Pregunta 1
Pregunta
What kind of software development projects can be executed by Scrum Project Management Framework?
Respuesta
-
Choice-1: Complete software packages
-
Choice-2: Customer projects
-
Choice-3: Sub-systems, components or parts of bigger systems
-
Choice-4: All kinds of software development projects
-
Choice-5: None of the given answers
Pregunta 2
Pregunta
What does NOT belong to cornerstones of the agile manifesto?
Respuesta
-
Choice-1: Individuals and interactions over processes and tools
-
Choice-2: Working software over comprehensive documentation
-
Choice-3: Processes over people
-
Choice-4: Customer collaboration over contract negotiation
-
Choice-5: Responding to change over following a plan
Pregunta 3
Pregunta
What is defined by the Scrum Framework?
A) Rules & Roles
B) Document guidelines
C) Artifacts and events
Respuesta
-
Choice-1: A
-
Choice-2: B
-
Choice-3: C
-
Choice-4: A, B ,C
-
Choice-5: A, C
Pregunta 4
Pregunta
Where are the customer requirements stored?
Respuesta
-
Choice-1: In the Product Backlog
-
Choice-2: In the Sprint Backlog
-
Choice-3: In a database
-
Choice-4: In a Scrum Product Requirement Specification
-
Choice-5: Nowhere. The Scrum Product Owner knows them
Pregunta 5
Pregunta
Which ones of the following main roles are defined by Scrum Framework?
A) Scrum Tester
B) The Scrum Team
C) Scrum Manager
D) Scrum Master
E) Scrum Product Owner
Respuesta
-
Choice-1: A, B, C, D, E
-
Choice-2: B, C, D, E
-
Choice-3: B, D, E
-
Choice-4: A, B, D, E
-
Choice-5: A, B, C, D
Pregunta 6
Pregunta
Which ones of the following main events are defined by Scrum Framework?
A) Sprint Planning Meeting
B) Sprint Retrospective Meeting
C) Sprint Review Meeting
D) Mid-Sprint Status Review Meeting
E) Daily Scrum Meeting
Respuesta
-
Choice-1: A, B, C, D, E
-
Choice-2: A, B, C, D
-
Choice-3: A, C, D, E
-
Choice-4: A, B, C, E
-
Choice-5: A, C, E
Pregunta 7
Pregunta
Which concept is NOT defined in the Scrum Framework?
Respuesta
-
Choice-1: Scrum Master
-
Choice-2: Project Manager
-
Choice-3: Scrum Product Owner
-
Choice-4: Daily Scrum
-
Choice-5: Scrum Product Burndown
Pregunta 8
Pregunta
What is important in all Scrum projects?
A) Self-organization
B) Clear hierarchies in the company
C) Communication
D) Continuous improvement
Respuesta
-
Choice-1: A, B, C, D
-
Choice-2: A, C, D
-
Choice-3: A, D
-
Choice-4: A
-
Choice-5: A, B
Pregunta 9
Pregunta
In software engineering what are the disadvantages of the classical waterfall model?
A) End-Product has to be fully anticipated beforehand.
B) Some requirements are implemented as defined in the beginning of the project, and yet they are not really needed by the customer.
C) Each phase is strictly separated.
Respuesta
-
Choice-1: A
-
Choice-2: B
-
Choice-3: C
-
Choice-4: A, B
-
Choice-5: A, B, C
Pregunta 10
Pregunta
What are the advantages of the Scrum Framework?
Respuesta
-
Choice-1: Fine-grained requirements are only defined when they are really needed.
-
Choice-2: All activities to design, build and test a certain functionality are kept together in one phase.
-
Choice-3: Changes are expected and welcomed by Scrum team.
-
Choice-4: All of the given answers
-
Choice-5: None of the given answers