Project Management Final CH 1-10

Questão 1 de 200

1

Identify the example that would not usually be considered a project.

Selecione uma das seguintes:

  • building a house

  • developing a computer software application program

  • hosting a wedding reception

  • assembly line manufacturing of automobiles

Explicação

Questão 2 de 200

1

According to the authors, the prime objectives of project management are

Selecione uma das seguintes:

  • scope, cost, time

  • quality, scope, schedule

  • customer satisfaction, budget, schedule

  • cost, quality, customer satisfaction

Explicação

Questão 3 de 200

1

In a conventional project lifecycle, as work progresses, uncertainty about the expected outcome should

Selecione uma das seguintes:

  • become a constant

  • decrease

  • increase

  • be fully removed

Explicação

Questão 4 de 200

1

The attributes that characterize a project are

Selecione uma das seguintes:

  • purpose, repetition, inter-dependencies, consistency, uncertainty, conflict, and one¬time occurrence

  • life cycle, schedule, cost, uncertainty, independence, uniqueness, and purpose

  • resources, uniqueness, conflict, inter-dependencies, one-time occurrence, and finite duration,

  • purpose, life cycle, conflict, certainty, independence, performance, and finite duration

Explicação

Questão 5 de 200

1

The "stretched-5" pattern observed during the project lifecycle, for the most part, is a result of the

Selecione uma das seguintes:

  • changing levels of resources used during successive stages of the project lifecycle

  • changing attitudes of the people who work in the project

  • difficulty in performing the individual activities of a project

  • principle that work expands to fill the allotted time

Explicação

Questão 6 de 200

1

The desired outcomes or results of a project are called

Selecione uma das seguintes:

  • subgroups

  • work packages

  • subprojects

  • deliverables

Explicação

Questão 7 de 200

1

Earned value is based on the concept that the percentage of project completion is closely correlated with

Selecione uma das seguintes:

  • the number of levels in the project

  • relevance of the project

  • cost or the use of resources

  • final assembly of the output

Explicação

Questão 8 de 200

1

Which of the following is not one of the four dimensions of project success?

Selecione uma das seguintes:

  • opening new opportunities for the future

  • number of people working on the project

  • impact on the customer

  • business impact on the organization

Explicação

Questão 9 de 200

1

The project to construct a highway is unique because

Selecione uma das seguintes:

  • the characteristics of terrain will be different for different segments

  • consistency of the concrete will vary for different segments

  • different types of laborers will be used to build various segments of the highway

  • different people manage different sections of the highway

Explicação

Questão 10 de 200

1

Projects often interact with other projects being carried out simultaneously within the organization and these interactions take the form of competition for scarce resources between project. This is an example of project

Selecione uma das seguintes:

  • bottleneck

  • breakdown

  • interdependencies

  • malfunctioning

Explicação

Questão 11 de 200

1

When done properly, project management begins with

Selecione uma das seguintes:

  • stakeholder interviews

  • scope definition

  • the initial concept for the project

  • budget estimation

Explicação

Questão 12 de 200

1

The chance that project processes or outcomes will not turn out as planned is called

Selecione uma das seguintes:

  • risk

  • projecting

  • effort

  • negative outcome

Explicação

Questão 13 de 200

1

Having only partial or no information about the situation or outcomes is called

Selecione uma das seguintes:

  • uncertainty

  • risk

  • effort

  • cluelessness

Explicação

Questão 14 de 200

1

Relations between organizational functions, where one function or task is dependent on others, are known as

Selecione uma das seguintes:

  • interdependencies

  • links

  • projects

  • tasks

Explicação

Questão 15 de 200

1

The of the project team is a crucial but unstated element of ancillary trade-
offs that the project manager must consider.

Selecione uma das seguintes:

  • health

  • plan

  • task

  • effort

Explicação

Questão 16 de 200

1

The project is generally credited with beginning the era of modern project
management

Selecione uma das seguintes:

  • Manhattan

  • Chicago

  • Great Wall of China

  • Egyptian pyramids

Explicação

Questão 17 de 200

1

is a subset of a project consisting of work packages

Selecione uma das seguintes:

  • task

  • program

  • project

  • process

Explicação

Questão 18 de 200

1

Projects are bound by the three objectives of scope, time, and cost. These are collectively referred to as the

Selecione uma das seguintes:

  • Triple Constraint

  • Triple Factors

  • Three Constraints

  • Triple Play

Explicação

Questão 19 de 200

1

Individuals or groups with a special interest in a project are called

Selecione uma das seguintes:

  • stakeholders

  • project managers

  • leaders

  • directors

Explicação

Questão 20 de 200

1

The production of weekly employment reports or the delivery of mail could be considered a

Selecione uma das seguintes:

  • project

  • non-project

  • quasi-projects

  • triple projects

Explicação

Questão 21 de 200

1

Which of the following demonstrates the quality of flexibility required of a project selection model?

Selecione uma das seguintes:

  • It does not require special interpretation, data that are difficult to acquire, or excessive personnel.

  • It gives valid results within the range of conditions that the firm might experience.

  • It reflects the multiple objectives of both the firm and its managers.

  • It deals with situations both internal and external to the project.

Explicação

Questão 22 de 200

1

The two basic types of project selection models identified in the text are

Selecione uma das seguintes:

  • biased and unbiased

  • numeric and nonnumeric

  • active and passive

  • numeric and qualitative

Explicação

Questão 23 de 200

1

If a system is being updated due to operating necessity, the project was selected because

Selecione uma das seguintes:

  • the system is worth saving at any cost

  • the system is worth saving at the estimated cost of the project

  • the dimension of cost is not relevant to execution of the project

  • the cost overruns can be hidden in someone else's budget

Explicação

Questão 24 de 200

1

The drawback of the ___________ model is that it fails to consider cash flows obtained once the initial investment has been recovered.

Selecione uma das seguintes:

  • payback period

  • average rate of return

  • discounted cash flow

  • profitability index

Explicação

Questão 25 de 200

1

If the NPV for a project is < 0, it indicates that the project will

Selecione uma das seguintes:

  • report a profit loss

  • report a profit gain

  • fail to cover its required rate of return

  • fail to generate cash inflows

Explicação

Questão 26 de 200

1

Scoring models are most often used to overcome this disadvantage of profitability models.

