Laura Qualey
Test por , creado hace más de 1 año

Test sobre Project Management Final, creado por Laura Qualey el 22/07/2015.

57
3
0
Sin etiquetas
Laura Qualey
Creado por Laura Qualey hace alrededor de 9 años
Cerrar

Project Management Final

Pregunta 1 de 198

1

You are the Project Manager for a large construction project. While reviewing the expenditures, you realize that you are 20% over budget. What process group are you working in?

Selecciona una de las siguientes respuestas posibles:

  • Closure

  • Execution

  • Planning

  • Monitor & Control

Explicación

Pregunta 2 de 198

1

What is the main benefit of a balanced matrix organization over a projectized organizational structure?

Selecciona una de las siguientes respuestas posibles:

  • As a Project Manager, you have a great deal of authority

  • More efficient use of resources

  • Reporting to a functional manager

  • Reporting to 2 Managers

Explicación

Pregunta 3 de 198

1

As the Sponsor on a large, multi-national hydroelectric power project, during the execution phase, your primary responsibilities are to:

Selecciona una de las siguientes respuestas posibles:

  • Provide the financial resources and champion the project

  • Manage a group of interrelated projects

  • Manage the Project Team

  • Provide status updates to the customer

Explicación

Pregunta 4 de 198

1

Name the 5 project management process groups.

Selecciona una de las siguientes respuestas posibles:

  • Initiating, Planning, Executing, Monitoring & Control, Closing

  • Planning, Executing, Monitoring, Integrated Change, Closing

  • Business Case, Planning, Executing, Monitoring & Control, Closing

Explicación

Pregunta 5 de 198

1

You are hired to manage an exciting new project for a software development company making CRM tools. You are unfamiliar with the project management resources available in the company. Who should you go to for help identifying the resources and best practices?

Selecciona una de las siguientes respuestas posibles:

  • Project Sponsor

  • Operations Manager

  • Other Project Managers

  • Project Management Office

Explicación

Pregunta 6 de 198

1

As you progress through the project life cycle:

Selecciona una de las siguientes respuestas posibles:

  • Risk increases and cost of changes increases

  • Cost of changes decreases and risk increases

  • Risk decreases and cost of changes increases

  • Cost of changes decreases and risk decreases

Explicación

Pregunta 7 de 198

1

The purpose of the Closer Process Group is:

Selecciona una de las siguientes respuestas posibles:

  • Complete the work as quickly as possible

  • Analyze the project risks at the end of the project

  • Inspect the outputs to ensure the quality is as planned

  • Formally complete the project

Explicación

Pregunta 8 de 198

1

In the Statement Of Work, you provide:

Selecciona una de las siguientes respuestas posibles:

  • Project charter

  • Market demand analysis

  • Change control tools you will use

  • Scope description

Explicación

Pregunta 9 de 198

1

The output of the Develop Project Charter process is:

Selecciona una de las siguientes respuestas posibles:

  • Project charter

  • Project Management Plan

  • Work performance data

  • Business case

Explicación

Pregunta 10 de 198

1

According to the PMBOK all the following are types of project constraints except:

Selecciona una de las siguientes respuestas posibles:

  • Scope

  • Portfolio Alignment

  • Risks

  • Schedule

Explicación

Pregunta 11 de 198

1

You are the Project Manager for a project that will design and build the iPhone X, the latest in mobile phone technology. The requirements call for a new production facility in Asia. Immediately after working with Senior Management to create a business case and statement of work for the new production facility, what document will you want to produce?

Selecciona una de las siguientes respuestas posibles:

  • Project document updates

  • Lessons learned

  • Project plan

  • Project charter

Explicación

Pregunta 12 de 198

1

The ideal Project Team size is?

Selecciona una de las siguientes respuestas posibles:

  • 10-15

  • 3-6, 6-9

Explicación

Pregunta 13 de 198

1

Your project has been officially approved by your sponsor, what process group will you move from and which process group will you move to?

Selecciona una de las siguientes respuestas posibles:

  • Planning to execution

  • Initiation to execution

  • Planning to initiation

  • Initiation to planning

Explicación

Pregunta 14 de 198

1

All the following are examples of expert judgement except:

Selecciona una de las siguientes respuestas posibles:

  • PMO

  • Tech manuals

  • PM information system

  • Professional associations

Explicación

Pregunta 15 de 198

1

In Project Integration Management, as you develop the Project Management Plan, you will:

Selecciona una de las siguientes respuestas posibles:

  • Direct and manage the planning of work defined in the Project Charter and implement to achieve the project’s objectives

  • Provide the project schedule which is derived from progress against the schedule baseline.

  • Validate plans and changes from Perform Integrated Change Control and ensure that the changes are appropriately executed

  • Define, prepare, and coordinate all subsidiary plans and integrate them into a comprehensive plan.

Explicación

Pregunta 16 de 198

1

The process group where you will identify if any changes to the plan are needed and initiate those plans is:

Selecciona una de las siguientes respuestas posibles:

  • Monitoring and control

  • Executing

  • Planning

  • Initiating

Explicación

Pregunta 17 de 198

1

The organizational structure that gives project managers a very high degree of authority over their project is:

Selecciona una de las siguientes respuestas posibles:

  • Functional

  • Projectized

  • Weak matrix

  • Strong matrix

Explicación

Pregunta 18 de 198

1

The largest portion of the projects budget will be expended in what process group?

Selecciona una de las siguientes respuestas posibles:

  • Planning

  • Execution

  • Closing

  • Monitoring and control

Explicación

Pregunta 19 de 198

1

All of the following are examples of Enterprise Environmental Factors EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • Established communication channels

  • Organizational culture

  • Project management information system

  • Project charter

Explicación

Pregunta 20 de 198

1

The leader of the project is working on completing a database upgrade but cannot get the additional resources she needs to be able to complete the project. The rest of the project team is working on daily operations work. The leader has not been given the authority to put additional resources on the project. What is the organizational structure this team is working in?

Selecciona una de las siguientes respuestas posibles:

  • Project team

  • Strong matrix

  • Projectized

  • Functional

Explicación

Pregunta 21 de 198

1

Portfolio management refers to:

Selecciona una de las siguientes respuestas posibles:

  • Applying resource-leveling heuristics across all the organization's projects to achieve the organization's strategic objectives.

  • Managing the levels of functional authority to facilitate project decision making.

  • Managing various contents of the project file

  • The centralized management of one or more portfolios to achieve strategic objectives.

Explicación

Pregunta 22 de 198

1

A project has all of the following characteristics except:

Selecciona una de las siguientes respuestas posibles:

  • Short duration

  • Unique

  • Temporary endeavor

  • Specific end

Explicación

Pregunta 23 de 198

1

A program is:

Selecciona una de las siguientes respuestas posibles:

  • Project over 1$ mill

  • Group of related projects, subprograms & program activities managed in a coordinated way.

