SAB4#126 Contingency Types (risks)

Description

Rita 447-448
anesio.benna
Mind Map by anesio.benna, updated more than 1 year ago
anesio.benna
Created by anesio.benna over 9 years ago
8
0

Resource summary

SAB4#126 Contingency Types (risks)
  1. Residual Risks
    1. These are the risks that REMAIN after risk response planning. So after you have done all recomended actions, some risks remain. Those residual risks that are passively accepted should be properly documented and reviewed throughout the project to see if their ranking has changed.
    2. Secondary Risks
      1. Any NEW risks CREATED by the implementation of selected risk resonses should also be analyzed as part of risk response planning. The discovery of secondary risks may require aditional risk response planning.
      Show full summary Hide full summary

      Similar

      English Terminology for AS Level
      rhigzy
      AS Psychology - Research Methods
      kirstygribbin
      Romeo and Juliet: Key Points
      mbennett
      Fractions
      Kayleigh Elkins
      A View from the Bridge Quotes
      Emma Payne
      IB Biology Topic 4 Genetics (SL)
      R S
      Health and Social Care
      Kelsey Phillips
      Frankenstein Key Quotes
      michelle.lau
      Computer science quiz
      Ryan Barton
      Relationships in A Streetcar Named Desire
      Emily Garvin-Howard
      Week 1: 28.01 - 01.02
      Marilia Ferreira