PRINCE 2 (Lecture 5)- Starting Up a Project (SU) / Initiating a Project (IP)

Pregunta 1 de 10

1

Which is NOT an objective of the Initiating a project process?

Selecciona una de las siguientes respuestas posibles:

  • Ensure there is a common understanding of who will take significant project management roles within the project.

  • Ensure there is a common understanding of how and when the project's products will be achieved and at what cost.

  • Ensure there is a common understanding of the reasons for doing the project, the benefits expected and the associated risks.

Explicación

Pregunta 2 de 10

1

Which of the following is NOT a PRINCE2 management product?

Selecciona una de las siguientes respuestas posibles:

  • Risk Management Strategy

  • Configuration Management Strategy

  • Communication Management Strategy

  • Cost Management Strategy

Explicación

Pregunta 3 de 10

1

The Business Case will contain a summary of key risks, where will the details of all the risks be stored?

Selecciona una de las siguientes respuestas posibles:

  • Issues Register.

  • Configuration Item Records

  • Risk Management Strategy

  • Risk Register

Explicación

Pregunta 4 de 10

1

Which of the following is defined as part of setting up controls for the project?

Selecciona una de las siguientes respuestas posibles:

  • Tolerances for delegated authority.

  • Quality management procedure.

  • Tools and techiques for managing risks

  • How information from outside of the project environment will be sent or received.

Explicación

Pregunta 5 de 10

1

Information on project controls is included in which management product?

Selecciona una de las siguientes respuestas posibles:

  • Project Brief

  • Business Case

  • Stage Quality Plan

  • Project Initiation Documentation

Explicación

Pregunta 6 de 10

1

The Outline Business Case is prepared as part of which process?

Selecciona una de las siguientes respuestas posibles:

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

  • Directing a Project

Explicación

Pregunta 7 de 10

1

The information gathered in the Starting Up a Project process should answer what basic uestions?

Selecciona una de las siguientes respuestas posibles:

  • Do we have a viable and worthwhile project?

  • Do we know who thought of this idea?

  • Do we care about the outcome at this stage?

  • Do we solve the problem now or later?

Explicación

Pregunta 8 de 10

1

What management product produced in Starting Up a Project is submitted to the Project Board with a request to initiate a Project?

Selecciona una de las siguientes respuestas posibles:

  • Project Brief

  • Refined Business Case

  • Project Initiation Document (PID)

  • Project Plan

Explicación

Pregunta 9 de 10

1

How does the Starting up a Project process support the defined roles and responsibilities principle?

Selecciona una de las siguientes respuestas posibles:

  • By nominating the project manager responsible for project assurance.

  • By appointing the executive, the project manager and the project management team.

  • It doesn't.

  • By ensuring lessons from previous projects are captured and analyzed.

Explicación

Pregunta 10 de 10

1

Who is responsible for creating the Initiation Stage Plan?

Selecciona una de las siguientes respuestas posibles:

  • Project Manager

  • Project Board

  • Team Manager

  • Project Assurance

Explicación