PMP 03 - 80 Questões

Descripción

150 questoees
Cássio Olaia
Test por Cássio Olaia, actualizado hace más de 1 año
Cássio Olaia
Creado por Cássio Olaia hace alrededor de 8 años
349
0

Resumen del Recurso

Pregunta 1

Pregunta
QUESTION 17( EXAME 3) You are a consulting project manager with over 15 years experience running software development projects. You have been engaged to manage a finance application project for a new customer. However on the first day onsite at the customer's headquarters you are told the project has been cancelled, but there is a need for a project manager to manage a major infrastructure project to deploy a large number of servers and storage devices. The customer asks if you would be interested in leading this project. You have never managed this type of project before but would be interested in the challenge. Which of the follow is the best response?
Respuesta
  • A. Do not mention your lack of experience, but ask for more information about the project. After reviewing the information and see that you could probably wing the project, accept the project.
  • B. Accept the job with the caveat you can bring in any needed resources to work on the project, then hire a project manager you know that works in this area to handle the implementation details.
  • C. Decline the opportunity, citing your lack of experience and knowledge in this area. .
  • D. Do not mention your lack of experience and accept the job

Pregunta 2

Pregunta
QUESTION 18 A Project manager estimates the work to be accomplished in the near term in detail, at a low level of the Work Breakdown structure (WBS); while he estimates work far in the future as WBS components, that are at a relatively high level of the WBS. What is this technique called?
Respuesta
  • A. Decomposition
  • B. Rolling wave planning
  • C. Scope Creep
  • D. Earned value planning

Pregunta 3

Pregunta
QUESTION 19 Negative risks can either be ______, transferred, or mitigated as a countermeasure.
Respuesta
  • A. enhanced
  • B. avoided
  • C. exploited
  • D. ignored

Pregunta 4

Pregunta
QUESTION 20 The WBS represents all product and project work. The total work at the lowest levels should roll up to the higher levels so that nothing is left out and no extra work is performed. This is also called as: e
Respuesta
  • A. 100% rul
  • B. 80/20 rule
  • C. Pareto's rule
  • D. Ground rule

Pregunta 5

Pregunta
QUESTAO 21 You are at work related social event and a colleague tells you another project manager has just hired her niece's engineering firm for a city public improvement project that you are managing. You know that this company's proposal did not meet the pre-defined selection criteria to be considered for award. What do you do?
Respuesta
  • A. File a complaint with PMI.
  • B. Escalate the issue to the appropriate management.
  • C. Ask the project manager about what you have just heard. If your suspicions are confirmed, escalate the issue to the appropriate management.
  • D. Do nothing.

Pregunta 6

Pregunta
QUESTAO 22: A project manager is just finishing a project that has not gone well. Apart from cost overruns and schedule overruns, there have been a lot of quality defects and the project required a lot of senior management intervention to finally reach completion. The project manager should now:
Respuesta
  • A. Focus on closing the project and moving on to the next one. Lessons learned is not applicable to this project since it has done badly
  • B. Focus on presenting the data in positive light while ensuring that the reasons for the delays and problems are appropriately documented.
  • C. Mask bad data and only present good data since his performance appraisal will otherwise be impacted.
  • D. Document lessons learned from the project and update the lessons learned knowledge database.

Pregunta 7

Pregunta
QUESTAO 23: In a matrix organization, where the team members report to both, a functional manager as well as a project manager, generally, whose responsibility is it to manage the dual reporting relationship?
Respuesta
  • A. Functional manager
  • B. HR manager
  • C. Team members
  • D. Project Manager

Pregunta 8

Pregunta
QUESTAO 24: A Resource Breakdown Structure (RBS) would be used to breakdown the project by type of resources. The RBS is an example of a:
Respuesta
  • A. Linear chart
  • B. Matrix chart
  • C. Flow chart
  • D. Hierarchical chart

Pregunta 9

Pregunta
QUESTAO 25: While managing a project, you decide to prepare an email for the project stakeholders describing the current project status. This is best described as an example of:
Respuesta
  • A. Vertical communication
  • B. Nonverbal communication
  • C. Informal communication
  • D. Formal communication

Pregunta 10

Pregunta
QUESTAO 26: QUESTION 26 Analogous Estimating is an estimation technique that use the values of parameters such as scope, cost, budget and duration from a previous similar activity as the basis of activity and is frequently used to estimate when there is a limited amount of information about the project. This is a form of:
Respuesta
  • A. Gross value estimation
  • B. Function point estimation
  • C. Fixed point estimation
  • D. Precision Estimation

Pregunta 11

Pregunta
QUESTÃO 27: During the execution of your project, you decide that you would like to have charts of your project status - cost and schedule, display certain key project data, and hold your project meetings in a specific conference room. Such a place would be called:
Respuesta
  • A. Armageddon
  • B. War room
  • C. Battlefield
  • D. Ground zero

Pregunta 12

Pregunta
QUESTAO 28: The document that formally authorizes a project is the:
Respuesta
  • A. Project SOW
  • B. Project Plan
  • C. Project Charter
  • D. Project Scope Statement

Pregunta 13

Pregunta
QUESTAO 29: You are managing a medium sized construction project, and are reviewing some invoices from the electrical contractor. You see that materials not required for your project have been included on the invoice. After making a few phone calls it becomes clear that one of your project resources asked one of the vendor's staff to add a few extra circuits to one part of the building. This change was never approved through the change management process. What do you do?
Respuesta
  • A. Notify the manager of your project resource that he failed to follow proper processes. .
  • B. Refuse to pay the charges
  • C. Call a team meeting to determine how this will impact the project, then inform stakeholders of the impacts.
  • D. Immediately inform the project stakeholders of the unauthorized scope change. Then call a team meeting to determine the impact to the project.

Pregunta 14

Pregunta
QUESTAO 30: You are presented with a situation in a project where you need to measure the performance of the project. Which of these techniques would suit your requirement? A. Learned Value Technique
Respuesta
  • A. Learned Value Technique
  • B. Earned Value Technique
  • C. Analogous Estimating
  • D. Expert Judgment

Pregunta 15

Pregunta
QUESTAO 31: A manager asks you to evaluate four new projects that he has suggested for next year. You review the projects and notice that one is not really a project, but more an operational task. Which of these is not a project?
Respuesta
  • A. Change the product to enable increased consumer usage
  • B. Manage a set of people for the next year to deliver the desired productivity results
  • C. Respond to a customer request for different product packaging
  • D. Resolve a space constraint issue by building a new addition to the plant

Pregunta 16

Pregunta
QUESTAO 32: Which of the following Project Scope Management processes documents a configuration management system?
Respuesta
  • A. Control Scope
  • B. Define Scope
  • C. Verify Scope
  • D. Plan Scope Management

Pregunta 17

Pregunta
QUESTAO 33: The stakeholders of a project typically have:
Respuesta
  • A. Positive objectives
  • B. Negative objectives
  • C. Conflicting objectives
  • D. Similar objectives

Pregunta 18

Pregunta
QUESTAO 34: A project was estimated to cost $ 200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly delayed. This was however made up by receiving the first batch of materials for the project by air. The net result was that there was some additional cost in the project. At the end of the second month, the Project Manager reviews the project and finds that the project is 20% complete and Actual Costs are $ 50,000. The Estimate to complete (ETC) for the project would now be:
Respuesta
  • A. $160,000
  • B. $210,000
  • C. $250,000
  • D. $200,000

Pregunta 19

Pregunta
QUESTAO 35: You have a team of engineers working on your project. Two of the engineers have frequent disagreements. You ask them to resolve their differences through a discussion. However, that does not yield any results. Subsequently, you get involved and based on an analysis of the situation, suggest some changes in the way they work with each other. This still does not yield results and you find that the project schedule is beginning to suffer. What is you next course of action?
Respuesta
  • A. Take Disciplinary action, if required, since the needs of the project are not being met.
  • B. Don't do anything. Differences of opinion amongst the team members is a healthy situation
  • C. Speak to the two team members and ask them to resolve their conflict amicably.
  • D. Ensure that they work in different shifts so that they don't clash with each other.

