Pregunta 1
Pregunta
Which are purposes of initiating a project process?
1. Establishes a firm base for the project
2. Ensures there is clear understanding of the work involved to deliver the project’s products
3. Avoids commitment of funds before it is appropriate to do so
4. Makes Sufficient information available to define and prepare the Project Brief
Pregunta 2
Pregunta
A purpose of the Managing a stage Boundary Process is to provide the Project Board with information needed to ratify the [?] for the project?
Pregunta 3
Pregunta
What is an objective of Managing a stage boundary Process?
Respuesta
-
Enables the project board to commit resources and expenditure required for the initiation stage.
-
Maintain focus on required outcome
-
Provides a controlled break between those managing the project and those creating the products
-
Ensures a periodic review is held to sign-off the products created within the completed stage
Pregunta 4
Pregunta
Which statement does NOT define a characteristic of a project?
Respuesta
-
Has a higher degree of risk than the other business activities
-
Involves people with different skills introducing a change that will impact others outside of the team
-
Has a life span that usually covers the delivery of the desired outcomes and the realization to the benefits
-
A temporary management structure created for the implementation of business products
Pregunta 5
Pregunta
Which fact is true of project assurance but not quality assurance?
Respuesta
-
Responsible for monitoring the conduct of the project
-
Independent of the project manager
-
Appointed as part of the management team
-
Responsible for reviewing the project for compliance with corporate standards
Pregunta 6
Pregunta
Basing projects on a ‘management by exception’ framework provides which benefit?
Respuesta
-
Promotes consistency of project work
-
Project is not seen as an end its self
-
Clarity of what a project will deliver, why, when and by whom
-
Efficient and economic use of management time
Pregunta 7
Pregunta
How does the controlling a stage process support the learn from experience principle?
Respuesta
-
Supports the Project Manager in ensuring products are delivered within the tolerances agreed with the Project Board
-
Encourages the Project Manger to review the progress of the stage and log any lessons
-
Requires escalation of issues and risks to the project board which threatens the stage or project tolerances
-
Recommends a Work Package is created to deliver products that require specific skills
Pregunta 8
Pregunta
Which theme provides information on what is required, how it will be achieved and by whom?
Respuesta
-
Organization
-
Plans
-
Business Case
-
Quality
Pregunta 9
Pregunta
The purpose of which theme is to establish ways to check that a project will still provide the expected benefits?
Respuesta
-
Business Case
-
Change
-
Progress
-
Quality
Pregunta 10
Pregunta
What is the purpose of Managing Product Delivery Process?
Respuesta
-
Controls the link between the Project Manager and the Team Manager(s)
-
Tracks the progress of a stage through the consolidation of checkpoints reports
-
Provides a link between the work of the Project Manager and the project
-
Maintains a focus on the delivery of benefits throughout the stage
Pregunta 11
Pregunta
Which role is responsible for capturing the customer’s quality expectations?
Respuesta
-
Project Manager
-
Executive
-
Senior Supplier
-
Senior User
Pregunta 12
Pregunta
Which product forms the ‘contract ‘between the Project Manager and the Project Board?
Pregunta 13
Pregunta
What is a product Description used for in controlling a Stage Process?
Respuesta
-
Demonstrating that a product meets its quality criteria through the method specified
-
Forming part of a Work Package that is passed to a supplier for creation
-
Developing the product(S) to the defined quality criteria
-
Obtaining approval for completed products from authorities identified therein
Pregunta 14
Pregunta
Which role is responsible for authorizing and monitoring work to be completed and for taking corrective action within a stage?
Respuesta
-
Project Manager
-
Project Support
-
Project Assurance
-
Team Manager
Pregunta 15
Pregunta
Which of the following is a baseline management product?
Respuesta
-
Benefit Review Plan
-
Issue Register
-
Highlight Report
-
Product Status Account
Pregunta 16
Pregunta
What is an objective of the Closing a Project process?
Respuesta
-
Checks that all the project’s products have been signed off by the users
-
Prepares for the final stage of the project
-
Captures the customer’s quality expectations
-
Ensures that all benefits have been achieved
Pregunta 17
Pregunta
Which process covers the authority to initiate a project?