Selecione uma das seguintes:

  • The inability to account for the time value of money

  • The inability to account for project results beyond the payback period

  • The inability to account for multiple decision criteria

  • The inability to account for cash flow

Explicação

Questão 27 de 200

1

Firms usually have two or more projects and this collection of projects is referred to as

Selecione uma das seguintes:

  • a portfolio

  • an initiation

  • a program

  • a stochastic model

Explicação

Questão 28 de 200

1

A technique useful for developing numeric values that are equivalent to subjective, verbal measures of relative value is the

Selecione uma das seguintes:

  • Delphi system

  • expert system

  • portfolio

  • simulation

Explicação

Questão 29 de 200

1

Which of the following is a type of numeric model?

Selecione uma das seguintes:

  • the sacred cow

  • the operating necessity

  • payback period

  • the product line extension

Explicação

Questão 30 de 200

1

The _________ is the value of an opportunity foregone

Selecione uma das seguintes:

  • real option

  • profit

  • opportunity cost

  • revenue

Explicação

Questão 31 de 200

1

The _________ is the interest rate set by an organization as the minimum acceptable rate of return for a project

Selecione uma das seguintes:

  • hurdle rate

  • acceptable rate

  • internal rate of return

  • net present value

Explicação

Questão 32 de 200

1

In a project portfolio, _______________ projects have objectives or deliverables that are only
incrementally different in both product and process from existing offerings.

Selecione uma das seguintes:

  • breakthrough

  • R&D

  • platform

  • derivative

Explicação

Questão 33 de 200

1

In a project portfolio, a project that involves a new technology or even a disruptive technology that is known to the industry would serve as an example of a project

Selecione uma das seguintes:

  • breakthrough

  • R&D

  • platform

  • derivitive

Explicação

Questão 34 de 200

1

The set of documents submitted when evaluating a project is referred to as the

Selecione uma das seguintes:

  • project proposal

  • evaluation set

  • evaluation criteria

  • project manual

Explicação

Questão 35 de 200

1

When the decision maker's information is not complete, he/she will have to make a decision under conditions of

Selecione uma das seguintes:

  • proof

  • uncertainty

  • management

  • risk mitigation

Explicação

Questão 36 de 200

1

The discounted cash flow method determines the net present value of all cash flows by discounting them by the

Selecione uma das seguintes:

  • hurdle rate

  • acceptable rate

  • internal rate of return

  • net present value

Explicação

Questão 37 de 200

1

Financial forecasts are reported as __________ financial statements.

Selecione uma das seguintes:

  • final

  • initial

  • pro forma

  • hypothetical

Explicação

Questão 38 de 200

1

A project selection criteria that focuses on how well new products would fit the firm's existing product line would be

Selecione uma das seguintes:

  • sustainability

  • comparative benefit model

  • production line extension

  • operating necessity

Explicação

Questão 39 de 200

1

According to research by Sanchez and Robert (2010), which of the following is not a reason why strategic benefits may be difficult to appraise?

Selecione uma das seguintes:

  • Not immediately realized

  • Difficult to quantify

  • May be confounded with other factors

  • Easy to plan for when they occur

Explicação

Questão 40 de 200

1

________ is a modeling technique for emulating a process, usually conducted a
considerable number of times to understand the process better and measure its outcomes under different policies.

Selecione uma das seguintes:

  • Simulation

  • Project management

  • Projectizing

  • Modeling

Explicação

Questão 41 de 200

1

According to the authors, the analytic method, when applied to systems, focuses on

Selecione uma das seguintes:

  • assembling the components of a system into an integrated package

  • building an array of individually designed and manufactured components

  • calculating the cost and schedule requirements

  • dividing the components of a system into smaller and smaller elements

Explicação

Questão 42 de 200

1

The ideal project manager should be

Selecione uma das seguintes:

  • a direct, technical supervisor knowledgeable in the technology of the process being used

  • both generalist/facilitator and have a high level of technical competence in the science of the project

  • a facilitator and specialist with technical credibility

  • a technical specialist competent in principles of robust design

Explicação

Questão 43 de 200

1

The project manager must make trade-offs between project progress and process. Conceptually, this involves trade-offs between the _______ functions.

Selecione uma das seguintes:

  • technical and managerial

  • schedule and cost

  • performance and schedule

  • cost and performance

Explicação

Questão 44 de 200

1

According to the authors the project manager should be more skilled at

Selecione uma das seguintes:

  • general management

  • technology

  • synthesis

  • analysis

Explicação

Questão 45 de 200

1

The project manager needs _______ credibility.

Selecione uma das seguintes:

  • technical and personal

  • administrative and personal

  • technical and administrative

  • technical and financial

Explicação

Questão 46 de 200

1

Projects are conducted in four important environments. They are

Selecione uma das seguintes:

  • economic, political, legal, and sociotechnical

  • internal, external, transitional, and multicultural

  • routine, unique, fast-paced, and complex

  • profit, not for profit, government, and industry

Explicação

Questão 47 de 200

1

According to the authors, the key to coping with uncertainty at the end of a project (a common obstacle for project managers) is

Selecione uma das seguintes:

  • discipline

  • communication

  • planning

  • supervision

Explicação

Questão 48 de 200

1

During the buildup phase, the project goals, in order of importance, are

Selecione uma das seguintes:

  • schedule, scope, cost

  • cost, schedule, scope

  • schedule, cost, scope

  • cost, scope, schedule

Explicação

Questão 49 de 200

1

Resources initially budgeted for a project are frequently _________ for the task, partly because of natural optimism by the proposer about how many resources are needed.

Selecione uma das seguintes:

  • sufficient

  • delayed

  • insufficient

  • hindrances

Explicação

Questão 50 de 200

1

Most of the time spent by a project manager is spent

Selecione uma das seguintes:

  • attending technical workshops

  • overseeing the workforce

  • filing paperwork

  • coordinating and communicating

Explicação

Questão 51 de 200

1

11. The functional manager uses the ________ approach and the PM uses the ________ approach

Selecione uma das seguintes:

  • systems; analytic

  • numerical; nonnumeric

  • analytic; systems

  • nonnumeric; numerical

Explicação

Questão 52 de 200

1

The project manager's responsibility to the project and to the client is met by ensuring that the _______ of the project is preserved in spite of conflicting demands made by stakeholders.

