  1. Network diagram and activity duration estimates are completed
    1. Schedule model

      Nota:

      • Approved Realistic Formal
      1. Critical path method

        Nota:

        • Critical path have zero float
        1. Involves determine the longest path (critical path), the earlier and latest an activity can start (and be completed)
          1. Critical path: helps to prove how long the project will take, where to focus your efforts, provides a vehicle to compress the scehdule, shows which activities have float
            1. Near Critical Path
              1. It's the closest in length to the critical path, this could be critical during the project
              2. Float (slack)
                1. Total float or slack: is the amount of time an activity can be delayed without delaying the project
                  1. Free float or slack: is the amount of time an activity can be delayed without delaying the early start date of its sucessor
                    1. Project float: is the amount of time a Project can be delayed without delaying the externally imposed Project completion date
                      1. Start Float = Late Start -Early Start Finish Float= Late Finish -Early Finish
                        1. You have to completed the forward pass and then the backward pass
                    2. Schedule compression
                      1. Technique used in project management to create output faster without changing the actual scope of a project. Sometimes, there is a tangible benefit to significantly shortening the project timeline
                        1. Fast tracking
                          1. This technique involves taking crtical path activities that were originally planned in a series and doing them instead in parallel for some or all of their duration. Often results in rework , usually increases risk, and requieres more attention to comunication.
                          2. Crashing
                            1. This technique adding or adjusting resources in order to compress the Schedule while maintaining the original Project scope . REsults in increased costs and may increase risk. Its trades time for money..
                          3. Modeling
                            1. Montecarlo Analysis
                              1. This technique uses computer to simulate the outcome of a Project based on the three points estimates (optimistic, pessimistic and most likely. This technique is more accurate tha other methods because it simulates the actual details of the Project and calculates probability.
                                1. Can help deal with path convergence , thus adding risk to the Project.
                              2. Resource optimization
                                1. Resource leveling
                                  1. Lengthens the Schedule and increases cost in order to deal with a limited amount of resources, resources availability and resources constraints. Allows level peaks and valleys of the Schedule.
                                  2. Resource Smooting
                                    1. Resources are leveled only within the limits of the float of their actvities , so the completation of activities are not delayed.
                                  Mostrar resumen completo Ocultar resumen completo

                                  Similar

                                  LA PRIMERA GUERRA MUNDIALO LA GRAN GUERRA
                                  Erika Urban
                                  Traducciones de Latín
                                  Diego Santos
                                  Dinamica de Grupos
                                  Monica Espinoza
                                  Deutsch - B1 - Grammatik - Liste der Verben mit Präpositionen
                                  Sandra PlaGo
                                  5 Pasos para el Éxito en el Aprendizaje_2
                                  Diego Santos
                                  Marketing Digital
                                  Diego Santos
                                  Códigos de la principales aerolíneas
                                  Diego Santos
                                  Campos o áreas de la psicología
                                  Melina Contreras
                                  Mapa Conceptual Resolucion 1995 de 1999
                                  alsalazar5
                                  u3. actividad 2, caracteristicas de el neoliberalismoy globalizacion.
                                  Hermilo gonzalez hernandez
                                  CUADRO SINÓPTICO DE LOS TRASTORNOS DE LA PERSONALIDAD
                                  yonaidy granados