Pregunta 20

Pregunta
QUESTAO 37:While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?
Respuesta
  • A. Start-to-Finish
  • B. Start-to-Start
  • C. Finish-to-Start
  • D. Finish-to-Finish

Pregunta 21

Pregunta
Which of the following is not a tool and technique of the Collect Requirements process?
Respuesta
  • A. Group creativity techniques
  • B. Interviews
  • C. Questionnaires
  • D. Traceability matrix

Pregunta 22

Pregunta
You are planning out the communications methods to use as part of stakeholder management. The most effective means for communicating and resolving issues with stakeholders is:
Respuesta
  • A. Status reports.
  • B. Electronic mail.
  • C. Telephone calls.
  • D. Face-to-face meetings

Pregunta 23

Pregunta
A project manager wishes to illustrate the connections between the work that needs to be done and the project team members. According to the PMBOK, the resulting document would be called: A. Responsibility Assignment Matrix (RAM)
Respuesta
  • A. Responsibility Assignment Matrix (RAM)
  • B. Resource Planning Chart (RPC)
  • C. Task Assignment Model (TAM)
  • D. Resource Assignment (RAC)

Pregunta 24

Pregunta
Which of the following contains an extensive procurement changes approval process?
Respuesta
  • A. Scope statement
  • B. Test plan
  • C. Requirements management plan
  • D. Contract change control system

Pregunta 25

Pregunta
A project manager found that some of the project work was not done at the right time and was done in an improper sequence. What do you think was the likely issue?
Respuesta
  • A. This is a project communications breakdown. The project manager needs to re-develop the communication management plan
  • B. The Project Scope document was not properly updated.
  • C. The Work Authorization System was not properly established in the project.
  • D. This is due to poor teamwork.

Pregunta 26

Pregunta
A contract change control system should include:
Respuesta
  • A. Vendor contact information, tracking systems, and approval levels necessary for authorizing changes
  • B. Paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changes
  • C. Information database, dispute resolution procedures, and approval levels necessary for authorizing changes
  • D. Tracking systems, legal ramifications for certain actions, and approval levels necessary for authorizing changes

Pregunta 27

Pregunta
PMP Lite Mock Exam 4 QUESTION 1 Your project is slightly behind schedule, and you have not yet made a full impact assessment to make associated project changes to accommodate it. The weekly project status meeting is this afternoon, and because of your conference call schedule this morning you will not be able to complete the assessment to report to in the meeting. However, this is only a minor delay and you do not want anyone to worry unnecessarily. What is the best response? .
Respuesta
  • A. Use contingency reserves to compensate for the delay and report that progress is as planned
  • B. Report the actual status of the project in the meeting, and assure the project team that additional updates will be coming soon.
  • C. Inform the project team the progress is slightly behind schedule, and use the contingency reserves to cover the delay.
  • D. Say nothing about the delay at this time, and report that there are no major issues.

Pregunta 28

Pregunta
You are involved as project manager in a fairly large-sized project. You are in the process of making a procurement decision and plan to go with a simple purchase order. However, you are doubtful whether this is the correct thing to do and decide to find out more details about the process to be followed. Based on your findings, which of the following would be correct?
Respuesta
  • A. A simple purchase order is not appropriate for project. The project manager should always use the Request for Proposal (RFP) route.
  • B. Organizational process assets are guidelines available to the project. As project manager you have the final decision making authority and can decide whether to go in for a simple purchase order or not.
  • C. The value of the project is immaterial. As project manager, you have the final decision making authority to go in for a simple purchase order as long as you are contracting with an approved vendor
  • D. You would need to verify the policy constraints that form part of the Organizational process assets. Many organizations have policies that constrain procurement decisions and require use of a longer form of contract for projects above a certain value.

Pregunta 29

Pregunta
Robert is currently identifying his project stakeholders. Which of the following is the key input to this process?
Respuesta
  • A. Project charter
  • B. Cost management plan
  • C. Scope management plan
  • D. Stakeholder register

Pregunta 30

Pregunta
A control chart is used to determine whether or not a process is stable or has predictable performance. When a process is within acceptable limits, the process need not be adjusted. What are the upper and lower control limits usually set as?
Respuesta
  • A. + / - 3 sigma
  • B. + / - 6 sigma
  • C. + / - 2 sigma
  • D. + / - 1 sigma

Pregunta 31

Pregunta
Robert is currently identifying his project stakeholders. Which of the following is the key input to this process?
Respuesta
  • A. Project charter
  • B. Cost management plan
  • C. Scope management plan
  • D. Stakeholder register

Pregunta 32

Pregunta
The Cost Management Plan is an output of the Plan Cost Management process. This plan is then integrated with other project plans in which of these processes?
Respuesta
  • A. Develop Project Management Plan
  • B. Monitor and Control Project Work
  • C. Perform Integrated Change Control
  • D. Direct and Manage Project Work

Pregunta 33

Pregunta
The three categories into which contracts can be broadly classified are:
Respuesta
  • A. Cost-Reimbursable, Time and Material, Cost plus fixed fee
  • B. Fixed Price, Cost-Reimbursable and Lump Sum
  • C. Fixed Price, Cost-Reimbursable, Time and material.
  • D. Fixed Price, Time and Material, Lump Sum

Pregunta 34

Pregunta
For any complex project, once the project stakeholders are identified, the next step is to classify these stakeholders based on their current and desired engagement levels. What is the benefit of classifying the project stakeholders?
Respuesta
  • A. To help identify the project scope
  • B. To help populate the stakeholder register
  • C. To help define an approach strategy
  • D. It is a mandatory step in stakeholder analysis

Pregunta 35

Pregunta
A ______ is a collection of projects or programs grouped together for strategic business needs.
Respuesta
  • A. Portfolio
  • B. Management System
  • C. Enterprise
  • D. Array

Pregunta 36

Pregunta
In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity 5 days before its predecessor is complete. This is accomplished by providing 5 days of:
Respuesta
  • A. Lag
  • B. Load
  • C. Fast-tracking
  • D. Lead

Pregunta 37

Pregunta
While managing a project, you decide to contract to an external enterprise. You enter into a contract where you pay the external enterprise a set amount (as defined by the contract), irrespective of the seller's costs. What would best describe this type of contract?
Respuesta
  • A. FP-EPA
  • B. FFP
  • C. FPIF
  • D. CPFF

Pregunta 38

Pregunta
Which of the following inaccurately describes a prototype?
Respuesta
  • A. A prototype is tangible and allows stakeholders to fine-tune their expectations.
  • B. Requirements from a prototype are usually insufficient to move to the design phase.
  • C. Prototypes support the concept of progressive elaboration.
  • D. A prototype is a working model of the expected product.