Selecione uma das seguintes:

  • management

  • integrity

  • analysis

  • synthesis

Explicação

Questão 53 de 200

1

During the final or phaseout stage of the project lifecycle, ___________ is the dominant goal of many project managers.

Selecione uma das seguintes:

  • schedule

  • cost

  • scope

  • quality

Explicação

Questão 54 de 200

1

The structure of a society is determined by its

Selecione uma das seguintes:

  • institutions

  • wages

  • jobs

  • enemies

Explicação

Questão 55 de 200

1

Which of the following is not a phase in the Tuckman ladder?

Selecione uma das seguintes:

  • forming

  • defining

  • norming

  • mourning

Explicação

Questão 56 de 200

1

The _________ is a person who spearheads an idea or action and sells it throughout the organization.

Selecione uma das seguintes:

  • stakeholder

  • champion

  • interviewer

  • coach

Explicação

Questão 57 de 200

1

The ______________ is an alternative action if the expected result fails to materialize.

Selecione uma das seguintes:

  • trade-off

  • system plan

  • feedback

  • contingency plan

Explicação

Questão 58 de 200

1

The __________ represents everything outside the system that delivers inputs or
receives outputs from the system.

Selecione uma das seguintes:

  • environment

  • feedback

  • culture

  • system

Explicação

Questão 59 de 200

1

The __________ is the "corporate culture" within the organization, or even within the
project

Selecione uma das seguintes:

  • cultural anomaly

  • microculture

  • multiculture

  • interfirm culture

Explicação

Questão 60 de 200

1

The project manager makes a ___________ by allowing one aspect of the project to get
worse in return for allowing another aspect of the project to get better.

Selecione uma das seguintes:

  • decision

  • turnaround

  • trade-off

  • chart

Explicação

Questão 61 de 200

1

A party to a conflict will usually be satisfied when the level of frustration has been

Selecione uma das seguintes:

  • increased by the domination of the other party

  • lowered to the point where no action against the other party is contemplated

  • lowered because the party realizes the hopelessness of continuing the conflict

  • eliminated because the party has surrendered to the other party

Explicação

Questão 62 de 200

1

Most of the conflicts that involve the organization and outsiders have to do with

Selecione uma das seguintes:

  • interpersonal differences

  • cultural differences and status differences

  • technical differences

  • property rights and contractual obligations

Explicação

Questão 63 de 200

1

During project formation, the organizational structure selected will have a major impact on the ways in which conflicts are handled. Lack of clarity about the relative power/influence/authority of the PM and the functional managers is a major component of all conflicts involving

Selecione uma das seguintes:

  • contractual obligations

  • property rights

  • budgeting

  • resource allocation, and scheduling

Explicação

Questão 64 de 200

1

If a resource conflict arises between two high-priority projects, precedence is typically given to the project with the

Selecione uma das seguintes:

  • earliest due date

  • fastest completion time

  • biggest revenue stream

  • lowest cost to complete

Explicação

Questão 65 de 200

1

During project build-up, the project should move from a general concept to

Selecione uma das seguintes:

  • implementation of plans

  • a highly detailed set of plans

  • a project charter

  • a project contract

Explicação

Questão 66 de 200

1

During project build-up, if the project is independent and standalone, the project manager seeks a commitment of __________ from the functional departments.

Selecione uma das seguintes:

  • work

  • materials

  • people

  • budgets

Explicação

Questão 67 de 200

1

During project build-up, if the project is functionally tied down, the project manager seeks a commitment of _________ from the functional departments.

Selecione uma das seguintes:

  • work

  • materials

  • people

  • budgets

Explicação

Questão 68 de 200

1

Personality conflicts during project phase-out are often caused by

Selecione uma das seguintes:

  • the absence of deadlines

  • the influx of newer technology

  • pressure to complete the project and anxiety about leaving the project

  • distribution of expenses charged to the project

Explicação

Questão 69 de 200

1

According to the authors, the nature of negotiation as it applies to project management is the realization that few of the conflicts arising in projects have to do with

Selecione uma das seguintes:

  • whether or not the task will be done

  • the precise design of the deliverable

  • how the design will be achieved

  • who will do the work, when, and at what cost

Explicação

Questão 70 de 200

1

When dealing with conflict between parties, it is recommended that one _______ in order to avoid the conflict becoming interpersonal.

Selecione uma das seguintes:

  • avoid the situation

  • define the substantive problem

  • leisurely discuss the issue

  • focus on interests

Explicação

Questão 71 de 200

1

Partnering is an attempt to _________ the risk associated with sub-contracting.

Selecione uma das seguintes:

  • mitigate

  • Increase

  • absorb

  • allow

Explicação

Questão 72 de 200

1

_________ is the process which begins when one party perceives that the other has frustrated, or is about to frustrate, some concern of his.

Selecione uma das seguintes:

  • conflict

  • happiness

  • contentment

  • utility

Explicação

Questão 73 de 200

1

According to the authors, the favored technique for resolving conflict is

Selecione uma das seguintes:

  • negotiation

  • mitigation

  • avoidance

  • collaboration

Explicação

Questão 74 de 200

1

The process through which two or more parties seek an acceptable rate of exchange for items they own or control is called

Selecione uma das seguintes:

  • negotiation

  • mitigation

  • compromising

  • collaboration

Explicação

Questão 75 de 200

1

During the early program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to

Selecione uma das seguintes:

  • cost

  • schedules

  • scope

  • quality

Explicação

Questão 76 de 200

1

During the main program phases of the project lifecycle, Thamhain et al say that conflict intensity is the greatest with respect to

Selecione uma das seguintes:

  • cost

  • schedules

  • scope

  • quality

Explicação

Questão 77 de 200

1

Toward the end of the project lifecycle, Thamhain et at say that conflict intensity is the greatest with respect to

Selecione uma das seguintes:

  • cost

  • schedules

  • scope

  • quality

Explicação

Questão 78 de 200

1

Negotiating to a(n) __________ solution is the key to conflict resolution in project management.