Pregunta 18
Pregunta
What is a stated purpose of the Closing a Project process?
Respuesta
-
Define the procedure for handing over products
-
Provide a fixed point at which acceptance for the project product is confirmed
-
Capture the lessons identified during the last stage
-
Confirm all project benefits have been achieved
Pregunta 19
Pregunta
What does a Product Description contain?
1. A breakdown of the individual parts that make up the product
2. The management stage in which the product is to be created
3. Details of the individuals responsible for reviewing the product
4. Any allowable deviation from the specifies quality criteria
Pregunta 20
Pregunta
Two Management products are given to the Project Board after the end of the process Starting Up a Project. The first is the Project Brief. What is the second?
Pregunta 21
Pregunta
The Lessons Log is used during the process Starting Up a Project to:
Respuesta
-
Record details of things learned in the past that need to be taken into account of in this project
-
Record what will need to be recorded in this project to pass on to future projects.
-
Record who will need to be responsible in this project fro recording any lessons learned, and who will be responsible for passing that information on.
-
All of the above.
Pregunta 22
Pregunta
Which of these logs and Registers is created in Starting Up a Project?
Respuesta
-
Issues Register
-
Project Log
-
Quality Register
-
Daily Log
Pregunta 23
Pregunta
Which two roles are appointed first in Starting Up a Project?
Respuesta
-
Senior User and Project Manager
-
Senior Supplier and Senior User
-
Executive and Senior User
-
Executive and Project Manager
Pregunta 24
Pregunta
Which of these questions is answered by the process Starting Up a Project?
Respuesta
-
Do the Benefits Outweigh the costs of the project?
-
Do we have a viable and worthwhile project?
-
Does the Product Breakdown Structure reflect the full extent of the project?
-
Have all the risks been documented and the associated risk actions approved?
Pregunta 25
Pregunta
Which of these is NOT covered in the process Starting Up a Project
Respuesta
-
Appointing the Project Board
-
Appointing Project Support
-
Appointing Programme Management
-
Appointing Project Assurance
Pregunta 26
Pregunta
What's the difference between the Business Case included in the Project Brief and the one included later on in the Project Initiation Document (PID)
Respuesta
-
The project brief is not included in the Project Brief at all/
-
It's less detailed than the version in the PID
-
It's more detailed in the PID version, to support initial decision making.
-
There's no difference: The Project Brief version is carried forward into the PID.
Pregunta 27
Pregunta
Which of the following statements accurately reflects an important aim of the process 'Starting Up a Project?
Respuesta
-
To do the minimum necessary in order to decide whether it's worthwhile initiating a project.
-
To document all aspects of a project in detail to allow Initiation, if approved, to proceed on a sound basis.
-
To build in delay to the start of Initiation and so provide a cooling off period where managers can consider whether the project is really justified
-
To carry out thorough risk analysis to prevent a high risk project ever being taken forward into Initiation.
Pregunta 28
Pregunta
Which of the following is a true statement?
Respuesta
-
Starting Up a Project is the first stage in any Prince2 Project.
-
Starting Up a Project is an optional theme in Prince2.
-
Starting Up a Project includes consideration of the way in which work will be conducted - the project approach.
-
Starting Up a Project ends with the production of the Project Initiation Document (PID).
Pregunta 29
Pregunta
After Initiation and the production of the Project Initiation Document(PID), the Project Brief is:
Respuesta
-
No Longer Maintained
-
Maintained as a section of the PID
-
Held in the Daily Log and kept up to date to serve as the Project Manager's overview
-
Used as a baseline for checks at the end to see whether the project satisfied it's original objectives.
Pregunta 30
Pregunta
Which is one of the six aspects of project performance that needs to be managed?
Respuesta
-
Accuracy
-
Reliability
-
Scope
-
Ease of use
Pregunta 31
Pregunta
What theme ensures the project is desirable, viable and achievable?
Respuesta
-
Organisation
-
Progress
-
Business Case
-
Risk
Pregunta 32
Pregunta
What process is triggered by the Project Manager's request to initiate a project?