Pregunta 39

Pregunta
Susan is the project manager for a dam construction project. All project communications are recorded and documented for future reference. It has been decided that the project team will maintain last three months of project communication records at any given point in time. It has also been decided that the older communication records will be archived on a monthly basis. Where these records must be archived?
Respuesta
  • A. Change log
  • B. Organizational process assets
  • C. Enterprise environmental factors
  • D. Issue log

Pregunta 40

Pregunta
Which of these is not an information gathering technique used in the Identify Risks process?
Respuesta
  • A. Interviewing
  • B. Root cause analysis
  • C. Brainstorming
  • D. Delta technique

Pregunta 41

Pregunta
QUESTION 15 Which of the following is accurate regarding Project Integration Management?
Respuesta
  • A. Project deliverables are not part of Integration Management
  • B. It involves the integration of process groups and not individual processes
  • C. The need for it becomes evident in situations where individual processes interact
  • D. It involves disregarding trade-offs and focuses on clearly articulating how accomplish all requirements by the deadline

Pregunta 42

Pregunta
Which of the following is NOT a tool or technique of the Acquire Project Team process?
Respuesta
  • A. Negotiation
  • B. Multi-criteria decision analysis
  • C. Pre-assignment
  • D. Conflict management

Pregunta 43

Pregunta
A company you worked for several years ago is bidding on a project your new company will be starting in approximately 6 months. You have been selected to manage the project, and will be participating in the vendor selection processes. What should you do?
Respuesta
  • A. Notify the stakeholders of your status and excuse yourself from the vendor selection process.
  • B. Provide the vendor selection committee with as much detail as you can remember about your former company so that the best decision can be reached.
  • C. Notify the project stakeholders of your status as a former employee of the bidding company, and comply with their preferences for how you participate in the vendor selection process.
  • D. Do nothing.

Pregunta 44

Pregunta
While the five process groups are typically completed in order, they often overlap with each other throughout the project. Which two process groups do not overlap unless a project is canceled?
Respuesta
  • A. Initiating and Closing
  • B. Initiating and Executing
  • C. Initiating and Monitoring and Control
  • D. Planning and Closing

Pregunta 45

Pregunta
Which of the following is the correct logical sequence of the five process groups?
Respuesta
  • A. Planning, Monitoring and Controlling, Initiating, Executing, Closing
  • B. Planning, Initiating, Executing, Monitoring and Controlling, Closing
  • C. Initiating, Monitoring and Controlling, Planning, Executing, Closing
  • D. Initiating, Planning, Executing, Monitoring and Controlling, Closing

Pregunta 46

Pregunta
You have met with your project sponsor and have been told that the project MUST be completed by the end of the year, no exceptions. This should be included in the project scope statement as a:
Respuesta
  • A. Project Constraint
  • B. Project Boundary
  • C. Project Acceptance Criteria
  • D. Project Assumption

Pregunta 47

Pregunta
The change requests created as an output of the Monitor and Control Project Work process may be attributed to all of the following except:
Respuesta
  • A. Preventive Action
  • B. Defect Repair
  • C. Project status update
  • D. Corrective Action

Pregunta 48

Pregunta
Lee is the project manager of a project and is planning responses to a set of risks. As a direct response of implementing this risk response, he anticipates certain other risks to arise. These would be termed as:
Respuesta
  • A. Secondary risks
  • B. Primary risks
  • C. Planned risks
  • D. Workaround

Pregunta 49

Pregunta
You have been identified as the project manager for constructing a large shopping mall in your city. Which of the following are not necessarily stakeholders in your project?
Respuesta
  • A. The suppliers of the project
  • B. The tenants of the shopping mall
  • C. A senior project manager in your organization who just completed a similar project.
  • D. The chief financial officer of your company who controls the project finances.

Pregunta 50

Pregunta
Three strategies that typically deal with negative risks or threats are:
Respuesta
  • A. Enhance, Share and Accept
  • B. Transfer, Exploit and Accept
  • C. Avoid, Transfer and Exploit
  • D. Avoid, Transfer and Mitigate

Pregunta 51

Pregunta
Which of the Project Time Management processes involves identifying and documenting dependencies between schedule activities?
Respuesta
  • A. Sequence Activities
  • B. Define Activities
  • C. Develop Schedule
  • D. Control Schedule

Pregunta 52

Pregunta
What does it mean if the Earned Value is equal to Actual Cost?
Respuesta
  • A. Schedule Variance Index is 1
  • B. Project is on budget and on schedule
  • C. There is no cost variance
  • D. There is no schedule variance

Pregunta 53

Pregunta
Your project sponsor has asked you to add 30% contingency to your project budget as a hedge against any unforeseen costs that could exceed the currently forecasted expenses, but has not provided any additional detail about why this is required. What do you do?
Respuesta
  • A. Add 30% to the management reserves.
  • B. Ask the sponsor to elaborate the risks that are behind the request.
  • C. Rebaseline the project budget.
  • D. Add 30% to the total budget.

Pregunta 54

Pregunta
Steve is the project manager of a global project. He finds that of late, there has been a deterioration in the quality of communication between various team members across the globe. What would you term this?
Respuesta
  • A. Noise
  • B. Encoding
  • C. Medium
  • D. Message

Pregunta 55

Pregunta
You are the project manager managing a project to design a print head for dot matrix printers. In order to determine ideal settings for print quality, the quality manager of the company suggests trying out various scenarios for printing by varying certain parameters on the print head. Identifying such variables which influence the product or process under development is called:
Respuesta
  • A. Benchmarking
  • B. Design of Experiments
  • C. Statistical Sampling
  • D. Brainstorming

Pregunta 56

Pregunta
Which of the following statements best describes Time & Material (T&M) contracts?
Respuesta
  • A. T&M contracts are hybrid type of contractual agreements that could contain aspects of both cost-reimbursable and fixed-price type arrangements
  • B. T&M contracts are the best form of contracts when the scope of work and the number of hours of work for a specific resource category is clearly known.
  • C. T&M contracts are the same as Fixed Price contracts except that the total value is calculated using Fixed rates and the effort data is available to the purchaser as well as the seller. Once this is agreed upon, it becomes the same as a Fixed Price project.
  • D. T&M contracts are very risky since the value of the project is not known. It is best to go in for a fixed price (FP) contract.

Pregunta 57

Pregunta
When does the Close Project or Phase process need to be performed in case of multi-phased projects?
Respuesta
  • A. The Close Project or Phase process needs to be done at the end of each phase of the project; however, it is left to the project manager's discretion on whether he/she wants to perform this process in between phases. It necessarily needs to be done at the end of the project.
  • B. The Close Project or Phase process is done at the end of the project in case the work is contracted out to external performing organizations.
  • C. The Close Project or Phase process needs to performed at the end of the project and involves closing out the entire project scope.
  • D. The Close Project or Phase process needs to be performed at the end of each phase of the project and involves closing out the portion of project scope applicable to that phase.