  • Sequence of steps constituting a project

  • Group of related tasks lasting one year or less

Explicación

Pregunta 24 de 198

1

The project manager has the lowest level of authority in this type of organization:

Selecciona una de las siguientes respuestas posibles:

  • Projectized

  • Weak matrix

  • Strong matrix

  • Functional

Explicación

Pregunta 25 de 198

1

Project Management Process Groups are:

Selecciona una de las siguientes respuestas posibles:

  • Genearlly, discrete, one-time events

  • Overlapping activities that occur throughout the project

  • Overlapping activities that generally occur at the same level of intensity within each phase of the project.

  • Discrete, repetative events that occur generally at the same level of intensity throughout each phase of the project.

Explicación

Pregunta 26 de 198

1

Decomposition is:

Selecciona una de las siguientes respuestas posibles:

  • Creating subproject to ensure scope

  • Organizing and defining the complete scope

  • Subdividing project scope & deliverables into more manageable components

  • Documents planning assumptions

Explicación

Pregunta 27 de 198

1

You are exactly half way through a construction project when the customer insists that you add a third entry way. What process will you need to follow to make the updates?

Selecciona una de las siguientes respuestas posibles:

  • Validate scope

  • Brainstorming

  • Control scope

  • Collect requirements

Explicación

Pregunta 28 de 198

1

What process group determines how the scope is defined?

Selecciona una de las siguientes respuestas posibles:

  • Create WBS

  • Control scope

  • Plan scope management

  • Define scope

Explicación

Pregunta 29 de 198

1

Requirements must be:

Selecciona una de las siguientes respuestas posibles:

  • A component of change control

  • A validated for conformity as part of the project scope statement

  • An out put of the Validate Scope process

  • Measureable

Explicación

Pregunta 30 de 198

1

All of the following are tools for collecting requirements EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • Focus groups

  • Observations

  • Interviews

  • Quality assurance

Explicación

Pregunta 31 de 198

1

The process that documents stakeholder needs to meet the projects objectives are:

Selecciona una de las siguientes respuestas posibles:

  • Decomposition

  • WBS

  • Validate scope

  • Collect requirements

Explicación

Pregunta 32 de 198

1

Acceptance Criteria is:

Selecciona una de las siguientes respuestas posibles:

  • Part of the lessons learned

  • Unique & verifiable product, result or capability for a product

  • A set of conditions that is required to be met before deliverables are accepted.

  • Given by the PMO

Explicación

Pregunta 33 de 198

1

The project scope statement is:

Selecciona una de las siguientes respuestas posibles:

  • Determining, documenting, and managing stakeholder needs and requirements.

  • Set of conditions that is required to be met before deliverables are accepted.

  • The features and functions that characterize a project.

  • Description of the project, major deliverables, assumptions and constraints

Explicación

Pregunta 34 de 198

1

The WBS is:

Selecciona una de las siguientes respuestas posibles:

  • Project schedule components organized by work package

  • Work breakdown system

  • Project document updates

  • a hierarchical decomposition of the total scope of work to be carried out by the project team

Explicación

Pregunta 35 de 198

1

The lowest level of WBS components are:

Selecciona una de las siguientes respuestas posibles:

  • Quality requirements

  • Acceptance criteria

  • WBS dictionary

  • Work packages

Explicación

Pregunta 36 de 198

1

The project scope statement includes all of the following except:

Selecciona una de las siguientes respuestas posibles:

  • Scope baseline

  • Scope description

  • Deliverable

  • Acceptance criteria

Explicación

Pregunta 37 de 198

1

One of the outputs for the validate scope process is:

Selecciona una de las siguientes respuestas posibles:

  • Acceptance criteria

  • Resources required

  • Description of work

  • Accepted deliverables

Explicación

Pregunta 38 de 198

1

Which of the following provides more detailed information?

Selecciona una de las siguientes respuestas posibles:

  • Scope statement

  • Scope baseline

  • WBS

  • WBS dictionary

Explicación

Pregunta 39 de 198

1

You are the leader of the Project Management Office for your company. One day, an experienced Project Manager asks why he should go to the trouble of creating a Work Breakdown Structure for his new project. The best answer would be:

Selecciona una de las siguientes respuestas posibles:

  • It is optional

  • It is a legal requirement for external projects

  • It will help you organize project deliverables & work

  • It helps to verify project quality

Explicación

Pregunta 40 de 198

1

What is the purpose of the validate scope process?

Selecciona una de las siguientes respuestas posibles:

  • Collect requirements for the project

  • Make needed changes to the project charter

  • Acceptance of the project deliverables

  • Create WBS

Explicación

Pregunta 41 de 198

1

Create WBS is in which process group?

Selecciona una de las siguientes respuestas posibles:

  • Execution

  • Monitoring & control

  • Initiation

  • Planning

Explicación

Pregunta 42 de 198

1

Gold plating is:

Selecciona una de las siguientes respuestas posibles:

  • Decreasing risk by providing project safeguards

  • Changing requirements to improve the project

  • Giving a customer more than they want

  • Taking features away to keep costs down

Explicación

Pregunta 43 de 198

1

Project scope is:

Selecciona una de las siguientes respuestas posibles:

  • Making sure there is no gold plating in the project

  • The value created by completing a project under budget and on schedule

  • Determining, documenting & managing stakeholder needs and requirements

  • Work performed to deliver a product, service or results with specified features and functions

Explicación

Pregunta 44 de 198

1

What is the WBS typically used for?

Selecciona una de las siguientes respuestas posibles:

  • Defines the stakeholder list

  • Identifies the logical person to be the sponsor

  • Defines the level of reporting that the seller provides the buyer

  • Organizes & defines the work elements required to create the required deliverables

Explicación

Pregunta 45 de 198

1

Which of the following processes is not an output of the control scope process?

Selecciona una de las siguientes respuestas posibles:

  • Work performance information

  • Change requests

  • Project document updates

  • Accepted deliverables

Explicación

Pregunta 46 de 198

1

You are managing a global project that involves stakeholders and several international locations. You are likely to consult the WBS dictionary to find:

Selecciona una de las siguientes respuestas posibles:

  • Strengths, weaknesses, opportunities, and threats of key stakeholders and their impact upon the WBS.

  • Detail deliverable, activity, and scheduling information about each component in the WBS.

  • Accepted deliverables

  • High level task information for the schedule management plan

Explicación

Pregunta 47 de 198

1

The following is an example of a constraint associated with the project scope that limits the team's options and scope definition:

Selecciona una de las siguientes respuestas posibles:

  • Threat of a strike

  • Quality of analysis

  • Predefined budget or any imposed dates/schedule milestones that are issued by the customer or performing organization.