Selecione uma das seguintes:

  • win-lose

  • win-win

  • avoidance

  • confrontation

Explicação

Questão 79 de 200

1

The total level of conflict in the project lifecycle is highest during the _________ stage

Selecione uma das seguintes:

  • closing

  • main program

  • project build-up

  • project formation

Explicação

Questão 80 de 200

1

The ___________ approach to negotiation aims to achieve a win-win result.

Selecione uma das seguintes:

  • principled

  • posititional

  • stakeholder

  • paretto

Explicação

Questão 81 de 200

1

If the project manager controls when and what people do while the functional managers control who will be assigned to the project and what technology will be used, the ______organizational form is probably being used.

Selecione uma das seguintes:

  • projectized

  • pure project

  • matrix

  • weak project

Explicação

Questão 82 de 200

1

In the systems approach to design, one organization would have to take responsibility for

Selecione uma das seguintes:

  • manufacturing everything in the system

  • the integrity of the project design

  • the integrity of the subcontractors

  • product warranties

Explicação

Questão 83 de 200

1

The process of dealing with uncertainties in projects that may affect the project for better or for worse has come to be known as

Selecione uma das seguintes:

  • scope management

  • risk management

  • quality management

  • procurement management

Explicação

Questão 84 de 200

1

A common objective of an organization's PM is often created by organizations to

Selecione uma das seguintes:

  • establish consistent project management standards and methods

  • deal with technological obsolescence

  • train process managers

  • administer application software

Explicação

Questão 85 de 200

1

A major purpose of the project management office should be to serve as

Selecione uma das seguintes:

  • the central location for all clerical support

  • the critical disaster recovery support

  • a link between strategic management and project management

  • maintenance for the project management library

Explicação

Questão 86 de 200

1

This member of the project team is in charge of product design and development and is responsible for functional analysis, specifications, drawings, cost estimates, quality/reliability, engineering changes, and documentation

Selecione uma das seguintes:

  • systems architect

  • manufacturing engineer

  • project controller

  • support services manager

Explicação

Questão 87 de 200

1

This member of the project team is responsible for the efficient production of the product of the process, including the manufacturing engineering, design and production of tooling, production scheduling, and other production tasks

Selecione uma das seguintes:

  • project engineer

  • development engineer

  • contract administrator

  • support services manager

Explicação

Questão 88 de 200

1

This person is responsible for the installation, testing, and support of the product (process) once its engineering is complete.

Selecione uma das seguintes:

  • development engineer

  • systems architect

  • test engineer

  • project controller

Explicação

Questão 89 de 200

1

One of the main technical problems faced by the project manager is meeting ________ without compromising performance.

Selecione uma das seguintes:

  • supplier's targets

  • schedule and cost goals

  • technical specifications

  • cost and conflict goals

Explicação

Questão 90 de 200

1

A major advantage of using a _________ placement for a project is that individual
experts can be utilized by many different projects.

Selecione uma das seguintes:

  • standard

  • virtual

  • projectized

  • functional

Explicação

Questão 91 de 200

1

Virtual teams, when composed, should consist of "boundary spanners" who number about one in every _________ team members

Selecione uma das seguintes:

  • 6-7

  • 8-12

  • 10-20

  • 25-30

Explicação

Questão 92 de 200

1

When a firm engages in a large number of similar projects, the ___________ organizational form is apt to be preferred.

Selecione uma das seguintes:

  • pure project

  • partial matrix

  • functional

  • mixed matrix

Explicação

Questão 93 de 200

1

When the standard departments of the organization represent individual disciplines such as engineering, marketing, purchasing, and so on, the organization follows

Selecione uma das seguintes:

  • projectized management

  • matrixed management

  • functional management

  • mixed management

Explicação

Questão 94 de 200

1

The firm or organization within which the project is being conducted is known as the

Selecione uma das seguintes:

  • parent organization

  • consulting firm

  • project team

  • stakeholder company

Explicação

Questão 95 de 200

1

______________ engineering refers to the use of a design team that includes design and manufacturing engineers as well as staff from other relevant areas of the business.

Selecione uma das seguintes:

  • Concurrent

  • Alignment

  • Matrix

  • Social

Explicação

Questão 96 de 200

1

The _________ is a basic project document that describes all the work that must be done to complete the project and forms the basis for costing, scheduling, and work

Selecione uma das seguintes:

  • WBS

  • OBS

  • PMO

  • project charter

Explicação

Questão 97 de 200

1

The approach to organizing that includes both functions (disciplines) and projects in its hierarchy is known as the

Selecione uma das seguintes:

  • mixed organization

  • functional organization

  • projectized organization

  • matrix organization

Explicação

Questão 98 de 200

1

This person's task is the efficient production of the product or process the project engineer has designed, including responsibility for manufacturing engineering, design and production of code, unit testing, production scheduling, and other production tasks.

Selecione uma das seguintes:

  • test engineer

  • contract administrator

  • development engineer

  • systems architect

Explicação

Questão 99 de 200

1

TQM and Six Sigma are good examples of ____________ programs

Selecione uma das seguintes:

  • participative

  • exclusive

  • frequency

  • inclusive

Explicação

Questão 100 de 200

1

If both functional and projectized divisions coexist in a firm, this would result in the __________ organizational structure.

Selecione uma das seguintes:

  • composite

  • objective

  • encompassing

  • free-form

Explicação

Questão 101 de 200

1

The _________ is a specialized view of the action plan that focuses on who has what
responsibility for each project task.

Selecione uma das seguintes:

  • resource histogram

  • linear responsibility chart

  • project team directory

  • scope management plan

Explicação

Questão 102 de 200

1

The success of the project launch meeting is dependent on the existence of

Selecione uma das seguintes:

  • a project charter

  • the project's scope statement

  • a well-defined set of objectives for the project

  • project planning templates

Explicação

Questão 103 de 200

1

This project plan element describes both the managerial and the technical approaches to the work. The technical discussion describes the relationship of the project to available technologies.