Pregunta 58

Pregunta
A project manager is about to start on a new project. Where would he find details about his authority level in the project?
Respuesta
  • A. Organizational Process Assets
  • B. The Project Charter
  • C. The PMBOK
  • D. The Scope statement

Pregunta 59

Pregunta
Which of the following is not true about the WBS?
Respuesta
  • A. The project team must be involved in developing the WBS
  • B. The WBS must represent all product and project work.
  • C. WBS should focus on activities rather than deliverables
  • D. WBS is usually represented in a hierarchical fashion

Pregunta 60

Pregunta
Which of the following is accurate regarding the Estimate Activity Resources process?
Respuesta
  • A. It produces project resource calendars as the output
  • B. It determines dependencies that may require a lead or lag to define the relationship
  • C. This process is coordinated independent of the Estimate Cost process
  • D. It involves determining what and how many resources will be used

Pregunta 61

Pregunta
In a project, Activity A has a duration of 4 days and begins on the morning of Monday the 4th. The successor Activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to-Start relationship has 2 days of lag, and Activity B has a duration of 3 days. If Saturday and Sunday are non working days, which of the following statements is true?
Respuesta
  • A. Total elapsed days (completing both activities) is 7 days
  • B. Activity B will be completed by the end of day on Thursday, 14th
  • C. Activity B will be completed by the end of day on Friday, 15th.
  • D. Activity B will be completed by the end of day on Tuesday, 12th

Pregunta 62

Pregunta
What is the BEST way to make an accurate forecasting of ETC?
Respuesta
  • A. EAC - AC
  • B. BAC – EV
  • C. Manual forecasting of cost of the remaining work.
  • D. (BAC – EV)/CPI

Pregunta 63

Pregunta
Which of the following is not a valid instance of Risk Transference?
Respuesta
  • A. Use of a Cost Reimbursable contract
  • B. Warranties
  • C. Fixed Price contracts
  • D. Performance bonds

Pregunta 64

Pregunta
Under which of the following scenarios would you not use a Decision tree?
Respuesta
  • A. When some future scenarios are unknown.
  • B. When you need to look at the implications of not choosing certain alternatives.
  • C. When the future scenarios are known.
  • D. When the outcomes of some of the actions are uncertain.

Pregunta 65

Pregunta
You have been assigned as a project manager of a new project to be executed out of New York. However, you determine that the project requires a Global Positioning Systems Expert who is not available within the company in New York. On doing a little checking, you determine that the company has an expert based in London, who is suitable for the project. However, the London based employee is not willing to relocate to New York for the project. In such a case:
Respuesta
  • A. Write to the manager of the London based employee and inform him that the employee needs to be convinced to relocate to New York due to project requirements.
  • B. You would look at the option of moving ahead with the project by using a virtual team.
  • C. Manage the project without the key resource and flag this as a risk.
  • D. Co-location of resources is a key factor for the success of projects. As per PMI guidelines, you will not be able to proceed with the project since the resources is not available in New York.

Pregunta 66

Pregunta
PMP Lite Mock Exam 5 QUESTAO 1You are managing a project to manufacture widgets for a customer. The customer has come to the factory to examine the product, and determines that while the product itself meets its requirements, the manner in which about half the widgets have been packaged does not meet requirements and is insisting they be repackaged. This re-work will require considerable time, resources, and cost to complete. The investigation into how and why the packaging was problematic, revealed that no process was developed to govern how the widget was to be placed in the packaging. The result is that the assembly line workers developed their own processes for packaging. What do you do?
Respuesta
  • A. Notify the project stakeholders immediately and accept responsibility for the failure to develop and implement a packaging process.
  • B. Pursue formal disciplinary action against the assembly line manager and the quality manager.
  • C. Contact the legal department.
  • D. Crash the project.

Pregunta 67

Pregunta
When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where must this information be documented?
Respuesta
  • A. Human resource management plan
  • B. RACI chart
  • C. Resource calendar
  • D. Resource Breakdown Structure (RBS)

Pregunta 68

Pregunta
A project's financial management reserve is identified in which process:
Respuesta
  • A. Estimate Costs
  • B. Determine Budget
  • C. Control Costs
  • D. Estimate Activity Resources

Pregunta 69

Pregunta
Which of these is not a component of the scope baseline that is contained in the project management plan?
Respuesta
  • A. Work Breakdown Structure (WBS)
  • B. Requirements documentation
  • C. WBS Dictionary
  • D. Project Scope Statement

Pregunta 70

Pregunta
John has been assigned to design a new car model for a well-known car manufacturer. The project has a small number of key stakeholders and John is planning to meet all of them in person in order to understand their requirements and expectations. Which of the following is not a project key stakeholder?
Respuesta
  • A. Project sponsor.
  • B. Project manager. .
  • C. Customer.
  • D. Competitor.

Pregunta 71

Pregunta
Project stakeholders are individuals and organizations that are actively involved in the project or have an interest in it. Which of the following is not a stakeholder?
Respuesta
  • A. Customer.
  • B. Project Sponsor.
  • C. Competitor.
  • D. Project Manager.

Pregunta 72

Pregunta
You have landed your dream job, as project manager working in an exotic sports car factory. Your project involves coming up with a smoother ride for the car. You have tasked the engineers to determine which type of suspension and what type of tires will provide the best ride and the most reasonable cost. This relates to which of the following processes?
Respuesta
  • A. Control Risks.
  • B. Perform Quality Assurance.
  • C. Control Quality.
  • D. Plan Quality Management.

Pregunta 73

Pregunta
The Manage Communications process requires which of the following inputs to determine which project management information system is available to manage project communications?
Respuesta
  • A. Communications Management Plan.
  • B. Enterprise Environmental Factors.
  • C. Organizational Process Assets.
  • D. Work Performance Reports.

Pregunta 74

Pregunta
You are about to contract out a project to a service provider. However, at the time of awarding the contract, you are not sure of the total effort involved. Since the scope of work cannot be accurately estimated, you want to agree the per unit rates for difference services. Which of the following would best suit your purpose?
Respuesta
  • A. Cost-Plus-Fixed-Fee (CPFF).
  • B. Time & Material (T&M).
  • C. Fixed Price (FP).
  • D. Cost-Plus-Incentive-Fee (CPIF).

Pregunta 75

Pregunta
The Identify Stakeholders process has four inputs. Three of them are project charter, enterprise environmental factors and organizational process assets. What is the fourth one?
Respuesta
  • A. Procurement documents.
  • B. Stakeholder register.
  • C. Stakeholder engagement matrix.
  • D. Stakeholder management plan.

Pregunta 76

Pregunta
As an experienced PMP, you have found that running a WBS meeting is tricky because you need to find a balance between decomposition and excessive decomposition. When items are excessively decomposed it leads all of the following, EXCEPT:
Respuesta
  • A. It breaks the 100% rule.
  • B. Inefficient use of resources.
  • C. Non productive management effort.
  • D. Decreased efficiency when performing work.