  • Existing relationships with sellers, suppliers, or others in the supply chain

Explicación

Pregunta 48 de 198

1

An output of the define scope process is:

Selecciona una de las siguientes respuestas posibles:

  • WBS

  • Scope & schedule delays control plan

  • Project scope statement

  • Resource breakdown structure

Explicación

Pregunta 49 de 198

1

The difference between the Project Charter and the Project Scope Statement is:

Selecciona una de las siguientes respuestas posibles:

  • The Project Scope Statement lists high level technical requirements and regulatory constraints.

  • The Project Scope Statement provides a high level description of scope elements.

  • The Project Charter provides a high level description of scope elements.

  • The Project Charter lists project deliverables in smaller, more manageable components.

Explicación

Pregunta 50 de 198

1

Control scope:

Selecciona una de las siguientes respuestas posibles:

  • Updates the WBS dictionary to ensure all tasks are accounted for

  • Ensures risks are mitigated

  • Plans how to determine scope

  • Manages changes to the scope baseline

Explicación

Pregunta 51 de 198

1

Plan schedule management is:

Selecciona una de las siguientes respuestas posibles:

  • Identifying and documenting logical relationships among project activities.

  • Analyzing activity sequences to create the project schedule baseline.

  • Monitoring the status of project activities to ensure they are performing to expected specifications in regards to project constraints.

  • Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule.

Explicación

Pregunta 52 de 198

1

The duration of a milestone is:

Selecciona una de las siguientes respuestas posibles:

  • 0 days

  • 1 days

  • 10 days

Explicación

Pregunta 53 de 198

1

What is the best tool for determining the overall length of a project?

Selecciona una de las siguientes respuestas posibles:

  • WBS

  • Precedence diagram

  • Expert judgement

  • Pie chart

Explicación

Pregunta 54 de 198

1

The critical path is:

Selecciona una de las siguientes respuestas posibles:

  • The shortest sequence duration

  • The sequence of activities that are determined to be key activities for successful project execution

  • The path with the highest number of activities

  • The shortest amount of time you can get the project done in

Explicación

Pregunta 55 de 198

1

The maximum amount of slack in the critical path is:

Selecciona una de las siguientes respuestas posibles:

  • +1

  • -1

  • 0

Explicación

Pregunta 56 de 198

1

The Critical Path has a duration of 10. There is an independent sequence, XYZ. Activity X has a duration of 2. Activity Y has a duration of 3. Activity Z has duration of 2. The EAC is 4000. The total float of XYZ is:

Selecciona una de las siguientes respuestas posibles:

  • 0

  • 3

Explicación

Pregunta 57 de 198

1

To complete your project on time, you ask for additional overtime for your project team. This is an example of:

Selecciona una de las siguientes respuestas posibles:

  • Fast tracking

  • Crashing

  • Critical chain

  • Schedule network analysis

Explicación

Pregunta 58 de 198

1

Lag is:

Selecciona una de las siguientes respuestas posibles:

  • The time an activity will start sooner than its dependency

  • Determined by the critical chain

  • The time when an activity is dependent on another activity to start at the same time

  • The time an activity will start later than its dependency

Explicación

Pregunta 59 de 198

1

You ask your construction manager how long it will take to complete the new server room. He gives you a likely estimate of 6 weeks, but says it may take as long as 10 weeks. He may be able to get it done in 4 weeks if everything goes well. Calculate your PERT estimate of how long it will take to complete the server room.

Selecciona una de las siguientes respuestas posibles:

  • 20 weeks

  • 6.3 weeks

  • 6 weeks

  • 4.6 weeks

Explicación

Pregunta 60 de 198

1

The method where buffers are added to each activity to account for resource availability is:

Selecciona una de las siguientes respuestas posibles:

  • Critical path

  • Resource leveling

  • Critical chain

  • Crashing

Explicación

Pregunta 61 de 198

1

A benefit of bottom-up estimating is:

Selecciona una de las siguientes respuestas posibles:

  • Determines resources need to schedule the project

  • Ability to automate your estimate

  • Allows for what-if analysis

  • A more accurate estimate

Explicación

Pregunta 62 de 198

1

One of the outputs of the Develop Schedule process group that helps create the Project Management plan is:

Selecciona una de las siguientes respuestas posibles:

  • Sequence activities

  • Work package acceptance criteria

  • Schedule baseline

  • Scope baseline

Explicación

Pregunta 63 de 198

1

The minimum project duration is 6 months. Another path, series ABCD, will take 4 months to complete. In addition, series EFG will take 2 months. How much float is in ABCD?

Selecciona una de las siguientes respuestas posibles:

  • 4 months

  • 0 months

  • 2 months

  • 12 months

Explicación

Pregunta 64 de 198

1

Which of the following allows you to accomplish tasks in parallel when they normally would be done in sequence?

Selecciona una de las siguientes respuestas posibles:

  • Fast tracking

  • Critical chain

  • Resource leveling

  • Crashing

Explicación

Pregunta 65 de 198

1

Analogous estimating is a technique for estimating the duration or cost of an activity or project using historical data from a similar activity or project. What is the disadvantage of this technique?

Selecciona una de las siguientes respuestas posibles:

  • More costly

  • Takes more time

  • Requires using PERT

  • Less accurate

Explicación

Pregunta 66 de 198

1

Your project will run through the summer when your employees generally take vacation. To account for the risk of lower resource availability in your project plan, you could use:

Selecciona una de las siguientes respuestas posibles:

  • Critical chain

  • Crashing

  • Resource leveling

  • Fast tracking

Explicación

Pregunta 67 de 198

1

You need Activity A in your project plan to start 3 days before Activity B. Activity B would be called:

Selecciona una de las siguientes respuestas posibles:

  • Lag

  • Lead

  • Critical chain

Explicación

Pregunta 68 de 198

1

You are creating the Schedule Baseline for a multi-national government pipeline project that will deliver oil faster and cheaper. You need to know how long it will take to build the new capacity. Who would you consult to determine the time required?

Selecciona una de las siguientes respuestas posibles:

  • Government experts

  • Project sponsor

  • Scrum master

  • The people that will be doing the work

Explicación

Pregunta 69 de 198

1

An example of a finish to finish relationship is:

Selecciona una de las siguientes respuestas posibles:

  • Rocket fuel tanks that must be filled prior to launch

  • A dinner cruise that sells tickets up until departure

  • Dinner when all of the food is ready at the same time

  • Drag racing

Explicación

Pregunta 70 de 198

1

Parametric estimating:

Selecciona una de las siguientes respuestas posibles:

  • Accounts for risk

  • Is where an algorithm is used to calculate cost or duration based on historical data

  • Focuses on planning at a daily activity level

Explicación

Pregunta 71 de 198

1

In rolling wave planning:

Selecciona una de las siguientes respuestas posibles:

  • Focus is maintained on long-term objectives, allowing near-term objectives to be rolled out as part of the ongoing wave of activities.

