SAB4#60 Leads & Lags
  1. LAG time is when you purposefully put a DELAY between the predecessor task and the successor
    1. Example: You need TO WAIT 3 days after pouring concrete to construct a frame from a house
      1. Activities Finish-to-Start
    2. LEAD time is when you give a successor task some time to getstarted BEFORE the predecessor finishes
      1. Example: "Team 2" can start reviewing the document "A" BEFORE "Team 1" has finished reviewing the document "X"
        1. Activities Start-to-Start
      2. The project management team determines the dependencies that may require a LEAD or a LAG to accurately define the logical relationship.
        1. The use of leads and lags should not replace schedule logic
          1. Activities and their related assumptions should be documented
            1. A lead or a lag CAN affect the project time duration
              1. Leads and Lags MUST be used SPECIALLY in crtical activities
                Mostrar resumen completo Ocultar resumen completo

                Similar

                Ambientes Virtuales de Aprendizaje AVA
                Fredy Clavijo
                LAS CLAVES DE LA ARGUMENTACION DE ANTHONY WESTON
                revisorsur
                Esquema Del Feudalismo
                irismateos
                Crisis del Antiguo Régimen
                Claudia Romero
                E-UNAM-2012 HISTORIA DE MEXICO
                ROSA MARIA ARRIAGA
                EL DIÁLOGO
                Eva Sánchez
                Clasificación de las voces humanas
                mariajesus camino
                TEORÍAS DEL COMERCIO INTERNACIONAL
                Yuleni Fkgeghtrhrqwergw
                Análisis de una Pintura
                Sandra Ortega L.
                MAPA CONCEPTUAL DE NETIQUETA
                Hayler Narvaez