Pregunta 77

Pregunta
You are the sponsor of a project that is designed to record phone calls for quality control purposes. You are in the process of writing the charter, what is NOT an input into this document?
Respuesta
  • A. Organizational standard processes
  • B. Marketplace conditions
  • C. Government or industry standards
  • D. Project Scope Statement

Pregunta 78

Pregunta
John, a project manager, for Code Crashers Inc. has been assigned a project where he must lead a group of inexperienced programmers in developing a software package that creates Material Safety Data Sheets (MSDS) for a chemical company. This is very similar to a project that his colleague, Peter, worked on in 2006, with some junior programmers. If John needs to come up with a rough order of magnitude estimate, what tool or technique should he use?
Respuesta
  • A. Parametric Estimating.
  • B. Bottom Up Estimating.
  • C. Three-point estimate.
  • D. Analogous Estimating .

Pregunta 79

Pregunta
You are an expatriate working in a foreign country and have been asked to offer a cash payment gift to the procurement manager at a company you are bidding on work for. How BEST should you interpret this request?
Respuesta
  • A. Agree to provide the cash payment because the procurement manager controls whether your bid is accepted.
  • B. Inform the procurement manager that offering such a payment would violate your professional standards.
  • C. Base your interpretation of the request on an understanding of the norms of the country you are in.
  • D. Express your anger at the request and inform the procurement manager that this would never happen in your home country.

Pregunta 80

Pregunta
Jonathan is managing a computer network deployment project at a university campus. Jonathan wants to involve the key project stakeholders in the scheduling of the major work packages. He sends out a meeting invitation to all key stakeholders for this brainstorming session. Which of the following types of communication methods has Jonathan selected for the brainstorming?
Respuesta
  • A. Push communication
  • B. Interactive communication
  • C. Pull communication
  • D. One-sided communication

Pregunta 81

Pregunta
QUESTION 16 (exame 5 ) The Project Managers have maximum authority in which type of organization?
Respuesta
  • A. Weak Matrix
  • B. Strong Matrix
  • C. Functional
  • D. Balanced Matrix

Pregunta 82

Pregunta
QUESTION 17 As the Project Manager on the construction of a new hotel you have developed a project management plan that you believe is realistic and will be formally approved. The organizational assets that influenced the development of the plan may include all of the following except:
Respuesta
  • A. Project management plan templates
  • B. Risk register from a past project
  • C. Change control procedures
  • D. Business case for the project

Pregunta 83

Pregunta
QUESTION 18 As part of your staffing management plan, you have developed a chart indicating the # of hours (Y axis) a senior programmer will be working over the months (X axis) of the project. This is an example of what?
Respuesta
  • A. Pareto Chart
  • B. Ishikawa Diagram
  • C. Resource Histogram
  • D. Staff Acquisition Chart

Pregunta 84

Pregunta
QUESTION 19 Which of the following is a control tool that helps the project management team quantify and categorize defects according to sources?
Respuesta
  • A. Scatter chart
  • B. Pareto diagram
  • C. Control chart
  • D. Cause and effect diagram

Pregunta 85

Pregunta
QUESTION 20 While performing an audit on a project run by another project manager, a certified PMP, you find that project processes have not been followed, and that company procurement policies have been repeatedly violated. What do you do?
Respuesta
  • A. Develop a plan to deal with the associated problems.
  • B. Ask the project manager to explain why these things have happened.
  • C. Notify the appropriate management immediately.
  • D. File a complaint with PMI

Pregunta 86

Pregunta
QUESTION 21 You have successfully passed your PMP exam and are leading a project to replace the storage devices in a data center. In the following week, you and your team of experts will be meeting with a storage device vendor to discuss the status of their deliverables that are due at week's end. What management process do these activities reflect?
Respuesta
  • A. Plan Procurement Management
  • B. Control Procurements
  • C. Conduct Procurements
  • D. Close Procurements

Pregunta 87

Pregunta
QUESTION 22 Alan is the project manager of a project with 6 stakeholders. If the number of stakeholders goes up to 8, how many additional channels does he have to manage?
Respuesta
  • A. 2
  • B. 14
  • C. 13
  • D. 28

Pregunta 88

Pregunta
QUESTION 23 The project management plan can best be described as:
Respuesta
  • A. A list of tasks, activities, durations and resources in a software program (e.g., Microsoft Project)
  • B. Coordinating changes across the entire project
  • C. Integrating and coordinating all project plans to create a consistent, coherent document
  • D. Integrating and coordinating all project documents and stakeholder expectations

Pregunta 89

Pregunta
QUESTION 24 Which of the following is not an example of a procurement document?
Respuesta
  • A. Tender Notice
  • B. Risk Register
  • C. Request for Proposal (RFP)
  • D. Invitation for Negotiation

Pregunta 90

Pregunta
QUESTION 25 Your company will receive a large bonus payment for completing a customer's project by a certain date. However, as the project manager, you know the project will complete approximately 2 weeks after that date as it is currently scheduled. Your manager is insisting that you to do whatever it takes to finish the project by that date, even if it means "cutting corners here and there." What do you do?
Respuesta
  • A. Make a formal scope change request.
  • B. Fast track the project.
  • C. Explain to both your manager and the project stakeholders the impact that this schedule change could have on the project.
  • D. Compress the schedule

Pregunta 91

Pregunta
QUESTION 26 An organization wishes to ensure that the opportunity arising from a risk with positive impact is realized. This organization should:
Respuesta
  • A. Exploit the risk
  • B. Mitigate the risk
  • C. Accept the risk
  • D. Avoid the risk

Pregunta 92

Pregunta
QUESTION 27 Your Vice President has asked you what the Estimate at Completion is going to be for a small project you are working on. You were given a budget of $30,000, and to date you have spent $20,000 but only completed $10,000 worth of work. You are sure that the future work will be accomplished at the planned rate.
Respuesta
  • A. $40,000
  • B. $30,000
  • C. $60,000
  • D. $10,000

Pregunta 93

Pregunta
QUESTION 28 You have just sat through an exhausting change control meeting discussing a change in scope to the project you have been working on for the last 7 months. After lengthy discussion the change in scope was approved. As the Project Manager you should now update all of the following documentation, EXCEPT:
Respuesta
  • A. Scope Baseline
  • B. Requirements documentation
  • C. WBS Dictionary
  • D. Project charter

Pregunta 94

Pregunta
QUESTION 29 You work at a software company that authors Material Safety Data Sheets (MSDS) for chemical companies. Prior to releasing the MSDS to the company you have created a list of items to be reviewed to see that they appear on the document such as: chemical name, CAS#, protection required, what to do an emergency, etc. This is an example of what type of tool?
Respuesta
  • A. Checklist
  • B. Process Improvement Plan
  • C. Quality Management Plan
  • D. Quality Metrics

Pregunta 95

Pregunta
QUESTION 30 A project team is required to prepare a monthly project update report for the project key stakeholders. This report must contain the current status of the deliverables, information related to the recently approved change requests, project's health and the forecasted estimates. This report is an example of?
Respuesta
  • A. Milestone
  • B. Expert judgment
  • C. Work performance information
  • D. Work performance data

Pregunta 96

Pregunta
QUESTION 31 You are the Project Manager for a large petroleum company and are in the process of writing the project charter for your sponsor. You have used the following as inputs except:
Respuesta
  • A. Business case for the project
  • B. Project statement of work
  • C. Work breakdown structure (WBS)
  • D. Project contract