  • The work to be accomplished in the near term is planned in detail, the work in the more distant future is planned at a higher level.

Explicación

Pregunta 72 de 198

1

Analogous duration estimating is:

Selecciona una de las siguientes respuestas posibles:

  • Frequently used to estimate project duration when there is a limited amount of detailed information about the project

  • A bottom up estimating technique

  • Based on multiple duration estimating

  • Generally more accurate than other duration estimating methods when expert judgement is used

Explicación

Pregunta 73 de 198

1

To enter logical dependencies in MS project you enter the dependency in which column:

Selecciona una de las siguientes respuestas posibles:

  • Predecessor

  • Resource

  • Linkages

  • Critical chain

Explicación

Pregunta 74 de 198

1

Outputs from the Estimate Activity Resources process include:

Selecciona una de las siguientes respuestas posibles:

  • Activity resource requirements

  • Salary schedules for various project human resources

  • Risk register

  • Activity list

Explicación

Pregunta 75 de 198

1

An example of a mandatory dependency is:

Selecciona una de las siguientes respuestas posibles:

  • A dependency established based on knowledge of best practices within a particular application area

  • A dependency established based on some unusual aspect of the project where a specific sequence is desired

  • On a construction project, to erect the superstructure only after the foundation has been built.

  • On a software development project, to start design only after completion and approval of all project requirements.

Explicación

Pregunta 76 de 198

1

Earned Value is:

Selecciona una de las siguientes respuestas posibles:

  • Actual cost of work scheduled

  • AC / % Complete

  • Measure of work expressed in terms of budget authorized for that work

Explicación

Pregunta 77 de 198

1

A SPI is 1.4 - your project is?

Selecciona una de las siguientes respuestas posibles:

  • Ahead of schedule

  • Over budget

  • Under budget

Explicación

Pregunta 78 de 198

1

You are 1 month into your project. You need to determine how much your project will cost when it is done. What Earned Value metric will you use to determine the cost?

Selecciona una de las siguientes respuestas posibles:

  • BAC

  • EAC

Explicación

Pregunta 79 de 198

1

Project XYZ has a Schedule Variance of -500. That means that:

Selecciona una de las siguientes respuestas posibles:

  • The SPI is 500

  • Your project is behind schedule

Explicación

Pregunta 80 de 198

1

Your EAC is 4000. The PV is 1000. The AC is 400. What is the ETC?

Selecciona una de las siguientes respuestas posibles:

  • -10

  • 10

  • 2600

  • 3600

Explicación

Pregunta 81 de 198

1

All of the following are processes included in Project Cost Management except:

Selecciona una de las siguientes respuestas posibles:

  • Determine budget

  • Estimate activity resources

  • Estimate costs

  • Control costs

Explicación

Pregunta 82 de 198

1

Planned value is:

Selecciona una de las siguientes respuestas posibles:

  • Actual cost of work

  • Realized cost of work

  • Authorized budget assigned to the scheduled work

  • Difference btwn earned value and actual cost

Explicación

Pregunta 83 de 198

1

If the earned value is 40,000, the planned value is 50,000, and the actual cost is 45,000, what is the cost performance index?

Selecciona una de las siguientes respuestas posibles:

  • 1.13

  • .88

  • 1.27

Explicación

Pregunta 84 de 198

1

In class, we discussed that in Initiation, a Rough Order of Magnitude estimate should be within what percent?

Selecciona una de las siguientes respuestas posibles:

  • + - 25%

  • + - 3%

  • + - 50%

Explicación

Pregunta 85 de 198

1

Your project is behind schedule and over budget. When calculating the project’s CPI, you will get:

Selecciona una de las siguientes respuestas posibles:

  • number greater than 1

  • number less than 1

Explicación

Pregunta 86 de 198

1

What metric will show how efficiently the project team is using time?

Selecciona una de las siguientes respuestas posibles:

  • PV

  • SPI

  • CPI

  • SV

Explicación

Pregunta 87 de 198

1

The output of the determine budget process is:

Selecciona una de las siguientes respuestas posibles:

  • Schedule

  • Cost forecasts

  • Cost management plan

  • Cost baseline

Explicación

Pregunta 88 de 198

1

During a project, earned value analysis is performed. You get the following numbers:

EV = 50,000 PV = 60,000 AC = 75,000

What are the correct results?

Selecciona una de las siguientes respuestas posibles:

  • CV = -25000 SV = -10000

  • CV 10000 SV= -15000

Explicación

Pregunta 89 de 198

1

There are 4 activities in your project. Activity A has a planned value of 20,000. Activity B has a planned value of 30,000. Activity C has a planned value of 10,000. Activity D has a planned value of 40,000. What is the BAC?

Selecciona una de las siguientes respuestas posibles:

  • 25000

  • 37000

  • 12500

  • 100000

Explicación

Pregunta 90 de 198

1

Determine the variance at completion with the following information:

SV = -50,000

Estimate at completion = 100,000

Budget at completion = 200,000

Selecciona una de las siguientes respuestas posibles:

  • 50000

  • 10000

  • 2

  • 1.5

Explicación

Pregunta 91 de 198

1

Direct costs are:

Selecciona una de las siguientes respuestas posibles:

  • Directly related to the project and can be controlled

  • Included in overhead costs

  • Excluded from the project budget

  • Part of activity cost estimates

Explicación

Pregunta 92 de 198

1

Which of the following processes do not belong to the Project Cost Management process group?

Selecciona una de las siguientes respuestas posibles:

  • Plan cost management

  • Control cost

  • Determine budget

  • Contingency reserve

Explicación

Pregunta 93 de 198

1

Cost estimation of individual work packages or activities is called:

Selecciona una de las siguientes respuestas posibles:

  • Bottom-up estimating

  • Analogous estimating

  • Three point estimation

  • Expert judgement

Explicación

Pregunta 94 de 198

1

The output of determine budget is:

Selecciona una de las siguientes respuestas posibles:

  • Cost management plan

  • Activity cost estimate

  • Cost baseline

Explicación

Pregunta 95 de 198

1

The earned value calculations for your project are:

BAC = 10,000 EAC = 5,000 ETC = 4,000

What is the VAC and will you be over or under budget?

Selecciona una de las siguientes respuestas posibles:

  • 6000 and over budget

  • 5000 and over budget

  • 1000 and over budget

  • 6000 and under budget

Explicación

Pregunta 96 de 198

1

Parametric estimating involves:

Selecciona una de las siguientes respuestas posibles:

  • Defining cost or duration parameters of the project lifecycle

  • Calculating the individual cost estimates or each work package & integrating them to obtain the total cost of the project

  • Using statistical relationship between relevant historical data and other variables to calculate a cost estimate for project work

Explicación

Pregunta 97 de 198

1

The EAC is based on:

Selecciona una de las siguientes respuestas posibles:

  • The actual costs incurred for work completed (AC) and the estimate to complete (ETC) the remaining work

  • The EV and the actual cost for work completed CV

  • The cost performance index (CPI) and the cost of variance (CV).