Selecione uma das seguintes:

  • overview

  • objectives

  • general approach

  • contractual aspects

Explicação

Questão 104 de 200

1

This project plan element should include profit and competitive goals as well as technical goals.

Selecione uma das seguintes:

  • overview

  • objectives

  • general approach

  • contractual aspects

Explicação

Questão 105 de 200

1

The _______ of a project includes the objectives of the project as well as the time and cost required to complete the project to the customer's satisfaction.

Selecione uma das seguintes:

  • scope

  • change order

  • outcome

  • purpose

Explicação

Questão 106 de 200

1

RACI stands for

Selecione uma das seguintes:

  • responsive, accountable, consult, inform

  • responsible, accountable, consult, inform

  • responsive, accountable, consult, integrate

  • responsible, admissible, consult, integrate

Explicação

Questão 107 de 200

1

The set of physical elements required to build a project is called the

Selecione uma das seguintes:

  • bill of materials

  • deliverable

  • milestone list

  • work statement

Explicação

Questão 108 de 200

1

___________ is an approach that breaks the planning task down into the activities that must be done in each managerial level of the organization. Typically, the upper level sets the objectives for the next lower level.

Selecione uma das seguintes:

  • Strategic planning

  • Organizational planning

  • Hierarchical planning

  • Agile planning

Explicação

Questão 109 de 200

1

The major tool that a project manager uses during the planning phase is called the

Selecione uma das seguintes:

  • WBS

  • change request

  • scope statement

  • project plan

Explicação

Questão 110 de 200

1

___________is the tendency for the project objectives to be changed with little or no discussion with other parties actively engaged in the project

Selecione uma das seguintes:

  • Scope reference

  • Scope creep

  • Effectiveness

  • Hierarchical planning

Explicação

Questão 111 de 200

1

_______________ is a visual approach that closely mirrors how the human brain records and stores information that can help tap the creative potential of the entire project team

Selecione uma das seguintes:

  • WBS generation

  • Project planning

  • Risk response planning

  • Mind mapping

Explicação

Questão 112 de 200

1

When using a WBS, all of the work should roll up to the next level such that no extra work is required. This is referred to as the

Selecione uma das seguintes:

  • Development rule

  • All-inclusive rule

  • 100% rule

  • WBS rule

Explicação

Questão 113 de 200

1

For projects that are constantly changing, the __________ methodology is recommended

Selecione uma das seguintes:

  • waterfall

  • agile

  • adaptable

  • organic

Explicação

Questão 114 de 200

1

Having key stakeholders involved early in the project tends to

Selecione uma das seguintes:

  • increase communication errors

  • increase project risk

  • create buy-in

  • create more problems than it is worth

Explicação

Questão 115 de 200

1

When using the mind mapping process, you should designate one team member as the ___________ to ensure that all team members are involved and contributing, and to ensure that team members are focusing on the work that must be done.

Selecione uma das seguintes:

  • planner

  • facilitator

  • contractor

  • manager

Explicação

Questão 116 de 200

1

A useful tool for facilitating the management of changes to a project's scope is the

Selecione uma das seguintes:

  • requirements traceability matrix

  • WBS

  • project charter

  • mind map

Explicação

Questão 117 de 200

1

A project manager must ___________ as a type of risk response planning in order to soften the danger of a threat by reducing the likelihood that it will occur or by reducing its impact if it does occur.

Selecione uma das seguintes:

  • avoid

  • transfer

  • accept

  • mitigate

Explicação

Questão 118 de 200

1

The ____________ is a list of the project activities with major activities broken down into subactivities.

Selecione uma das seguintes:

  • linear responsibility chart

  • PCMCIA

  • activity prioritization

  • WBS

Explicação

Questão 119 de 200

1

The process of coordinating the work and timing of the different groups working on multidisciplinary teams is called

Selecione uma das seguintes:

  • procurement management

  • integration management

  • vertical management

  • matrix management

Explicação

Questão 120 de 200

1

This element of the project plan contains a brief description of the procedure to be followed in monitoring, collecting, storing, and evaluating the history of the project

Selecione uma das seguintes:

  • schedule

  • resources

  • personnel

  • evaluation methods

Explicação

Questão 121 de 200

1

If a project budget is under funded, it will often

Selecione uma das seguintes:

  • stimulate increased performance

  • improve utilization of resources

  • frustrate committed stakeholders

  • reduce costs

Explicação

Questão 122 de 200

1

The project's budget should

Selecione uma das seguintes:

  • associate resource use with the achievement of organizational goals

  • allow funds to be spent without linkage to achievement

  • not reflect the timing of expenses associated with the use of resources

  • never be changed during project execution

Explicação

Questão 123 de 200

1

In order to develop a budget, the PM must forecast

Selecione uma das seguintes:

  • the resources required

  • when resources will be needed

  • the cost of resources

  • All of the above

Explicação

Questão 124 de 200

1

A work element whose cost is fully developed would

Selecione uma das seguintes:

  • exclude the cost of labor and resources

  • include only the profit and direct costs

  • exclude the cost of special machinery and overheads

  • include direct costs plus overhead and G&A charges

Explicação

Questão 125 de 200

1

The traditional organizational budget is

Selecione uma das seguintes:

  • category-oriented

  • project-oriented

  • program-oriented

  • project-oriented or program-oriented

Explicação

Questão 126 de 200

1

__________ budgeting allows income and expenditures to be aggregated across projects.

Selecione uma das seguintes:

  • Category-oriented

  • Activity-oriented

  • Project-oriented

  • Expense-oriented

Explicação

Questão 127 de 200

1

The authors identify ____________ estimation errors as the two types of generic estimation errors.

Selecione uma das seguintes:

  • small and large

  • random and planned

  • certain and uncertain

  • random and biased

Explicação

Questão 128 de 200

1

The pattern of deviations in cost and usage used for exception reporting to management is called

Selecione uma das seguintes:

  • simulations

  • assumptions

  • variances

  • summaries

Explicação

Questão 129 de 200

1

___________ costs vary with output.

Selecione uma das seguintes:

  • general and administrative

  • overhead

  • direct

  • indirect

Explicação

Questão 130 de 200

1

Unless the project manager is familiar with the firm's ______________ it will be very difficult to exercise budget control.