Pregunta 97

Pregunta
QUESTION 32 Which of these statements is accurate regarding quality management?
Respuesta
  • A. Modern quality management complements project management
  • B. Overworking the team to meet requirements is not likely to increase attrition and rework
  • C. Quality and grade are essentially the same
  • D. Project requirements are turned into customer needs, wants, and expectations

Pregunta 98

Pregunta
QUESTION 33 Which of the following processes produces a Risk Register?
Respuesta
  • A. Perform Quantitative Risk Analysis
  • B. Plan Risk Management
  • C. Perform Qualitative Risk Analysis
  • D. Identify Risks

Pregunta 99

Pregunta
QUESTION 34 The Risk Register contains details of all identified risks and current status. It is a document containing the results of:
Respuesta
  • A. Plan Risk Responses
  • B. Identify Risks
  • C. Control Risks
  • D. Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis and Plan Risk Responses

Pregunta 100

Pregunta
QUESTION 35 A co-worker mentions that another project manager regularly takes certain project resources to expensive dinners and expenses it to the company. However, this project manager does not recognize or reward the contributions of any other project resources. What should you do?
Respuesta
  • A. Do nothing.
  • B. Confront the project manager.
  • C. Implement a formal reward and recognition program on your own project.
  • D. Report this to the appropriate management

Pregunta 101

Pregunta
QUESTION 36 You the project manager responsible for building a 100,000 sq. ft. data center. One of the schedule activities in your plan is to install the Computer Room Air Conditioning (CRAC) units, however in order to start the installation of the units the raised floor in the data center must be completely installed first, so the units have something to be bolted on to. This is an example of what type of dependency?
Respuesta
  • A. External
  • B. Optional
  • C. Discretionary
  • D. Mandatory

Pregunta 102

Pregunta
QUESTION 37 Robert wants to assign a risk owner for every project risk for which a risk response action has been planned. Where must he update this information?
Respuesta
  • A. Human resource management plan
  • B. Risk register
  • C. Stakeholder register
  • D. Project charter

Pregunta 103

Pregunta
QUESTION 38 You are analyzing the risk in a project and decide to do sensitivity analysis to determine which risks have the most potential impact on the project. You look at a tool to help compare the relative importance of variables that have a high degree of uncertainty to those that are more stable. One such tool is: A. Beta Distribution
Respuesta
  • A. Beta Distribution
  • B. S-Curve
  • C. Control Chart
  • D. Tornado Diagram

Pregunta 104

Pregunta
QUESTION 39 Which of these is accurate regarding the Develop Schedule process?
Respuesta
  • A. Schedules are optimized such that all non-critical activities have a zero total float.
  • B. The critical path method is a schedule network analysis technique that is performed using the schedule model
  • C. Schedule compression shortens the project schedule while changing the project scope
  • D. Schedule network analysis is a technique that is carried out once the schedule is approved.

Pregunta 105

Pregunta
QUESTION 40 A new CEO has come into your company and has promptly shut down your project because it no longer met the business needs of the company. While not pleased with the decision, you document the level and completeness of the project to date. What activity or process is this part of?
Respuesta
  • A. Close Project or Phase
  • B. Close Procurements
  • C. Control Scope
  • D. Validate Scope

Pregunta 106

Pregunta
QUESTION 41 When a project is performed under contract, the contractual provisions will generally be considered as _____________ for the project.
Respuesta
  • A. Constraints
  • B. Exclusions
  • C. Deliverables
  • D. Provisions

Pregunta 107

Pregunta
QUESTION 42 You are the project manager responsible for building a 100,000 sq. ft. data center. One of the schedule activities in your plan is to install the Computer Room Air Conditioning (CRAC) units, however in order to start the installation of the units the raised floor in the data center must be completely installed first. This is an example of what type of precedence relationship?
Respuesta
  • A. Finish to Finish
  • B. Start to Finish
  • C. Start to Start
  • D. Finish to Start

Pregunta 108

Pregunta
QUESTION 43 The Manage Project Team process is part of what process group?
Respuesta
  • A. Planning
  • B. Executing
  • C. Monitoring and Controlling
  • D. Closing

Pregunta 109

Pregunta
QUESTION 44 You have been assigned a project where you are responsible for building a condo complex in a resort town. The project is expected to take 2 years to complete. During your work breakdown structure meeting you have decomposed many deliverables into work packages and schedule activities, however there are some work packages that will be occurring a year from now, so you have elected not to decompose those deliverables and work packages at this time. This is an example of what tool and/or technique?
Respuesta
  • A. Scope Creep
  • B. Poor Planning
  • C. Rolling Wave Planning
  • D. Time Delayed Decomposition

Pregunta 110

Pregunta
QUESTION 45 A Probability and Impact Matrix contains risks prioritized according to their potential implications for meeting the project's objectives. The typical approach is:
Respuesta
  • A. To use a look-up table or Probability and Impact Matrix with specific combinations of Probability and impact that lead to a risk being rated as "high", "moderate" or "low" importance. The importance for planning responses to the risk are usually set by the organization.
  • B. To create a Risk Breakdown Structure with the probabilities and Impacts listed on the individual boxes. The higher the risk, the closer it is towards the Start Node.
  • C. To use a look-up table or Probability and Impact Matrix with specific combinations of Probability and impact that lead to a risk being rated as "high", "moderate" or "low" importance. The importance for planning responses to the risk are usually set by the project manager.
  • D. To create a matrix with the Cost, Time, Scope and Quality on one axis and probability of occurrence on the other.

Pregunta 111

Pregunta
QUESTION 46 You are attempting to estimate the resources required to put the server racks together in the new data center you are building. It has occurred to you that you may be able to compress the schedule if you look at using power tools vs. hand tools to build the racks and use individuals who have worked on this brand of rack in the past. This is an example of what type of resource estimating tool?
Respuesta
  • A. Top Down Estimating
  • B. Bottom Up Estimating
  • C. Alternative Analysis
  • D. Published Estimating Data

Pregunta 112

Pregunta
QUESTION 47 A project is contracted as a Time & Material (T&M) type of contract. The service provider initially estimates that the total effort involved would be about 1000 hours of effort. The project is contracted at a rate of US$ 75 per hour of effort. If the project ended up with 1200 hours of effort, what would the contract payout be.
Respuesta
  • A. US$ 75,000
  • B. US$ 90,000
  • C. US$ 82,500
  • D. US$ 120,000

Pregunta 113

Pregunta
QUESTION 48 A project is contracted as a Cost-Plus-Incentive-Fee (CPIF) type of contract. The project is negotiated such that if the final costs are less than expected costs, the sharing formula for cost savings is 75:25. The targeted cost is US$ 100,000 with an 8% incentive fee on the targeted cost. If the project comes in at US$ 80,000, what would be the cost of the total contract?
Respuesta
  • A. US$ 108,000
  • B. US$ 93,000
  • C. US$ 112,000
  • D. US$ 91,400

Pregunta 114

Pregunta
QUESTION 49 Organizations strongly influence the project framework. The PMBOK Guide recognizes which of the following types of organizations?
Respuesta
  • A. Projectized, Functional.
  • B. Strong Matrix, Organic.
  • C. Weak Matrix, Pre-existing.
  • D. Functional, Transactional.