Explicación

Pregunta 98 de 198

1

Earned value management (EVM) is a commonly used:

Selecciona una de las siguientes respuestas posibles:

  • Analysis of the value of the equipment that has been installed in the project as of the status to date.

  • Analysis of the sum of the labor costs, which have been incurred on the project to date.

  • Method to assess performance management and progress for projects.

  • Method of measuring the amount of money that has been spent on the project to date.

Explicación

Pregunta 99 de 198

1

You're earned value management analysis indicates that your project is falling behind its baseline schedule. You know this because the cumulative EV is much:

Selecciona una de las siguientes respuestas posibles:

  • Higher than the AC

  • Higher than the PV

  • Lower than the PV

  • Lower than the CPI

Explicación

Pregunta 100 de 198

1

Item PV AC EV

1 10,000 11,000 10,000

2 9,000 8,000 7,000

3 8,000 8,000 8,000

4 7,000 7,000 5,000

Selecciona una de las siguientes respuestas posibles:

  • 1

  • 2

  • 3

  • 4

Explicación

Pregunta 101 de 198

1

Plan quality management is:

Selecciona una de las siguientes respuestas posibles:

  • Process of identifying quality requirements

  • Planning the cost of precision measurement

  • Identifying project grade

  • Auditing the quality requirements and results

Explicación

Pregunta 102 de 198

1

What would be the least effective tool or method to reduce quality cost?

Selecciona una de las siguientes respuestas posibles:

  • Statistical sampling

  • Inspection

  • Nominal group technique

  • Control charts

Explicación

Pregunta 103 de 198

1

Quality is:

Selecciona una de las siguientes respuestas posibles:

  • Measure of exactness

  • Assessment of correctness

  • Degree to which a set of inherent characteristics fulfill requirements

Explicación

Pregunta 104 de 198

1

The 3 quality processes in project quality management are:

Selecciona una de las siguientes respuestas posibles:

  • Determine quality, monitor quality, plan quality

  • Cost benefit analysis, cost of quality, cost of conformance

  • Plan quality management, control quality, perform quality assurance

Explicación

Pregunta 105 de 198

1

The Ishikawa Diagram tool is used to:

Selecciona una de las siguientes respuestas posibles:

  • Gather info on the frequency of poor quality

  • Help identify the actionable root cause of the problem

  • Describe the central tendency of a process

  • Show if a process is stable and predictable

Explicación

Pregunta 106 de 198

1

Grade is:

Selecciona una de las siguientes respuestas posibles:

  • Measure of exactness

  • Measure of correctness

  • Categorization of deliverables having the same functional use but different technical characteristics

Explicación

Pregunta 107 de 198

1

The cost of quality includes all of the following EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • Prevention costs

  • Returns

  • Raw materials

  • Customer service

Explicación

Pregunta 108 de 198

1

The quality management plan is an output of which process:

Selecciona una de las siguientes respuestas posibles:

  • Project quality management

  • Plan quality management

  • Control quality

Explicación

Pregunta 109 de 198

1

Increased prevention costs should result in:

Selecciona una de las siguientes respuestas posibles:

  • Increased frequency of external failures

  • High internal failure costs

  • Decreased internal and external failure costs

Explicación

Pregunta 110 de 198

1

Pareto diagrams:

Selecciona una de las siguientes respuestas posibles:

  • Are used to gather attributes data while performing inspections

  • Identify the vital few sources that are responsible for causing the most problems

  • Are used to monitor cost and schedule variances

Explicación

Pregunta 111 de 198

1

Perform quality assurance is:

Selecciona una de las siguientes respuestas posibles:

  • The processes and activities that will determine quality policies, objectives & responsibilities

  • Auditing the quality requirements and results from quality control measurements

  • Process of determining project grade

Explicación

Pregunta 112 de 198

1

Scatter diagrams:

Selecciona una de las siguientes respuestas posibles:

  • Show forces for and against change

  • Map operational details of procedures

  • Seek to explain changes in variable Y in relation to changes in X

Explicación

Pregunta 113 de 198

1

A project manager can use a control chart to determine:

Selecciona una de las siguientes respuestas posibles:

  • The central distribution of a statistical distribution

  • If the amount of prevention costs are increasing

  • If a process is stable or predictable

Explicación

Pregunta 114 de 198

1

The results of performing the control quality process are:

Selecciona una de las siguientes respuestas posibles:

  • Decreased costs

  • Stable processes

  • Verified deliverables

Explicación

Pregunta 115 de 198

1

An example of appraisal costs is:

Selecciona una de las siguientes respuestas posibles:

  • Rework

  • Warranties

  • Training

  • Inspections

Explicación

Pregunta 116 de 198

1

The perform quality assurance process is in:

Selecciona una de las siguientes respuestas posibles:

  • Execution

  • Planning

  • Monitor & Control

Explicación

Pregunta 117 de 198

1

Checksheets are:

Selecciona una de las siguientes respuestas posibles:

  • Used to organize facts in a manner that will facilitate the effective collection of useful data about a potential quality problem

  • Used to monitor cost & schedule variances

  • Used to describe the central tendency, dispersion, and the shape of the distribution

Explicación

Pregunta 118 de 198

1

Degree of quality should be:

Selecciona una de las siguientes respuestas posibles:

  • Inspected in

  • Planned in

  • SWOT

Explicación

Pregunta 119 de 198

1

Control Quality is:

Selecciona una de las siguientes respuestas posibles:

  • Comparing the cost of quality to the requirements

  • Achieving project objectives of scope, time & cost

  • Process of monitoring & recording results of quality activities to asses project performance

Explicación

Pregunta 120 de 198

1

Understanding, evaluating, defining & managing requirements are essential to satisfying:

Selecciona una de las siguientes respuestas posibles:

  • Customer expectations

  • The scope statement

  • Upper management

  • Functional requirements

Explicación

Pregunta 121 de 198

1

The quality management plan is a component of the ________________ that describes how the organization's quality policies will be implemented.

Selecciona una de las siguientes respuestas posibles:

  • WBS

  • Project scope

  • Project management plan

Explicación

Pregunta 122 de 198

1

The seven basic quality tools include all of the following EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • Calibration graphs

  • Pareto diagrams

  • Control charts

Explicación

Pregunta 123 de 198

1

Inspection is:

Selecciona una de las siguientes respuestas posibles:

  • Examination of a work product to determine if it conforms to documented standards

  • Documenting results of control quality activities

  • A validated deliverable required by the project

Explicación

Pregunta 124 de 198

1

Which of the following is true regarding precision and accuracy?