Selecione uma das seguintes:

  • accounting system

  • budget plans

  • marketing procedure

  • cost accounting

Explicação

Questão 131 de 200

1

The __________ form of budgeting has the advantage of using individuals closer to the work to provide estimates of resource requirements.

Selecione uma das seguintes:

  • top-down budgeting

  • work element costing

  • bottom-up budgeting

  • iterative budgeting

Explicação

Questão 132 de 200

1

The ___________ charge is composed of the costs of senior management, the various data functions, and any other expenses not included in overhead. Often, these charges are a fixed percentage of either the direct costs or the total of all direct and indirect costs.

Selecione uma das seguintes:

  • salary

  • project management

  • ethical

  • G&A

Explicação

Questão 133 de 200

1

Each time the output doubles, the worker hours per unit decrease to a fixed percentage of their previous value. That percentage is called the ___________ rate.

Selecione uma das seguintes:

  • inflation

  • hurdle

  • interest

  • learning

Explicação

Questão 134 de 200

1

Suppose that a person requires 60 minutes to complete a work element on the first attempt. On the second attempt, the work element is completed in 48 minutes. The learning rate for this person is _________% for this work element

Selecione uma das seguintes:

  • 80

  • 60

  • 70

  • 120

Explicação

Questão 135 de 200

1

_____________ relies on well-known statistical correlations between various factors such as the total cost of a house relative to the square feet of living area.

Selecione uma das seguintes:

  • Parametric estimating

  • Statistical equivalence

  • Bottom-up estimating

  • Top-down estimating

Explicação

Questão 136 de 200

1

A budget strategy that is based on collecting the judgments and experiences of top and middle managers is referred to as the ___________ approach or method.

Selecione uma das seguintes:

  • parametric estimating

  • statistical equivalence

  • bottom-up estimating

  • top-down estimating

Explicação

Questão 137 de 200

1

________________ are where the defined responses to the risks are detailed, but their amounts are not
yet precisely known.

Selecione uma das seguintes:

  • Known-unknowns

  • Unknown-knowns

  • Known-knowns

  • Unknown-unknowns

Explicação

Questão 138 de 200

1

Unknown-unknowns are not part of the baseline budget and are referred to as

Selecione uma das seguintes:

  • management reserves

  • contingency reserves

  • PMBOK reserves

  • Buffered reserves

Explicação

Questão 139 de 200

1

The advantage of the ____________ process is that it is generally associated with participative management

Selecione uma das seguintes:

  • bottom-up

  • top-down

  • Murphy's

  • Efficient

Explicação

Questão 140 de 200

1

______________ issues are present when bidders "low-ball" a bid or when some bidders get a "last look."

Selecione uma das seguintes:

  • Ethical

  • Strategic

  • Efficient

  • Effective

Explicação

Questão 141 de 200

1

The authors recommend preparing a schedule for each

Selecione uma das seguintes:

  • work package in the WBS

  • task in the WBS

  • major task level in the WBS

  • project that has a WBS

Explicação

Questão 142 de 200

1

In the AOA network, circles depict

Selecione uma das seguintes:

  • networks

  • events

  • logical dependencies

  • dummy activities

Explicação

Questão 143 de 200

1

The shortest time in which the entire network can be completed is referred to as the

Selecione uma das seguintes:

  • critical time of the network

  • real duration of the network

  • elapsed time of the network

  • slack time of the network

Explicação

Questão 144 de 200

1

A precedence relationship where the completion of a successor activity depends on the completion of a predecessor activity is called a

Selecione uma das seguintes:

  • start to finish dependency

  • finish to start dependency

  • finish to finish dependency

  • start to start dependency

Explicação

Questão 145 de 200

1

A precedent relationship where the completion of a predecessor activity depends on the initiation of a successor activity is called a

Selecione uma das seguintes:

  • start to finish dependency

  • finish to start dependency

  • finish to finish dependency

  • start to start dependency

Explicação

Questão 146 de 200

1

The difference between the late start and early start for an activity is called its

Selecione uma das seguintes:

  • critical path

  • task

  • progress

  • float

Explicação

Questão 147 de 200

1

A(n) __________ is the conversion of the project work breakdown structure into an operating timetable.

Selecione uma das seguintes:

  • chart

  • application

  • crash

  • schedule

Explicação

Questão 148 de 200

1

A(n) _________ is a specific task or set of tasks that are required by the project, use up resources, and take time to complete

Selecione uma das seguintes:

  • milestone

  • activity

  • node

  • path

Explicação

Questão 149 de 200

1

The arrangement of all activities (and, in some cases, events) in a project arrayed in their logical sequence and represented by arcs and nodes is called a

Selecione uma das seguintes:

  • network

  • critical path

  • path

  • crashed path

Explicação

Questão 150 de 200

1

In a network, if the delay of an activity will delay completion of the project, the activity is called a(n)

Selecione uma das seguintes:

  • valuable

  • efficient

  • critical

  • noteworthy

Explicação

Questão 151 de 200

1

In AOA networks, an activity of zero duration is called a(n)

Selecione uma das seguintes:

  • dummy activity

  • critical

  • important

  • critical activity

Explicação

Questão 152 de 200

1

The _____________ chart shows planned and actual progress for a number of tasks displayed against a horizontal timescale.

Selecione uma das seguintes:

  • PERT

  • timeline

  • critical

  • Gantt

Explicação

Questão 153 de 200

1

A clearly identifiable point in a project or set of activities that commonly denotes a reporting requirement or completion of a large or important set of activities is called a(n)

Selecione uma das seguintes:

  • milestone

  • anniversary

  • node

  • dummy activity

Explicação

Questão 154 de 200

1

In AON diagrams, a(n) ________________ is a point where one or more lines (arrows) begin or terminate, commonly used for depicting an event or activity.

Selecione uma das seguintes:

  • activity

  • path

  • node

  • arc

Explicação

Questão 155 de 200

1

______________ is the amount of one factor that must be sacrificed in order to achieve more or less of another factor.

Selecione uma das seguintes:

  • trade-off

  • synergy

  • barter limit

  • limiting quantity

Explicação

Questão 156 de 200

1

A _____________ is a combination of interrelated activities and events depicted with arcs and nodes.