Pregunta 115

Pregunta
QUESTION 50 During a work breakdown structure meeting you have decomposed the deliverables into work packages and created your WBS dictionary. However, you now want to decompose the work packages to assist you in estimating, executing and control the project. These decomposed work packages are called?
Respuesta
  • A. Work Packages can't be decomposed into smaller units
  • B. Activities
  • C. Milestones
  • D. Control Accounts

Pregunta 116

Pregunta
(EXAME 6) QUESTION 1 While having lunch with another project manager, he tells you that he underestimated the number of staff resources needed for his project by nearly 50%, but says he has plenty of reserves to cover the costs. During the next staff meeting, the same project manager says he has nothing new to report for his project and that all is progressing according to schedule. What do you do?
Respuesta
  • A. Double check your own resource estimates.
  • B. File a complaint with PMI.
  • C. Do nothing.
  • D. Report this to the appropriate management.

Pregunta 117

Pregunta
QUESTION 2 Accepted deliverables are an input to the Close Project or Phase process. These deliverables would have been accepted through which of the following processes?
Respuesta
  • A. Validate Scope
  • B. Control Quality
  • C. Control Scope
  • D. Perform Quality Assurance

Pregunta 118

Pregunta
QUESTION 3 Which of the following is not accurate about the initial phase of a project?
Respuesta
  • A. The highest uncertainty is at this stage of the project
  • B. The cost associated at the beginning of the project is highest
  • C. Stakeholders have maximum influence during this phase
  • D. Staffing levels are the highest at this stage

Pregunta 119

Pregunta
QUESTION 4 As part of the Define Scope process, a project manager documented the specific project assumptions associated with the project scope in the project scope statement. While reviewing this document, an experienced project manager pointed out that the project manager should also document:
Respuesta
  • A. The date on which the assumption becomes invalid.
  • B. The assigned responsibility for each of the assumptions.
  • C. The potential impact of the assumptions if they proved to be false.
  • D. An Assumption Management Plan.

Pregunta 120

Pregunta
QUESTION 5 Nancy has recently taken over a website development project. The project is already in execution and half of the project work has been completed. Nancy finds out that the stakeholder register does not contain any information about key stakeholders from the buyer of the product. What is the potential root cause of this issue?
Respuesta
  • A. Project stakeholders change over time.
  • B. The previous project manager was not competent.
  • C. This is an unknown risk that has just occurred.
  • D. The Identify Stakeholders process was not properly carried out in the past.

Pregunta 121

Pregunta
QUESTION 6 Which process group corresponds to the "do" part of the plan-do-check-act cycle?
Respuesta
  • A. Closing
  • B. Monitoring and Controlling
  • C. Planning
  • D. Executing

Pregunta 122

Pregunta
QUESTION 7 The Control Procurements process ensures that the seller's performance meets contractual requirements and that the buyer performs according to the terms of the contract. This process is part of which process group?
Respuesta
  • A. Executing
  • B. Closure
  • C. Planning
  • D. Monitoring & Controlling

Pregunta 123

Pregunta
QUESTION 8 You are currently leading a project and performing the work defined in the project management plan. This activity relates to which of the following processes?
Respuesta
  • A. Direct and Manage Project Work
  • B. Validate Scope
  • C. Control Scope
  • D. Monitor and Control Project Work

Pregunta 124

Pregunta
QUESTION 9 One of the configuration management activities in the project involved capturing, storing and reporting configuration information needed to manage products and product information. This is known as:
Respuesta
  • A. Configuration status accounting
  • B. Configuration auditing
  • C. Configuration verification
  • D. Configuration identification

Pregunta 125

Pregunta
QUESTION 10 Sharon has recently been asked to manage the deployment of an enterprise resource planning system for her organization. Sharon has sent her project sponsor a meeting request to discuss her project's stakeholder management plan. The sponsor believes that the stakeholder management planning is not relevant for such internal projects. The sponsor believes that only the scope, schedule and cost management plans are sufficient for such projects. The sponsor has asked Sharon to describe the objective of the meeting. Which of the following is the best response to this question?
Respuesta
  • A. The objective of the meeting is to develop the project stakeholder register.
  • B. The objective of the meeting is to develop strategies to effectively keep the project stakeholder engaged and committed to the project.
  • C. The objective of the meeting is to conform to the PMBOK standards.
  • D. The objective of the meeting is to identify and classify project stakeholders.

Pregunta 126

Pregunta
QUESTION 11 The paint on the exotic cars that are manufactured in your plant is bubbling after about a year of application. What would be the BEST tool for your team to use to find potential causes of the peeling paint?
Respuesta
  • A. Defect Repair Review
  • B. Ishikawa Diagram
  • C. Control Chart
  • D. Inspection

Pregunta 127

Pregunta
QUESTION 12 You are meeting with your team, early in the project, and would like to address all the strengths, weakness, opportunities and threats the project is facing. What tool should be used?
Respuesta
  • A. SWOT Analysis
  • B. Interviewing
  • C. Delphi Technique
  • D. Brainstorming

Pregunta 128

Pregunta
QUESTION 13 You are assigned to prepare the Procurement Management Plan for a project that involves setting up an org-wide supply chain management system. You are looking for a guideline on what type of contracts you can use and what type of contract forms are to be used for this project. Which source will help you obtain this?
Respuesta
  • A. Each project is unique so you will need to prepare the necessary documentation for this.
  • B. Department process repository
  • C. Organizational Process Assets
  • D. Integrated project Plan

Pregunta 129

Pregunta
QUESTION 14 You are in charge of constructing the Ferris wheel in each town a carnival visits. However, this is something you have never done before and you are getting different opinions from others on how long it takes. Joe, is new and has given you what you believe to be an optimistic estimate of 3 hours, Bill says it will take 10 hours, which seems too long to you and quite pessimistic. Lastly, Margie, who is the most experienced at this task is telling you it will take 8 hours. You are not sure who to believe, so you decide to do a PERT estimation, based on this you have determined it will take how many hours to assemble the Ferris wheel.
Respuesta
  • A. 7.5 hours.
  • B. 8 hours.
  • C. 21 hours.
  • D. 7 hours.

Pregunta 130

Pregunta
QUESTION 15 Rosemary is the project manager at a pharmaceutical company. She begins her day by analyzing her team's work requirements. She then assigns daily tasks to her team members over a centralized project management information system that then generates automatic task assignment notifications for the team members. Which of the following types of communication methods has been selected by Rosemary?
Respuesta
  • A. Formal, push communication.
  • B. Informal, pull communication. .
  • C. Formal, pull communication.
  • D. Informal, push communication.

Pregunta 131

Pregunta
QUESTION 16 A project manager colleague of yours is currently working under contract on a short term project. He has expressed some concerns about finding work after the project ends. The project he is working on is currently ahead of schedule and he expects they will finish a month sooner than initially expected. What advice would be appropriate to provide him?
Respuesta
  • A. Slow down work on the project to have it finish on schedule.
  • B. Continue the work within the project's scope and possibly finish ahead of schedule.
  • C. Exaggerate his experience to the sponsor to try to get a project manager position for him on other upcoming projects.
  • D. Inform the client the project is behind schedule and it will have to be extended.