Selecciona una de las siguientes respuestas posibles:

  • Precision is a measure of correctness whereas accuracy is an assessment of exactness

  • Precision is a measure of exactness, whereas accuracy is an assessment of correctness.

Explicación

Pregunta 125 de 198

1

Project Human Resource Management includes the following processes:

Selecciona una de las siguientes respuestas posibles:

  • Acquire project team, develop project team, HR management plan, performance assessments

  • Plan HR team, manage project team, evaluate project team, identify project roles

  • Plan HR management, acquire project team, develop project team, project team

Explicación

Pregunta 126 de 198

1

The human resource management plan is an output of which process:

Selecciona una de las siguientes respuestas posibles:

  • Acquire project team

  • Plan HR management

  • Develop project team

  • Manage project team

Explicación

Pregunta 127 de 198

1

The best illustrate for your project teams reporting relationships you would use:

Selecciona una de las siguientes respuestas posibles:

  • Matrix chart

  • RACI chart

  • A hierarchical chart

Explicación

Pregunta 128 de 198

1

Which of the following is NOT one of toucans 5 stages of team development?

Selecciona una de las siguientes respuestas posibles:

  • Norming

  • Storming

  • Adjourning

  • Developing

Explicación

Pregunta 129 de 198

1

There is a critical disagreement between two of your project team members. You need to help them resolve the issue. To help them find a solution that is a win for both sides, you would use which technique for resolving conflict?

Selecciona una de las siguientes respuestas posibles:

  • Force

  • Withdraw

  • Collaborate

  • Smooth

Explicación

Pregunta 130 de 198

1

RACI stands for?

Selecciona una de las siguientes respuestas posibles:

  • Rational Accountable Creative Informed

  • Responsible Actionable Creative Independent

  • Responsible Accountable Consulted Informed

Explicación

Pregunta 131 de 198

1

The project manager:

Selecciona una de las siguientes respuestas posibles:

  • Performs the work of the project

  • The person assigned to lead the team that is responsible for achieving the project objectives

  • The person who provides the resources and support for the project

Explicación

Pregunta 132 de 198

1

A member of your team has broken one of the agreed upon ground rules, who should enforce the rule?

Selecciona una de las siguientes respuestas posibles:

  • PMO

  • Project Manager

  • All project team members

  • Sponsor

Explicación

Pregunta 133 de 198

1

The process of developing an appropriate approach and plan for project communications based on stakeholder’s needs, requirements, and available organizational assets is:

Selecciona una de las siguientes respuestas posibles:

  • Control communications

  • Plan communications management

  • Manage communications

  • Develop communications plan

Explicación

Pregunta 134 de 198

1

In addition to distributing information, the Manage Communications process is also concerned with:

Selecciona una de las siguientes respuestas posibles:

  • Making sure the information has been received and understood

  • Creating the project communications plan

  • Planning the correct channel to use to distribute the information

Explicación

Pregunta 135 de 198

1

For your new project, you need to produce a simple status update for your Sponsor. What information would you not want to include?

Selecciona una de las siguientes respuestas posibles:

  • Lessons learned

  • Current status

  • Risks

Explicación

Pregunta 136 de 198

1

As a Project Manager in a matrix environment, you do not have direct authority over your project team. However, your team likes you and enjoys working for you. You are relying on what type of influence?

Selecciona una de las siguientes respuestas posibles:

  • Formal

  • Referent

  • Expert

  • Reward

Explicación

Pregunta 137 de 198

1

What topic would likely be covered in the kick off meeting?

Selecciona una de las siguientes respuestas posibles:

  • Procurement plan

  • Lessons learned

  • Performance evaluations

  • Roles and responsibilities

Explicación

Pregunta 138 de 198

1

Mid-way through a project, your sponsor comes to you and asks for a monthly project status report to be produced that will help the executive team understand the progress being made on the project. What process are you in now?

Selecciona una de las siguientes respuestas posibles:

  • Plan communications management

  • Control communications

  • Communication models

  • Manage communications

Explicación

Pregunta 139 de 198

1

You have a virtual team working on your project. What is a disadvantage of having a team that is not all located in the same place?

Selecciona una de las siguientes respuestas posibles:

  • Cannot have kick off meetings

  • Opportunity for misunderstandings

  • Easy conflict resolution

Explicación

Pregunta 140 de 198

1

The PMO:

Selecciona una de las siguientes respuestas posibles:

  • Is a person/group that provides resources/support

  • Standardizes the project related governance

  • Is a collection of logically related project activities that culminates in the completion of one or more deliverables

Explicación

Pregunta 141 de 198

1

Your project team is beginning to work together and adjust their habits to support the team. They are beginning to trust each other more. What development stage is your team in?

Selecciona una de las siguientes respuestas posibles:

  • Forming

  • Withdraw

  • Forcing

  • Norming

Explicación

Pregunta 142 de 198

1

You are creating a weekly status update, what process are you in?

Selecciona una de las siguientes respuestas posibles:

  • Develop project team

  • Control communications

  • Manage communications

  • Plan communications management

Explicación

Pregunta 143 de 198

1

Your project team is well organized, interdependent and handles issues effectively. What stage are they in?

Selecciona una de las siguientes respuestas posibles:

  • Developing

  • Norming

  • Performing

Explicación

Pregunta 144 de 198

1

The HRMP should generally include all of the following EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • Staffing management plan

  • Project interfaces

  • Roles & responsibilities

  • Project organization charts

Explicación

Pregunta 145 de 198

1

Techniques and considerations for effective communications management generally includes all of the following EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • Employing organizational process assets to reduce risk

  • Facilitation techniques for building consensus

  • Listening techniques

Explicación

Pregunta 146 de 198

1

The acquisitions strategy for acquiring a project team consists of:

Selecciona una de las siguientes respuestas posibles:

  • Hiring consultants from the outside

  • Obtaining resources through ranking criteria

  • Acquiring members of the team from other teams within the organization

Explicación

Pregunta 147 de 198

1

The Acquire Project Team is the process of confirming human resource availability and obtaining the team necessary to complete project activities. The enterprise environmental factors that can influence this process generally include all of the following EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • Organizational structure

  • Multi-criteria decision analysis

  • Competency levels, prior experience & cost rate.

Explicación

Pregunta 148 de 198

1

Generally acknowledged techniques for resolving conflict include:

Selecciona una de las siguientes respuestas posibles:

  • Accept, compromise, attack & separate

  • Smooth compromise collaborate co-locate

  • Accommodate compromise force & collaborate

Explicación

Pregunta 149 de 198

1

Project risk is:

Selecciona una de las siguientes respuestas posibles:

  • A condition that causes negative impact to the project

  • A threat to the success of the project

  • An uncertain event that if it occurs has a positive or negative effect

Explicación

Pregunta 150 de 198

1

The strategy to address opportunities and seek to ensure the opportunity happens is:

Selecciona una de las siguientes respuestas posibles:

  • Avoid

  • Enhance

  • Exploit

Explicación

Pregunta 151 de 198

1

The risk register is an output of which project risk management process?

