RFQ:
Is an ID number coming from Huawei Negotiation Platform.
https://esourcing.huawei.com
Once the Cost Estimate is approved by Honor Marketing Dpt. the Huawei Procurement Dpt. start with this process.
Once the RFQ link is generated UDG get an email invitation from Huawei Procurement to upload the accepted Cost Estimate on the platform.
Project Order or PO
Anotações:
After two or three weeks Huawei Procurement Dpt. produce the PO document.
UDG can find it on the SCS System (Supplier Collaboration System) or it is sent to us via email as a screenshot. POs can be hard to find in the system.
Project Execution
Deliverables Preparation
Anotações:
On a monthly basis we send our client a pack called deliverables, this pack is composed by:
- Presentation with all the worked content done from UDG IC.
- Intercompany Timelogs & 3rd Party costs report.
- Generated 3rd Party costs invoices.
ISSUES
IC Deliverables not on time
IC Timelogs not from SAP, might be not accurate
IC Timelogs just once in month, no possible controlling
3r Party invoices documents not in SAP
IC Deliverables, IC Timelogs & IC 3rd Party Costs Invoices come in different emails
Deliverables in SCS uploading
Anotações:
Honor PM Team upload the Deliverbales Packs on the SCS system
Rejected
Not accurate
Wrong information
Client don't approve timelogs
Remake
Accepted
Anotações:
Honor Marketing Team
FAR Generation process
Anotações:
FAR or Final Acceptance Report is an PDF document. Honor Marketing Dpt. should send this Document to UDG Honor - PM's. There's no procurement involved on this step.
ISSUES
Honor Marketing Dept. delays
UDG cloud system links expires in 1 week, Honor takes more time
Invoice Pack Preparation
Anotações:
The Invoice Pack is composed by:
- PO (pdf file)
- FAR: respective month (pdf file)
- Invoice: (excel file prepred by PM)
- Report: Timelogs & 3rd Party (excel file)
- Settlement List (word file)
- Deliverables Presentation
Invoice Pack Sendout
Anotações:
This step is done by UDG Finance Dept. (SCS)
Rejected
Wrong PO
Wrong Amount
Pack is not complete
Remake
Accepted
Anotações:
Honor Marketing
Huawei open Invoiceable budget ticket
Anotações:
This step is done by Huawei Procuremnt Dept. (SCS)
Invoice uploading on Budget ticket on SCS
Anotações:
This step is done by UDG Finance Dept. (SCS)
Acceptance & PAYMENT
ISSUES
UDG PM team don't follow what happen after this point
sign FARs and send them back
Anotações:
Honor rates UDG against a table of results including recommendations for improvement. This needs to be signed off my UDG.
ISSUES
Can take more than 2 weeks after RFQ submission
One project can get more than one PO
PO can contain wrong information like names, amounts...
ISSUES
Could take more than 3 weeks
Honor Marketing & Huawei Procurement lack of communication