SAB9#58_59_Types_Relation_Activities_&_Types_Estimations
  1. PDM (Precedence Diagramming Method)

    Nota:

    • or Activity-on-Node (AON)
    1. Finish to Start (FS)

      Nota:

      • The most common
      1. one thing needs to end before the next can begin
      2. Start to Start (SS)
        1. activities begin at the same time
        2. Finish to Finish (FF)
          1. These two finish at the same time
          2. Start to Finish (SF)

            Nota:

            • This dependency is rarely used
            1. An activity must star before the successor can finish
          3. Types of Dependencies
            1. External dependencies
              1. Sometimes your project will depend on things outside the work you are doing
              2. Discretionary dependencies (Preferred, Preferential, SOFT Logic)

                Nota:

                • you should set discretionary dependencies based on your knowledge of the best practices for getting the job done
                1. it’s just a matter of preference.
                2. Mandatory dependencies (HARD Logic)
                  1. Mandatory predecessors are the kind that have to exist just because of the nature of the work
                  2. Internal dependencies
                    1. Some dependencies are completely within the team’s control
                  3. One-Point Estimating

                    Nota:

                    • Is often not the best method to use
                    1. Expert judgment
                      1. Historical information
                      2. Analogous Estimating (Top-down)

                        Nota:

                        • Advantages---------  -allows for quick calculation -less expensive Disadvantages-------  -This technique can be problematic -It can force people into padding their estimates
                        1. Expert judgment
                          1. Historical information

                            Nota:

                            • previous projects
                          2. Parametric Estimating

                            Nota:

                            • -more accurate than analog -The results of parametric estimating can become heuristics 
                            1. Historical information
                              1. Relationships between variables
                                1. Regression analysis (scatter diagram)
                                  1. 2 variables to see if they are related and creates a mathematical formula
                                  2. Learning curve
                                  3. Heuristics
                                    1. a generally accepted rule, or best practice
                                  4. Three-Point Estimating
                                    1. Triangular Distribution (Simple Average)
                                      1. equal weight
                                      2. Beta Distribution (Weighted Average)
                                        1. gives stronger consideration to the most likely
                                          1. Standar Deviation
                                            1. the possible range for estimate
                                        2. Group Decision Making

                                          Nota:

                                          • team members
                                          1. brainstorming
                                            1. the nominal group technique
                                              1. Delphi technique
                                                1. anonymous
                                                  1. external experts
                                                2. Reserve Analysis
                                                  1. contingency reserves

                                                    Nota:

                                                    • are included in the project schedule baseline
                                                    1. identified schedule risks
                                                    2. management reserves

                                                      Nota:

                                                      • additional funds
                                                      1. unforeseen risks
                                                    Mostrar resumen completo Ocultar resumen completo

                                                    Similar

                                                    Enseñar con Mapas Mentales
                                                    Diego Santos
                                                    Inglés - Conjugación Verbos Irregulares
                                                    María Salinas
                                                    Exani II - Estructura
                                                    Gastón Amato
                                                    5 Pasos para el Éxito en el Aprendizaje
                                                    maya velasquez
                                                    ANATOMIA DEL SISTEMA NERVIOSO
                                                    Maria Heredia Sa
                                                    LEY 1/2000 ENJUICIAMIENTO CIVIL: "De los procesos matrimoniales y de menores" (II)
                                                    Miguel Angel del Rio
                                                    Arquitectura Von Neumann: Maquina Secuencial de Programa Almacenado
                                                    Jhon Jairo Ponton
                                                    USO DE LA FUERZA Y ARMAS NO LETALES EN LA POLICÍA NACIONAL
                                                    ALVARO ENRIQUE MORENO MORENO
                                                    Historia Psicología Precientífica
                                                    María Angélica Mesa Ramirez
                                                    HISTORIA DE LA COMPUTADORA
                                                    SERGYO DAVID CALDERON QUINTERO