PMP Prep quiz

Pregunta 1 de 10

1

Most common cause of conflicts in a project is:

Selecciona una de las siguientes respuestas posibles:

  • Schedules

  • Technical Opinions

  • Personal Issues

  • Project Priorities

Explicación

Pregunta 2 de 10

1

You are the Project Manager of the XYZ project. You want to find the planned expenses for next month. Which document do you need to refer to?

Selecciona una de las siguientes respuestas posibles:

  • Cost Management Plan

  • Cost Baseline

  • Cost Control Plan

  • Cost Variance report

Explicación

Pregunta 3 de 10

1

You are working on the project of painting of your house. You identify a dependency that the painting of roof should begin only after two days of completion of painting of walls. This is an example of :

Selecciona una de las siguientes respuestas posibles:

  • Lag

  • Lead

  • Slack

  • Float

Explicación

Pregunta 4 de 10

1

Control Procurements is a process in the Project Procurement Management Knowledge area.

Selecciona uno de los siguientes:

  • VERDADERO
  • FALSO

Explicación

Pregunta 5 de 10

1

Which of the following theory was suggested by Deming?

Selecciona una de las siguientes respuestas posibles:

  • Apply continuous small improvements to reduce costs and ensure consistency.

  • Marginal Analysis

  • Expectancy theory - people expect to be rewarded for their efforts.

  • Plan-do-check-act to improve quality.

Explicación

Pregunta 6 de 10

1

You are required to estimate the time to paint a large wall. You know it takes two hours to paint one square foot of wall. The wall has an area of 30 square foot. So you estimate that it will take 60 hours to paint the wall. Which estimation model are you using?

Selecciona una de las siguientes respuestas posibles:

  • Bottom-up

  • Parametric modeling

  • Analogous

  • Expert judgment

Explicación

Pregunta 7 de 10

1

In which process of Project Risk Management knowledge area are numeric values assigned to probabilities and impact of risks?

Selecciona una de las siguientes respuestas posibles:

  • Perform Qualitative Risk Analysis

  • Perform Quantitative Risk Analysis

  • Perform Numeric Risk Analysis

  • Plan Risk Response

Explicación

Pregunta 8 de 10

1

Which of the following is an output of the Identify Risks process.

Selecciona una de las siguientes respuestas posibles:

  • Lessons Learned

  • Checklists

  • Risk Register

  • SWOT Analysis

Explicación

Pregunta 9 de 10

1

The process of Conduct Procurements is part of the planning phase.

Selecciona uno de los siguientes:

  • VERDADERO
  • FALSO

Explicación

Pregunta 10 de 10

1

Which process identifies the project manager?

Selecciona una de las siguientes respuestas posibles:

  • Develop Project Management Plan

  • Develop Project Charter

  • Define Scope

  • Select Project Process

Explicación