Standard costing
Descripción
Mapa Mental sobre Standard costing, creado por Evgeniya Kachan el 08/03/2015.
Mapa Mental por
Evgeniya Kachan
, actualizado hace más de 1 año
Más
Menos
Creado por
Evgeniya Kachan
hace más de 9 años
511
3
0
Resumen del Recurso
Standard costing
standard cost = target/planned unit cost
types of standards
basic
to show trends over time, least useful
ideal
in perfect conditions, rarely achievable => adv motivational effect
attainable
efficient, but not perfect conditions
current
based on current levels, no incentive to improve
needed to prepare budgets
may be based on AC or MC
variance analysis
actual vs standard
sales variance
sales price
effect on profit of selling at a different price
(Actual price - Standard price) x Actual quantity sold
sales volume
effect on profit from the change in volume of sales
(Actual quantity sold - Budgeted quantity sold) x Standard margin
where standard margin is
standard profit per unit (AC)
standard contribution per unit (MC)
AQS > BQS => favourable variance, profit higher
total sales variance = Sales price variance + Sales volume variance
raw materials variance
materials price variance
(Actual quantity bought x Actual price) - (Actual quantity bought x Standard price)
standard price is usually set at mid-year standard, resulting in fav variances in beg of year, adv var later on
materials usage variance
(Actual quantity used x Standard price) - (Standard quantity for act prod x Standard price)
labour variances
labour rate variance
difference in rate paid
Actual hours x Actual rate - Actual hours x Standard rate
labour efficiency variance
difference in hours worked
Actual hours x Standard rate - Standard hours x Standard rate
variable overhead variances
variable overhead EXPENDITURE variance
var OH cost per hour changed
Actual hours x Actual rate - Actual hours x Standard rate
variable overhead EFFICIENCY variance
working fewer or more hours than expected for actual production
Actual hours x Standard rate - Stand. hours 4output x Stand. rate
if variance is due to change in unit output, impossible to calculate subvariances
fixed overhead variances
effect on profit of diff between actual and expected fixed overheads
Mostrar resumen completo
Ocultar resumen completo
¿Quieres crear tus propios
Mapas Mentales
gratis
con GoConqr?
Más información
.
Similar
Inglés - Conjugación Verbos Irregulares
maya velasquez
Readings para Preparar el First Certificate (I)
maya velasquez
Consejos para un Horario de Estudio para Selectividad
maya velasquez
PAU - Lengua
Jesús Peñalver
El sistema nervioso
crisferroeldeluna
ESPAÑOL I
NEMORIO GARCIA GARCES
A1-Español Lengua Extranjera
mgcollado
CCNN 5EP. Tema 6. Aparato locomotor
JOSÉ ALBERTO VERDUGO GARCÍA
FGM-11. DERECHOS Y DEBERES DE LOS MIEMBROS DE LAS FUERZAS ARMADAS
antonio del valle
La tutoría
amarcita1116
TIPOS DE TRANSPORTE CELULAR
CANDIDA ORTEGA CARABALLO
Explorar la Librería