Pregunta 33
Pregunta
The purpose of what theme is to establish mechanisms to monitor and compare actual achievements against those planned?
Respuesta
-
Business Case
-
Change
-
Progress
-
Quality
Pregunta 34
Pregunta
Which is an objective of the Closing a Project Process?
Respuesta
-
Check that all the project's products have been accepted by the users.
-
Prepare for the final stage of the project
-
Capture the customer's quality expectations
-
Ensure that all benefits have been achieved
Pregunta 35
Pregunta
Identify the missing words in the following sentence.
A purpose of the Managing a stage Boundary process is to provide the Project Board with sufficient information so that it can approve the [?] for the next stage.
Respuesta
-
Work Packages
-
Exception Report
-
Stage Plan
-
Project Brief
Pregunta 36
Pregunta
What theme provides information on what is required, how it will be achieved and by whom?
Respuesta
-
Organisation
-
Plans
-
Business Case
-
Quality
Pregunta 37
Pregunta
Which is recommended as a possible risk response type for an opportunity?
Respuesta
-
Reduce
-
Transfer
-
Reject
-
Fallback
Pregunta 38
Pregunta
Basing projects on a 'management by exception' principle provides which benefits?
Respuesta
-
Promotes consistency of project work and staff mobility
-
Provides a common language
-
Clarity of what a project will deliver, why, when and by whom
-
Efficient and cost-effective use of management time
Pregunta 39
Pregunta
Identify the missing words in the following sentence.
The purpose of the [?] process is to establish solid foundations for the project, enabling the organisation to understand the work that needs to be done to deliver the project's products.
Pregunta 40
Pregunta
Which is a purpose of the Managing Product Delivery process?
Respuesta
-
Control the link between the Project Manager and the Team Manager(s)
-
Tracks the progress of a stage with the help of checkpoint reports
-
Provides a link between the work of the Project Manager and the Project Board
-
Maintains a focus on the delivery of benefits throughout the stage
Pregunta 41
Pregunta
Which role is responsible for authorising and monitoring work to be completed and for taking corrective action within a stage?
Respuesta
-
Project Manager
-
Project Support
-
Project Assurance
-
Team Manager
Pregunta 42
Pregunta
Which fact is true of Project Assurance but not Quality Assurance?
Respuesta
-
Responsible for monitoring the conduct of the project
-
Independent of the Project Manager
-
Appointed as part of the project management team
-
Responsible for reviewing the project for compliance with corporate standards
Pregunta 43
Pregunta
What product forms the 'contract between the Project Manager and the Project Board for the project?
Pregunta 44
Pregunta
Which is NOT a characteristic of a project?
Respuesta
-
Has a higher degree of risk than business as usual
-
Involves people with different skills introducing a change that will impact others outside of the team
-
Has a lifespan that covers the delivery of the desired outcomes and the realisation of all the expected benefits
-
A temporary management structure created for the implementation of business products
Pregunta 45
Pregunta
Which is an objective of the Managing a Stage Boundary Process?
Respuesta
-
Enable the Project Board to commit resources and expenditure required for the initiation stage
-
Review and, if necessary, update the Project Initiation Documentation
-
Provides a break between those managing a project from those creating products
-
Ensure a periodic review is held to approve the products created within the completed stage
Pregunta 46
Pregunta
How should a Team Manager escalate a suggestion for an improvement to a product?
Respuesta
-
Include details in a Checkpoint Report
-
Include details in a Highlight Report
-
Raise an issue
-
Raise an Exception Report
Pregunta 47
Pregunta
Which is a purpose of the Closing a Project Process?
Respuesta
-
Define the procedure for handing over products
-
Provide a fixed point at which acceptance for the project product is confirmed
-
Define formal requirements for the acceptance, execution and delivery of project work
-
Confirm all project benefit have been achieved
Pregunta 48
Pregunta
Which is an objective of the Starting up a Project Process?
Respuesta
-
Confirm there are no known restrictions that would prevent the project from being delivered
-
Ensure all Team Managers understand their responsibilities
-
Get approval for the Project Plan from corporate or programme management
-
Prepare the Project Initiation Documentation for authority to initiate the project
Pregunta 49
Pregunta
What process is used to provide an interface with corporate or programme Management?
