SAB4#60 Leads & Lags
  1. LAG time is when you purposefully put a DELAY between the predecessor task and the successor
    1. Example: You need TO WAIT 3 days after pouring concrete to construct a frame from a house
      1. Activities Finish-to-Start
    2. LEAD time is when you give a successor task some time to getstarted BEFORE the predecessor finishes
      1. Example: "Team 2" can start reviewing the document "A" BEFORE "Team 1" has finished reviewing the document "X"
        1. Activities Start-to-Start
      2. The project management team determines the dependencies that may require a LEAD or a LAG to accurately define the logical relationship.
        1. The use of leads and lags should not replace schedule logic
          1. Activities and their related assumptions should be documented
            1. A lead or a lag CAN affect the project time duration
              1. Leads and Lags MUST be used SPECIALLY in crtical activities

                Semelhante

                verbos irregulares
                santosfilipe123
                IMPARARE ITALIANO.(APRENDA ITALIANO)
                Antonio de Moura Rodrigues
                Basic General Quiz
                Alessandra S.
                Classificação dos crimes
                simone ferreira
                Como Transformar sua Anotação em Suporte
                Alessandra S.
                Plano de Estudos com Mapas Mentais
                Alessandra S.
                Artigo Científico - estrutura
                alineadc
                HISTÓRIA REVOLUÇÃO FRANCESA
                neusamiotto
                Avaliação de Alunos
                Alessandra S.
                Geografia - Mapa do Brasil
                GoConqr suporte .
                CONSTITUIÇÃO
                Mateus de Souza