  • * Estimate Activity Durations is the process of estimating the numbers of work periods needed to complete individual activities with estimated resources. * Estimate how much time each Activity will take.
  1. Process: Estimate Activity Durations
    1. Process Group: Planning
      1. Knowledge Area: Time Management
        1. 1. Schedule Management Plan
          1. 2. Activity list
            1. 3. Activity attributes
              1. 4. Activity resources requirements
                1. Estimate Activities Resources
                2. 5. Resource Calendars
                  1. 6. Project Scope Statement
                    1. 7. Risk Register
                      1. 8. Resource breakdown structure RBS
                        1. Estimate Activities Resources
                        2. 9. EEF
                          1. 10. OPAs
                            1. 1. Expert Judgment

                              Anotações:

                              • Will come from your project team members who are familiar with the work that has to be done.
                              1. 2. Analogous Estimation (Top Down)

                                Anotações:

                                • Is when you look at activities from previous projects that were similar to this one and look at how long it took to do similar work before.
                                1. 3. Parametric Estimating

                                  Anotações:

                                  • Parametric estimating looks at the relationships between variables on an activity to calculate time or cost estimates.  The data can come  from historical records from previous projects, industry requirements, standard metrics, or other sources.
                                  1. Regression Analysis (scatter diagrams)
                                    1. Learning Curve
                                    2. 4. Three-Point estimating

                                      Anotações:

                                      • Statistically, there is a very small probability of completing a project on exactly any one date. As we know, things do not always go according to plan. With the three-point technique, estimators give an optimistic (0),  pessimistic (P), and most likely (M)  estimate for each activity.
                                      1. 5. Group decision-making techniques

                                        Anotações:

                                        • Involving team members in estimating can be beneficial on many levels. Those doing the work are most likely to have a good understanding of the time required to complete the effort.
                                        1. 6. Reserve Analysis

                                          Anotações:

                                          • Means adding extra time to the schedule (called a contingency reserve  or a buffer ) to account for extra risk.
                                          1. 1.- Activity duration estimates
                                            1. 2. Project Document Updates

                                              Semelhante

                                              Espanhol Básico
                                              Alessandra S.
                                              Introdução a Engenharia
                                              ismael-airoso
                                              MAPA MENTAL - METODOLOGIA DO ENSINO SUPERIOR
                                              ilda_silverio
                                              Dicas de Português para Concursos
                                              Rodrigo Pizetta
                                              Vestibular - Roteiro de Estudos
                                              GoConqr suporte .
                                              Enem 3
                                              Robson Bueno
                                              Revolução Industrial século XVIIl e XIX
                                              izabelamendeslop
                                              Revisão de Direito Penal
                                              Alice Sousa
                                              Liderança e Gestão de Equipes
                                              Pierre Curi
                                              Sistema Cardiovascular: Artérias, Veias e Capilares
                                              Natália Abitbol
                                              Revisão 1 - PROVA DE SARGENTO - MARINHA - EA-HSG - ( Com Verificação )
                                              Nilzeir Reis