Pregunta 50
Pregunta
Which is NOT a purpose of an End Project Report?
Respuesta
-
Compare project achievements against what was originally agreed
-
Record information that will help future projects
-
Prompt the Project Board to authorise the next stage
-
Pass on details of any on-going risks for those who will maintain and operate the finished product
Pregunta 51
Pregunta
Identify the missing word(s) in the following sentence.
If a base-lined product requires modification, the procedure should be applied in order to manage the modification.
Respuesta
-
risk management
-
exception
-
issue and change control
-
quality control
Pregunta 52
Pregunta
Which is a purpose of a Project Brief?
Respuesta
-
Describe an agreed position from which the project can be started
-
Describe the information needs of the project's stakeholders
-
Describe the configuration management procedure that will be used by the project
-
Describe the reporting requirements of the Project Board
Pregunta 53
Pregunta
Which is one of the four integrated elements within PRINCE2?
Respuesta
-
Quality
-
Role descriptions
-
Processes
-
Product Descriptions
Pregunta 54
Pregunta
Which of the following statements apply to a stage plan?
1. Is produced with the knowledge of earlier stages
2. Provides the basis for control by the Project Board
3. Is Produced close to the time when the planned events will take place.
4. Provides the basis for day-to-day control by the Project Manager
Pregunta 55
Pregunta
Identify the missing words in the following sentence.
Because the Project Board receives regular [?], there is no need for regular progress meetings.
Respuesta
-
End Stage Reports
-
Checkpoint Reports
-
Exception Reports
-
Highlight Reports
Pregunta 56
Pregunta
Which is a benefit of using the product-based planning technique?
Respuesta
-
All the required products of the project will be delivered to time and cost
-
Clearly shows how long a project will take
-
It removes the need for activity-based planning
-
Reduces the risk of incorrectly scoping the project
Pregunta 57
Pregunta
Are the following statements about the purpose of the Risk theme true or false?
1. The Risk theme identifies how to manage risks at the corporate or programme level of an organisation.
2. The Risk theme explains the risk management activities to use to improve the chances of a project delivering its objectives
Respuesta
-
Only 1 is true
-
Only 2 is true
-
Both 1 and 2 are true
-
Both 1 and 2 are false
Pregunta 58
Pregunta
Which project management team role can authorise the premature closure of a project?
Respuesta
-
Project Manager
-
Project Board
-
Project Suuport
-
Project Assurance
Pregunta 59
Pregunta
Which is a purpose of the Organisation Theme?
Respuesta
-
Set the tolerance on the cost of resources
-
Provide project management training to those working within the project
-
Define the structure of accountability and responsibilities on the project
-
Implement the controls required to permit management by exception
Pregunta 60
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 61
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 62
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 63
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 64
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 65
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 66
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 67
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 68
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 69
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 70
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 71
Pregunta
Which process enables the Project Board to exercise overall control of a project?
Respuesta
-
Directing a Project
-
Controlling a Stage
-
Starting up a Project
-
Initiating a Project
Pregunta 72
Pregunta
Which is the first plan to be created?
Respuesta
-
Project Plan
-
Initiation Stage Plan
-
Team Plan
-
Exception Plan
Pregunta 73
Pregunta
What is a PRINCE2 definition of a project?
Respuesta
-
A number of Projects managed as a unit
-
A unique undertaking that requires organisation and resources
-
An element of work that a Project Manager agrees to deliver
-
A temporary organisation created for the purpose of delivering business products.
Pregunta 74
Pregunta
Which is NOT an objective of the Managing Product Delivery process?
Respuesta
-
Ensure suppliers understand what is expected of them
-
Ensure products of appropriate quality are delivered
-
Ensure the Project Board is kept informed of progress on the products
-
Ensure work for the team is agreed with the Project Manager
Pregunta 75
Pregunta
Which is an objective of the quality review technique?
Respuesta
-
Involve key interested parties to promote wider acceptance of the product
-
Develop and improve the specification of a product through continuous assessment
-
Agree any changes to the base-lined product
-
Update the status information in the Configuration Item Record when a product is signed-off