is called a/an:
.
Respuesta
-
A Ishikawa diagram.
-
B Taguchi diagram.
-
C Gantt diagram.
-
D Fishbowl diagram