A company recently had to do a massive overhaul of a pump asset. The planner has to enter hundreds of tasks, sequence those tasks, and identify the labor, material, services and tools used on each task. The planner knows that this work will occur again as the company has numerous pumps of the same type. What must the planner do so that the work plan does not have to be re-entered?
Selecciona una o más de las siguientes respuestas posibles: