Jose Ramon Sagarna
Test por , creado hace más de 1 año

Medium (Kanban Board) Kanbanize Test sobre Kanban Board Quiz, creado por Jose Ramon Sagarna el 29/12/2015.

94
1
0
Jose Ramon Sagarna
Creado por Jose Ramon Sagarna hace más de 8 años
Cerrar

Kanban Board Quiz

Pregunta 1 de 7

1

When a column has a number like 3/2 , it means...

Selecciona una de las siguientes respuestas posibles:

  • That the limit has not been surpassed , as the limit is 3

  • That there are 3 tasks when the limit is a maximum of 2, but this should be an exceptional situation

  • It's not possible that this happens as the limit is 2 and no more than 2 cards could be managed at the same time.

Explicación

Pregunta 2 de 7

1

Rellena los espacios en blanco para completar el texto.

A is the status of the card being managed, which is tied to certain policies to be moved to the next .
A is a way to differentiate the cards in different groups or projects.

Explicación

Pregunta 3 de 7

1

A task that is under investigation by Development should be under the column
A task that needs more info should be under the column
A task should always be created in the area
The In Progress Column consists of SOLVING AND WAITING TO BE SOLVED
Only a tasks that has a Solving Reason should be moved to

Arrastra y suelta para completar el texto.

    SOLVING
    REQUESTED
    WAITING TO BE SOLVED
    BACKLOG
    INVESTIGATING
    Closed
    RESOLVING

Explicación

Pregunta 4 de 7

1

We consider a task info is completed by EuroMIS when AT LEAST the following are fullfiled...

Selecciona una o más de las siguientes respuestas posibles:

  • Service Level

  • Priority

  • Size

  • PBI

  • Deadline

  • Environment

  • Solving Reason

  • External Link

  • Agent

  • Repro Rate

Explicación

Pregunta 5 de 7

1

The FIFO rule means....

Selecciona una de las siguientes respuestas posibles:

  • We should have everything in the Backlog, save some time and start working every single card at the same time

  • We should work with 1 element, develop and finish it before starting with other.

  • FIrst Information, First Out, the first task that has information is the first one we should work with

  • First In Fx Online, FxOnline should always be the Priority

Explicación

Pregunta 6 de 7

1

If the limit of a column is surpassed, we should think of action the tasks in the overflown column before taking other tasks

Selecciona uno de los siguientes:

  • VERDADERO
  • FALSO

Explicación

Pregunta 7 de 7

1

Rellena los espacios en blanco para completar el texto.

Items in the column are being assessed to verify all the information is present.
ENTRY Policy: Items MUST be reproducible, have a T Shirt size, priority and class of service assigned.
EXIT Policy: All the information required is fulfilled.

Buffer column when Solving's WIP is full

EXIT Policy: Solving WIP allows more Items
Items in the column are being closed as the outcome is provided
EXIT Policy:
Submitter has acknowledged the receipt of the communication and agrees on the outcome
EuroMIS has been informed on the communication of the outcome

Items in the column are being investigated to determine if QA/DEV are to work in them or can be closed.
EXIT Policy:
We are sure it's a QA problem and the problem hasn't been solved yet. = Solving
We are sure it's a DEV problem that hasn't been solved yet = Closed
We are sure it's not a QA/DEV problem AND the requester agrees on the outcome = Closed

Items in the column are being solved with a defined outcome
EXIT Policy
We are sure it's a QA problem and the outcome has been transmitted and agreed with the requester
We are sure it's a DEV problem, a bug is created in TFS or a SCR has been created.
SOLVING REASON custom field has been fullfiled

Explicación