Selecciona una de las siguientes respuestas posibles:

  • Performing qualitative risk analysis

  • Perform quantitative risk analysis

  • Plan risk management

  • Identify risks

Explicación

Pregunta 152 de 198

1

The following process is in monitoring & control:

Selecciona una de las siguientes respuestas posibles:

  • Plan risk management

  • Control risks

  • Perform quant risk analysis

Explicación

Pregunta 153 de 198

1

Relies on anonymous feedback from experts through questionnaires and drives toward consensus

Selecciona una de las siguientes respuestas posibles:

  • Root cause analysis

  • Probability impact matrix

  • Delphi technique

  • Risk register

Explicación

Pregunta 154 de 198

1

The risk register should include:

Selecciona una de las siguientes respuestas posibles:

  • Identified risks & WBS number

  • Identified risks & potential responses

  • Risk categorization & identified risks

  • Identified risk & risk analysis

Explicación

Pregunta 155 de 198

1

Is used to determine the risk rating to help prioritize risks:

Selecciona una de las siguientes respuestas posibles:

  • Risk categorization

  • Risk register

  • Expected monetary value analysis

  • Probability & impact matrix

Explicación

Pregunta 156 de 198

1

Helps compare the relative importance & impact of variables that have a high degree of uncertainty to those that are more stable:

Selecciona una de las siguientes respuestas posibles:

  • Expected monetary analysis

  • Tornado diagram

  • Decision tree

  • Monte carlo technique

Explicación

Pregunta 157 de 198

1

Uses a computer to produce many simulations using random sampling to obtain probable results distribution:

Selecciona una de las siguientes respuestas posibles:

  • Expected monetary analysis

  • Monte Carlo technique

  • Decision tree diagram

  • Sensitivity analysis

Explicación

Pregunta 158 de 198

1

You are building a skyscraper in New York City. If the project falls behind schedule, you will lose millions of dollars in fees to the city. You want to shift the financial burden of the threat of fees to a third party. What strategy should you use?

Selecciona una de las siguientes respuestas posibles:

  • Mitigate

  • Avoid

  • Exploit

  • Transfer

Explicación

Pregunta 159 de 198

1

Your software project is given very good press in The Wall Street Journal. You want to make sure the chances for success are increased so you add more resources to the project. What strategy are you using?

Selecciona una de las siguientes respuestas posibles:

  • Share

  • Accept

  • Transfer

  • Enhance

Explicación

Pregunta 160 de 198

1

Qualitative risk analysis deals with:

Selecciona una de las siguientes respuestas posibles:

  • Developing options for risk responses

  • Numerically analyzing the effect of risks

  • Prioritizing risks

  • Monitoring residual risks

Explicación

Pregunta 161 de 198

1

Using Expected Monetary Value Analysis, calculate the average outcome for a project that has either a $300,000 profit and 30% chance of achieving it, or a $100,000 loss and 70% chance of having that happen.

Selecciona una de las siguientes respuestas posibles:

  • 160,000

  • 20,000

  • 400,000

  • 90,000

Explicación

Pregunta 162 de 198

1

Process of determining options to reduce threats and enhance opportunities:

Selecciona una de las siguientes respuestas posibles:

  • Identify risks

  • Control risks

  • Plan risk response

  • Perform qualitative risk analysis

Explicación

Pregunta 163 de 198

1

Your Risk Register calls out several risks, including not having enough resources available to complete the software in time to ship it. You check in weekly with the developers to make sure the software will be completed in time. What process are you in?

Selecciona una de las siguientes respuestas posibles:

  • Plan risk management

  • Control risks

  • Plan risk response

  • Identify risks

Explicación

Pregunta 164 de 198

1

When using the Delphi technique, you should:

Selecciona una de las siguientes respuestas posibles:

  • Have a unanimous decision

  • Encourage brainstorming

  • Not share the responses through the entire process

  • Make sure the participants are experts

Explicación

Pregunta 165 de 198

1

In the plan risk responses process, an accept strategy for a negative risk or threat indicates that the project team has decided:

Selecciona una de las siguientes respuestas posibles:

  • To agree with the PM

  • To eliminate a specific threat or risk

  • Not to change the project management plan to deal with a risk, or is unable to identify any other suitable response strategy

Explicación

Pregunta 166 de 198

1

As an update of the control risks process, an updated risk register generally includes some or all of the following EXCEPT:

Selecciona una de las siguientes respuestas posibles:

  • The WBS

  • Actual outcomes of the projects risks

  • Outcomes of risk reassessments

Explicación

Pregunta 167 de 198

1

To be successful, an organization should be committed to addressing risk management:

Selecciona una de las siguientes respuestas posibles:

  • Proactively throughout the entire project

  • As soon as time & cost estimates are ready

  • As early as possible in the execution phase

Explicación

Pregunta 168 de 198

1

The primary output of the identify risks process is the:

Selecciona una de las siguientes respuestas posibles:

  • Risk register

  • Risk mitigation plan

  • List of the corrective actions

Explicación

Pregunta 169 de 198

1

The mitigate risk response strategy:

Selecciona una de las siguientes respuestas posibles:

  • Reduces the probability of occurrence or impact of a threat

  • Seeks to make sure the risk negative response happens

  • Seeks to eliminate the threat or protect the project from its impact

Explicación

Pregunta 170 de 198

1

The probability and impact risk assessment thresholds:

Selecciona una de las siguientes respuestas posibles:

  • Show quantitative risk results for the project

  • Are determined by the # of threats

  • Are unique for each organization

Explicación

Pregunta 171 de 198

1

Sensitivity analysis helps determine which risks have the most potential impact on the project. How is that info shown?

Selecciona una de las siguientes respuestas posibles:

  • Probability and impact matrix

  • Cost/probability chart

  • Tornado diagram

Explicación

Pregunta 172 de 198

1

Expected monetary value (EMV) analysis has all of the following characteristics except:

Selecciona una de las siguientes respuestas posibles:

  • It is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen.

  • The EMV of opportunities are generally expressed as positive values, whereas those of threats are expressed as negative values.

  • EMV analysis cannot be used effectively in decision tree analysis unless a risk-averse assumption is made.

Explicación

Pregunta 173 de 198

1

An output of perform qualitative risk analysis is:

Selecciona una de las siguientes respuestas posibles:

  • Project documents updates

  • Risk management plan

  • Risk register

  • Meetings

Explicación

Pregunta 174 de 198

1

Identify stakeholders is a part of which process group?