Selecione uma das seguintes:

  • linked plan

  • chain of events

  • critical chain

  • network

Explicação

Questão 157 de 200

1

____________ law suggests that work expands to fill the allotted time.

Selecione uma das seguintes:

  • Parkinson's

  • Murphy's

  • Brooks'

  • Federal

Explicação

Questão 158 de 200

1

In application, PERT has primarily been used for

Selecione uma das seguintes:

  • construction projects

  • manufacturing projects

  • industrial projects

  • research and development projects

Explicação

Questão 159 de 200

1

The authors define _________ as the time an activity can be delayed without affecting the start time of any successor activity

Selecione uma das seguintes:

  • free slack

  • total slack

  • project slack

  • overhead slack

Explicação

Questão 160 de 200

1

__________ is one possible way to check the nature and impacts of interactions between probabilistic paths in a network.

Selecione uma das seguintes:

  • simulation

  • extrapolation

  • guessing

  • probabilistic time estimates

Explicação

Questão 161 de 200

1

If deterministic time estimates are used, and if project deadlines are firm, there is a high likelihood that it will

Selecione uma das seguintes:

  • not be necessary to crash any activities in projects

  • be necessary to crash the last few activities of most projects

  • be completed on time and within budget

  • be completed as per schedule

Explicação

Questão 162 de 200

1

Assume two activities, printing and binding. Printing is a predecessor of binding. If printing is _______, then binding will start late by whatever amount of lateness is bequeathed to it by printing.

Selecione uma das seguintes:

  • necessary

  • early

  • late

  • time-neutral

Explicação

Questão 163 de 200

1

________ aims to minimize the period-by-period variations in resource loading by shifting tasks within their slack allowances. The purpose is to create a smoother distribution of resource usage.

Selecione uma das seguintes:

  • Resource loading

  • Resource leveling

  • Scope loading

  • Resource succeeding

Explicação

Questão 164 de 200

1

A project task is said to be __________ if it requires a fixed amount of time and known quantities of resources

Selecione uma das seguintes:

  • scope constrained

  • time constrained

  • resource constrained

  • system constrained

Explicação

Questão 165 de 200

1

One of the problems that Goldratt observed was that if an activity has slack time, the task might become delayed until the slack is removed. This is referred to as

Selecione uma das seguintes:

  • Goldratt's Law

  • Murphy's Law

  • the delay game

  • the student syndrome

Explicação

Questão 166 de 200

1

The points between the extreme points of the relationship between time use and resource use represent

Selecione uma das seguintes:

  • time constrained projects

  • resource constrained projects

  • alternative trade-offs between time and resources

  • a non-feasible solution space of trade-off alternatives related to time and resource use

Explicação

Questão 167 de 200

1

The _________ technique overlaps the design and build phases of a project to expedite its completion.

Selecione uma das seguintes:

  • crashing

  • fast-tracking

  • leading

  • blitzing

Explicação

Questão 168 de 200

1

Most heuristic solution methods start with the _____________ and analyze resource usage period by period, resource by resource.

Selecione uma das seguintes:

  • GERT schedule

  • Gantt chart

  • PERT/CPM schedule

  • Master schedule

Explicação

Questão 169 de 200

1

The use of ______________ activity time estimates may reduce the chance that crashing the
project will be needed.

Selecione uma das seguintes:

  • one probabilistic

  • two probabilistic

  • three probabilistic

  • four probabilistic

Explicação

Questão 170 de 200

1

The standard practice with AOA and AON is to estimate activity times under the assumption of resource loadings that are

Selecione uma das seguintes:

  • probabillistic

  • crashed

  • normal

  • dynamic

Explicação

Questão 171 de 200

1

With respect to project scheduling, __________ is the amount of work waiting to be processed because there is a shortage of some resource.

Selecione uma das seguintes:

  • in-process inventory

  • schedule slippage

  • resource utilization

  • management delay

Explicação

Questão 172 de 200

1

If the appropriate scheduling equation for task A of a project were W = D * U, and it was initialized so that W = 40d, D = 10d, and U = 4 resources, and task A is an effort-driven activity, correctly balance this equation if the value for U is changed from 4 to 5. To balance the equation, the altered variable and its new value are

Selecione uma das seguintes:

  • D = 6w

  • W = 6d

  • D = 8d

  • W = 8d

Explicação

Questão 173 de 200

1

The principal reason why a project manager is surprised by resource constraints on a project is the failure to include _________ in risk identification activities.

Selecione uma das seguintes:

  • resource availability

  • resource cost

  • resource mobility

  • resource skill

Explicação

Questão 174 de 200

1

Which of the following describes a situation where priorities are assigned to activities according to some rule not associated with task length, slack, or resource requirements?

Selecione uma das seguintes:

  • student's syndrome

  • arbitrary

  • most successors

  • most resources

Explicação

Questão 175 de 200

1

The two fundamental approaches to constrained allocation problems are

Selecione uma das seguintes:

  • heuristic approaches and rules of thumb

  • linear programming approaches and optimization models

  • heuristic approaches and optimization models

  • goal programming and trial and error

Explicação

Questão 176 de 200

1

When crashing a project, our first task is to develop

Selecione uma das seguintes:

  • a table or graph of the cost of a project as a function of the project's possible completion dates

  • a schedule that shows the risks associated with each activity in the project

  • a list that shows the activities and the events of a project without referring to the costs

  • a table showing the noncritical activities and the cost associated with each of those activities

Explicação

Questão 177 de 200

1

In some situations, two activities are scheduled to be carried out in parallel and using the same scarce resource. If the supply of the scarce resource is not sufficient to allow both activities to be carried out simultaneously, then whichever of the two is given priority immediately lengthens the other activity's path but not its actual

Selecione uma das seguintes:

  • duration

  • slack

  • float

  • buffer

Explicação

Questão 178 de 200

1

The two principles to follow when crashing a project focuses on the

Selecione uma das seguintes:

  • critical path and selects the least expensive alternative

  • critical path and selects the most expensive alternative

  • shortest path and selects the least expensive alternative

  • shortest path and selects the most expensive alternative

Explicação

Questão 179 de 200

1

Using Goldratt's meaning of the word "dependent," the activities of a project can be ordered into paths based on their resource dependencies as well as on their technological precedence requirements. The longest of these paths of sequentially time-dependent activities is known as the

Selecione uma das seguintes:

  • priority chain

  • critical chain

  • dependency path

  • heuristic path

Explicação

Questão 180 de 200

1

The ___________ heuristic provides a general solution for critical path and time and is usually the default rule for a schedule.

