The RIBA Plan of Work 2013 Unit 5 M1 Preparation

Pregunta 1 de 20

1

How may stages are in the RIBA Plan of work 2013

Selecciona una de las siguientes respuestas posibles:

  • 7

  • 5

  • 10

  • 8

  • 12

Explicación

Pregunta 2 de 20

1

Which part of the stage of the RIBA Plan of Work 2013 is particularly relevant in the context of sustainability.

Selecciona una de las siguientes respuestas posibles:

  • Stage 4

  • Stage 1

  • Stage 0

  • Stage 7

  • Stage 5

Explicación

Pregunta 3 de 20

1

Stage 6 is primarily concerned with?

Selecciona una de las siguientes respuestas posibles:

  • Post occupancy

  • Concept design

  • Preparation and brief

  • Hand over and close out

  • Developed design maps

Explicación

Pregunta 4 de 20

1

What does BIM stand for

Selecciona una de las siguientes respuestas posibles:

  • Building Information Modelling

  • Business Information Modelling

  • Built Individual Model

  • Building In Materials

Explicación

Pregunta 5 de 20

1

Which stage is a new stage in which a project is strategically appraised and defined before a detailed brief is created?

Selecciona una de las siguientes respuestas posibles:

  • Stage 4 Technical Design

  • Stage 5 Construction

  • Stage 0 Strategic Definition

  • Stage 3 Developed Design

Explicación

Pregunta 6 de 20

1

Which stage of the RIBA plan of Work focuses on making sure the that the initial business case matches the desired outcomes.

Selecciona una de las siguientes respuestas posibles:

  • Stage 7 In use

  • Stage 0 Strategic definition

  • Stage 6 Handover and close out

  • Stage 3 Developed design

  • Stage 5 Construction

Explicación

Pregunta 7 de 20

1

What is meant by the term procurement?

Selecciona una de las siguientes respuestas posibles:

  • The design and execution of the infrastructure .

  • The construction of an object or a system.

  • The acquisition of goods, services or works from an outside external source.

  • Preparing for and forming building systems.

Explicación

Pregunta 8 de 20

1

Is The RIBA Plan of Work 2013 itself a contractual document?

Selecciona una de las siguientes respuestas posibles:

  • Yes

  • No

Explicación

Pregunta 9 de 20

1

Within the RIBA Plan of work which task bars are fixed and always present?

Selecciona una de las siguientes respuestas posibles:

  • Task Bar 1 Core Objectives, Task Bar 3 Programme & Task Bar 8 Government Gateways.

  • Task Bar 8 Government Gateways, Task Bar 6 Sustainability Checkpoints & Task Bar 3 Programme

  • Task Bar 1 Core Objectives,Task Bar 5 Key Support Tasks, & Task Bar 7 Information Exchanges

  • Task Bar 6 Sustainability Checkpoints,Task Bar 4 (Town) Planning &Task Bar 2 Procurement

Explicación

Pregunta 10 de 20

1

Which two task-bars can be switched on or off in The RIBA Plan of Work 2013?

Selecciona una de las siguientes respuestas posibles:

  • Task Bar 6 Sustainability Checkpoints & Task Bar 8 Government Gateways.

  • Task Bar 3 Programme & Task Bar 1 Core Objectives.

  • Task Bar 2 Procurement & Task Bar 5 Key Support Tasks,

  • Task Bar 8 UK Government Information Exchanges & Task Bar 6 Sustainability Checkpoints.

Explicación

Pregunta 11 de 20

1

Which three task-bars are variable in The RIBA Plan of Work 2013?

Selecciona una de las siguientes respuestas posibles:

  • Task Bar 4 (Town) Planning, Task Bar 5 Key Support Tasks & Task Bar 1 Core Objectives.

  • Task Bar 2 Procurement ,Task Bar 3 Programme & Task Bar 8 Government Gateways.

  • Task Bar 3 Programme ,Task Bar 2 Procurement & Task Bar 4 (Town) Planning

  • Task Bar 6 Sustainability Checkpoints, Task Bar 1 Core Objectives & Task Bar 5 Key Support Tasks.

Explicación

Pregunta 12 de 20

1

Why has the UK Government Information Exchanges task bar has been introduced?

Selecciona una de las siguientes respuestas posibles:

  • To encourage consideration of the stages that the UK Government requires information to be exchanged.

  • To provide guidance on the information that would typically be delivered at the Information Exchanges at the end of each stage.

  • To allow for a number of forms of procurement.

  • To underline the need on every project for a Project Programme that sets out the duration of each stage and any supporting activities.

Explicación

Pregunta 13 de 20

1

What has been a core requirement of collaborative contracts for some time as it ensures that each party is involved in the process of agreeing timescales and is fully aware of the risks that the programme generates in relation to their specific Schedule of Services?

Selecciona una de las siguientes respuestas posibles:

  • Construction Programme

  • Design Programme

  • Building Contract

  • Project Programme.

Explicación

Pregunta 14 de 20

1

On certain projects, where it is uncertain that consent will be granted, can the client appoint all of the designers or may appoint them on a restricted Stage 2 Schedule of Services?

Selecciona una de las siguientes respuestas posibles:

  • Yes

  • No

Explicación

Pregunta 15 de 20

1

The Sustainability Checkpoints task bar is selectable and can be switched off?

Selecciona uno de los siguientes:

  • VERDADERO
  • FALSO

Explicación

Pregunta 16 de 20

1

Where detailed circumstances specific to a given project require an alternative approach, what should used to deal with this?

Selecciona una de las siguientes respuestas posibles:

  • Building Contract

  • Health and Safety Strategy

  • Project Programme.

  • Design Responsibility Matrix

Explicación

Pregunta 17 de 20

1

What does the UK Government recognise that a client does not need to be involved in?

Selecciona una de las siguientes respuestas posibles:

  • Every Information Exchange

  • Data-rich information that can be used post- occupancy to manage its entire estate and to allow stringent benchmarking activities to occur.

Explicación

Pregunta 18 de 20

1

Which task-bar sets out key tasks in relation to statutory requirements, such as those relating to Building Regulations submissions and project and design management protocols, roles and responsibilities?

Selecciona una de las siguientes respuestas posibles:

  • Task Bar 7 Information Exchanges

  • Task Bar 5 Key Support Tasks

  • Task Bar 1 Core Objectives

  • Task Bar 8 Government Gateways

Explicación

Pregunta 19 de 20

1

It is also acknowledged that on certain projects (conservation projects, for example) other planning matters may have to be concluded during which other stage?

Selecciona una de las siguientes respuestas posibles:

  • Task Bar 5 Key Support Tasks

  • Task Bar 4 (Town) Planning

  • Task Bar 3 Programme

  • Task Bar 2 Procurement

Explicación

Pregunta 20 de 20

1

The RIBA Plan of Work 2013 does all of the following Acts across the full range of sectors and project sizes: Provides straight-forward mapping for all forms of procurement.
Integrates sustainable design processes. Maps Building Information Modelling (BIM) processes and provides flexible around (town) planning procedures.

Selecciona uno de los siguientes:

  • VERDADERO
  • FALSO

Explicación