Selecciona una de las siguientes respuestas posibles:

  • Initiation

  • Execution

  • Planning

Explicación

Pregunta 175 de 198

1

You are evaluating various bids to determine which vendor you will purchase your building materials from. What process are you in?

Selecciona una de las siguientes respuestas posibles:

  • Plan procurement management

  • Conduct procurements

  • Planning

Explicación

Pregunta 176 de 198

1

You are a Project Manager constructing a large building to store your company’s work vehicles. You know exactly what you want built. It will only take 3 weeks to build. In this case, what type of contract would you want to use?

Selecciona una de las siguientes respuestas posibles:

  • Hybrid

  • Time & material

  • Fixed price

  • Cost reimbursable

Explicación

Pregunta 177 de 198

1

You a working on a project that will augment the staff in grade schools by providing temporary substitute teachers for the school district. To account for fixed overhead costs and hourly wages, the best contract type would be:

Selecciona una de las siguientes respuestas posibles:

  • Fixed cost

  • Cost reimbursable

  • Time & material

Explicación

Pregunta 178 de 198

1

The stakeholder register is an output of which process?

Selecciona una de las siguientes respuestas posibles:

  • Stakeholder analysis

  • Plan stakeholder management

  • Manage stakeholder engagement

  • Identify stakeholders

Explicación

Pregunta 179 de 198

1

In the Power/Interest stakeholder grid, which quadrant should you spend the most time on and provide the most attention?

Selecciona una de las siguientes respuestas posibles:

  • Low p low I

  • High p low I

  • High p high I

Explicación

Pregunta 180 de 198

1

The stake holder register should contain at least the following:

Selecciona una de las siguientes respuestas posibles:

  • Identification information, risk analysis, assessment matrix

  • Stakeholder engagement data flow diagram, risk analysis, assessment matrix

  • Identification information, assessment information, stakeholder classification

  • Stakeholder management plan, stakeholder classification, risk analysis

Explicación

Pregunta 181 de 198

1

Lessons learned:

Selecciona una de las siguientes respuestas posibles:

  • Collects project performance data

  • Shows how events were addressed or should be addressed in the future with the purpose of improving future performance

  • An event to plan organize and direct work

Explicación

Pregunta 182 de 198

1

If a contract has an incentive fee, financial incentives are dependent on:

Selecciona una de las siguientes respuestas posibles:

  • Inflation

  • Legal penalties

  • Agreed upon metrics

Explicación

Pregunta 183 de 198

1

During closing, you should hand off the project to:

Selecciona una de las siguientes respuestas posibles:

  • PMO

  • Exec Sponsor

  • End User

  • The group that will own or be responsible on a daily basis

Explicación

Pregunta 184 de 198

1

In the agile framework, individuals and interactions are valued more than:

Selecciona una de las siguientes respuestas posibles:

  • Deliverables

  • Methodology

  • Processes & tools

Explicación

Pregunta 185 de 198

1

You are a Project Manager for Apple and your latest project is developing the new iPhone 6Z. You need to build a solar battery that will enable the phone to go without charging for 2 weeks at a time. Critical to this project is the new chip design that requires a special assembly line to produce. This new assembly line is not a core competency of Apple. You need to decide what type of contract will work best to acquire the new chip. What procurement process are you in?

Selecciona una de las siguientes respuestas posibles:

  • Conduct procurements

  • Identify stakeholders

  • Plan procurement management

Explicación

Pregunta 186 de 198

1

Which type of contract is the riskiest for a contractor?

Selecciona una de las siguientes respuestas posibles:

  • Cost plus fee

  • Time & materials

  • Firm fixed price

Explicación

Pregunta 187 de 198

1

The output of the conduct procurements process is:

Selecciona una de las siguientes respuestas posibles:

  • Procurement management plan

  • Closed procurements

  • Signed contract agreement

  • Work performance info

Explicación

Pregunta 188 de 198

1

Your project Sponsor is actively engaged in your project and understands the benefits and impacts. How would you classify the Sponsor as a stakeholder?

Selecciona una de las siguientes respuestas posibles:

  • Resistant

  • Expert

  • Leading

Explicación

Pregunta 189 de 198

1

During the Closing process, you should do all of the following except

Selecciona una de las siguientes respuestas posibles:

  • Conduct lessons learned

  • Gain approval to close

  • Classify stakeholders

Explicación

Pregunta 190 de 198

1

Enterprise environ factors are:

Selecciona una de las siguientes respuestas posibles:

  • Outputs

  • Project management systems

  • Conditions that influence or constrain

Explicación

Pregunta 191 de 198

1

Who represents the customer in SCRUM?

Selecciona una de las siguientes respuestas posibles:

  • PM

  • PT

  • Product Owner

  • Scrum master

Explicación

Pregunta 192 de 198

1

Procurement is:

Selecciona una de las siguientes respuestas posibles:

  • Acquiring goods & services

  • Reviewing contracts

  • Obtaining the resources you need for the project

Explicación

Pregunta 193 de 198

1

The best measure for progress in agile is:

Selecciona una de las siguientes respuestas posibles:

  • Design

  • Working software

  • Technical excellence

Explicación

Pregunta 194 de 198

1

Cost plus fixed fee contracts (CPFF) have all of the following characteristics except:

Selecciona una de las siguientes respuestas posibles:

  • Seller receives a fixed-fee payment calculated as the initial estimated project cost.

  • The fee is paid only for completed work and does not change due to seller performance unless the project scope changes.

Explicación

Pregunta 195 de 198

1

You are involved in the process of communicating and working with stakeholders to meet their needs/expectations, address issues as they occur, and foster appropriate stakeholder engagement in project activities throughout the project life cycle. This is known as:

Selecciona una de las siguientes respuestas posibles:

  • Plan stakeholder management

  • Communicate with stakeholders

  • Control stakeholders

  • Manage stakeholder engagement

Explicación

Pregunta 196 de 198

1

Manage Stakeholder Engagement involves all of the following activities except:

Selecciona una de las siguientes respuestas posibles:

  • Managing stakeholder expectations through negotiation and communication

  • Avoiding potential concern that have not yet become issues

  • Anticipating future problems

  • Clarifying & resolving identified issues

Explicación

Pregunta 197 de 198

1

Control Stakeholder Engagement tools and techniques include all of the following except:

Selecciona una de las siguientes respuestas posibles:

  • Behavior modification analysis

  • Expert judgement

  • Meetings

  • Information management systems

Explicación

Pregunta 198 de 198

1

Outputs from the Close Procurements Process generally include all of the following except:

Selecciona una de las siguientes respuestas posibles:

  • Deliverable acceptance

  • Closed procurements

  • Lessons learned

  • The contractors working proposal

Explicación