IT Websites inc is building a huge e-commerce system. However, the designer getting sick has delayed the finish by two weeks. The Project Manager evaluates the schedule and determines that the graphics and backend work could occur at the same time instead of right after each other, as laid out in the schedule. This is an example of what?
Selecciona una de las siguientes respuestas posibles: