The following are deliverables produced by the Architect:
Conceptual Mass Model
Preliminary Design Coordination Report between Architecture model & Structural model
Clash detection & resolution report between Architecture, Structure & MEP models
RFI Resolutions
All of the above
Current BIM implementation is still based on a Hybrid method
To generate the topography model, the Architect will use topography drawings of the existing site, provided by the Registered Surveyor / Civil Engineers
During Schematic design phase, the Architect do not produce
Layout plans 1:200 scale
Outline structural and mechanical design
Fabrication details
Generic wall / window / door components
During Detail Design phase, the Architect would produce:
Layout plans showing layer construction 1:100 – 1:50 scale
Produce 1:20 – 1:5 detail drawings
Construction sequencing
During Details Design phase, Model Exchange is done continuously as the design and project progresses. Early clash detections are performed to lessen conflict of elements before construction.
When continue and develop Architecture model to Contractor’s model, basic elements required from the Architecture model are:
X, Y, Z Coordinates
Topography (Existing Site Model)
Topography (Proposed Site Model)
Grid and Level
Building components: Wall, Architectural Column, Door, Window, Slab/ Floor, Ceiling, Fixtures, Furniture (optional), Facade, Railing, etc.