Pregunta 132

Pregunta
QUESTION 17 You have just returned from the weekly change control board meeting where you presented the requested changes to the employee move project. You had five change requests approved, however one rejected request. These are outputs of what process?
Respuesta
  • A. Control Quality
  • B. Control Scope
  • C. Control Risks
  • D. Perform Integrated Change Control

Pregunta 133

Pregunta
QUESTION 18 There are two activities on your schedule, which are: 1) Install server in lab 2) Move server into the data center. However, the second task can't start until the server has run in the lab for 5 days without failure. This is an example of what?
Respuesta
  • A. Fast Track
  • B. Lead
  • C. Crashing
  • D. Lag

Pregunta 134

Pregunta
QUESTION 19 You just found out that a major subcontractor for your project consistently provides deliverables late. The subcontractor approaches you and asks you to continue accepting late deliverables in exchange for a decrease in project costs. This offer is an example of:
Respuesta
  • A. Forcing
  • B. Smoothing
  • C. Confronting
  • D. Compromise

Pregunta 135

Pregunta
QUESTION 21 During your weekly status reports you are reporting the earned value for the project. This information is important for you and the stakeholders to gauge the progress of the project. What process group are the cost and schedule control part of?
Respuesta
  • A. Closing
  • B. Planning
  • C. Executing
  • D. Monitoring and Controlling

Pregunta 136

Pregunta
QUESTION 22 You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an example of a tool and technique in what process?
Respuesta
  • A. Manage Communications
  • B. Direct and Manage Project Work
  • C. Monitor and Control Project Work
  • D. Manage Project Team

Pregunta 137

Pregunta
QUESTION 23 You are working with your team and are looking at the cost risks in the project. You are your team are currently creating a tornado diagram for the project risks. This is done as a part of which of the following processes?
Respuesta
  • A. Qualitative Risk Analysis
  • B. Risk Response Planning
  • C. Quantitative Risk Analysis
  • D. Control Risks

Pregunta 138

Pregunta
QUESTION 24 Body language plays an important role in effective communications. This relates to which of the following communications dimensions?
Respuesta
  • A. Nonverbal
  • B. Informal
  • C. Verbal
  • D. Formal

Pregunta 139

Pregunta
QUESTION 25 You have taken over the management of a project from another project manager, who is a certified PMP. This project has been completed and is in the process of closing. You discover that there is no project schedule. What do you do?
Respuesta
  • A. Add this issue to the lessons learned database.
  • B. Do nothing.
  • C. Notify the appropriate management immediately.
  • D. Create a schedule.

Pregunta 140

Pregunta
QUESTION 26 You are in the execution stage of your project and you have been informed that "corporate" will be sending in a team of consultants to review whether your project activities comply with company's and PMI's policies, standards and procedures. This is an example of?
Respuesta
  • A. Quality Audit.
  • B. Organizational Process Assets.
  • C. Process Analysis.
  • D. Recommended Corrective Actions.

Pregunta 141

Pregunta
QUESTION 27 You are in the initiation phase of your project and believe the project can be completed for $100,000. However, you are an experienced project manager and know that many things can happen between the initiation phase and the closure of the project. You have provided an estimate in the project charter of $75,000 - $175,000. This is an example of?
Respuesta
  • A. Narrow Estimate
  • B. Absolute Estimate
  • C. Rough Order of Magnitude Estimate
  • D. True Estimate

Pregunta 142

Pregunta
QUESTION 28 PMBOK recognizes five process groups typical of almost all projects. Which of the following is not one of them?
Respuesta
  • A. Executing
  • B. Monitoring and Controlling
  • C. Planning
  • D. Pre-Inception

Pregunta 143

Pregunta
QUESTION 29 A technique that calculates multiple project durations with different sets of activity assumptions and variables is called:
Respuesta
  • A. Process analysis
  • B. Theoretical Analysis
  • C. Simulation
  • D. Effect Analysis

Pregunta 144

Pregunta
QUESTION 30 A project team is currently assessing the project stakeholder management plan for its validity. The project documents are essential inputs to this process. Which of the following project documents must be used by the project team during this process?
Respuesta
  • A. All project documents prepared during the project so far.
  • B. Project documents prepared during the project planning.
  • C. Project documents prepared during the project execution.
  • D. Project documents prepared during the project initiation.

Pregunta 145

Pregunta
QUESTAO 31 A process that states how formal validation and acceptance of the completed project deliverables will be obtained is documented in the:
Respuesta
  • A. Scope Management plan
  • B. Procurement Management plan
  • C. Risk Management Plan
  • D. Communications Management Plan

Pregunta 146

Pregunta
QUESTION 32 The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives. This is created as part of:
Respuesta
  • A. Project Integration Management
  • B. Project Scope Management
  • C. Project Procurement Management.
  • D. Project Time Management.

Pregunta 147

Pregunta
QUESTION 33 Which of the following Perform Quality Assurance techniques relates to root cause analysis and is used to identify a problem, discover the underlying causes, and develop preventive actions?
Respuesta
  • A. Sensitivity Analysis
  • B. Expected monetary value analysis
  • C. Earned Value Analysis
  • D. Process Analysis

Pregunta 148

Pregunta
QUESTION 34 The process of auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational definitions are used is the definition of:
Respuesta
  • A. Quality assurance
  • B. Quality planning
  • C. Quality control
  • D. Scope validation

Pregunta 149

Pregunta
QUESTION 35 Several of your resources report to another manager. You need them to participate in a series of project meetings over the next two weeks. How should you handle this?
Respuesta
  • A. Send meeting invitations to the project resources.
  • B. Provide a copy of the project charter to the other manager, showing that the resources on his team have been assigned to you for your project.
  • C. Request in advance resource participation from the other manager and the resources and communicate information about the timing and duration of the project meetings.
  • D. Shortly before each meeting, inform the other manager that his staff is required for your project meeting.

Pregunta 150

Pregunta
QUESTION 36 A buyer has just received a final set of deliverables from the seller and finds that they do not conform to the specifications that were originally planned for. Ideally, where would the buyer expect to find documentation on how to handle non-conforming deliverables?
Respuesta
  • A. Communication Plan
  • B. The contract
  • C. Quality Plan
  • D. Scope Statement
Mostrar resumen completo Ocultar resumen completo

Similar

Cómo Escribir texto en inglés
maya velasquez
Mapa conceptual
Franchesk Maestr
irregular verbs
Rosalia Ruiz Jurado
Funciones Esenciales de la salud Pública
Bere Segovia
Didáctica de la expresión escrita
Estibalitz Etxaide
GS-1. GUARDIAS DE ORDEN Y GUARDIAS DE LOS SERVICIOS
antonio del valle
INSTRUMENTOS DE PERCUSIÓN
Francisco José Figueroba Sánchez
Mapa Mental del Modelo OSI
Berenice Ríos
La desintegración del Renacimiento
amadis96
Choose the most suitable future form in each sentence
Margarita Beatriz Vicente Aparicio
La Capilla De Los Resurrectos.
Karen Guerrero