Selecione uma das seguintes:

  • as soon as possible

  • as late as possible

  • minimum slack first

  • shortest task first

Explicação

Questão 181 de 200

1

Monitoring, as an activity, should be kept distinct from __________, which uses data supplied by monitoring to bring actual performance into approximate congruence with planned performance.

Selecione uma das seguintes:

  • recording

  • controlling

  • collecting

  • reporting

Explicação

Questão 182 de 200

1

An appropriate and common secondary user for monitoring includes

Selecione uma das seguintes:

  • auditing, learning from mistakes, and reporting progress and status

  • exercising effective control over the project

  • evaluating current status of the project

  • fixing the blame when things go wrong

Explicação

Questão 183 de 200

1

According to the authors, the key items to be planned, monitored, and controlled are

Selecione uma das seguintes:

  • schedule, budget, and financial stability

  • schedule, quality, performance, and customer satisfaction

  • schedule, budget, and feasibility

  • schedule, budget, and performance

Explicação

Questão 184 de 200

1

According to the authors, in the planning - monitoring - controlling cycle, the directions of the flows indicate that

Selecione uma das seguintes:

  • information flows from the top to bottom and authority flows from the bottom to the top

  • information flows from the bottom to the top and authority flows from the top to the bottom

  • authority flows from the bottom to the top

  • information flows from the top to the bottom

Explicação

Questão 185 de 200

1

The first step in setting up a monitoring system is to

Selecione uma das seguintes:

  • collect existing data to see what data is relevant and available

  • collect every available piece of information so it can be analyzed

  • use whatever information is available

  • identify the key factors to be controlled

Explicação

Questão 186 de 200

1

In earned value analysis, the 50-50 rule assumes that

Selecione uma das seguintes:

  • 50 percent is earned when the task is half done and 50 percent is earned at completion

  • 50 percent is earned when the task begins and 50 percent is earned at completion

  • 50 percent is earned when the task begins and 50 percent is earned at the halfway stage

  • 50 percent is earned when the project is planned and 50 percent is earned when the project is over

Explicação

Questão 187 de 200

1

In earned value analysis, if the cost variance is (-$10,000),

Selecione uma das seguintes:

  • the cost variance is favorable

  • the cost variance is unfavorable

  • the scheduled variance is favorable

  • the scheduled cost avoidance is unfavorable

Explicação

Questão 188 de 200

1

One of the most common errors when collecting data is

Selecione uma das seguintes:

  • collecting rapidly changing data frequently

  • collecting data infrequently because data collection is so time consuming

  • collecting data that rarely changes

  • reporting to management after collecting data

Explicação

Questão 189 de 200

1

Reports for ______________ have a need for detailed information about individual tasks and the factors affecting such tasks.

Selecione uma das seguintes:

  • top executives

  • lower-level personnel

  • all the stakeholders

  • project managers

Explicação

Questão 190 de 200

1

The project control process should be viewed as a(n) ________________, with revised plans
and schedules (if warranted) following corrective actions. The project control process should run continuously until the project is completed.

Selecione uma das seguintes:

  • closed loop system

  • open loop system

  • open environment

  • earned value plan

Explicação

Questão 191 de 200

1

Ordinal rankings of performance are examples of a _________ type of measure.

Selecione uma das seguintes:

  • frequency count

  • raw number

  • verbal measure

  • subjective numeric rating

Explicação

Questão 192 de 200

1

____________ are used when some aspect of system performance cannot be measured
directly

Selecione uma das seguintes:

  • Indicators

  • Frequency counts

  • Raw numbers

  • Verbal measures

Explicação

Questão 193 de 200

1

____________ can often give the project manager early warning signals of potential problems in a project and help understand the relationships of individual tasks to one another and to the overall project.

Selecione uma das seguintes:

  • Detailed and timely reports

  • Executive summaries

  • Scope change reports

  • The WBS

Explicação

Questão 194 de 200

1

The earned value rule that divides the actual task time-to-date by the scheduled time for the task to calculate percent complete is called the _________ rule.

Selecione uma das seguintes:

  • 50-50

  • 0-100 percent

  • critical input use

  • proportionality

Explicação

Questão 195 de 200

1

In earned value analysis, EAC refers to the

Selecione uma das seguintes:

  • estimated cost at completion

  • estimated actual cost

  • eliminated annual cost

  • estimated annual cost

Explicação

Questão 196 de 200

1

In earned value analysis, BAC refers to the

Selecione uma das seguintes:

  • budgeted annual cost

  • budget at completion

  • budget at close-out

  • big annual cost

Explicação

Questão 197 de 200

1

If EV= $500, AC = $475, PV = $450; SV =

Selecione uma das seguintes:

  • $50

  • $25

  • 90%

  • 95%

Explicação

Questão 198 de 200

1

If CSI is less than 1, it is indicative of a(n)

Selecione uma das seguintes:

  • problem

  • good project

  • efficient project

  • budget error

Explicação

Questão 199 de 200

1

Conceptually, EAC represents the amount spent to date

Selecione uma das seguintes:

  • plus the delay costs

  • BAC

  • CV

  • ETC

Explicação

Questão 200 de 200

1

In earned value analysis, the 0 - 100 percent rule allows

Selecione uma das seguintes:

  • 100 percent credit before starting work and 0 percent credit after the completion

  • 0 percent credit when work begins and 100 percent credit when the project is complete

  • 0 percent credit when work begins and 100 percent credit at completion of the activity

  • 0 percent credit at completion of the activity and 100 percent credit at formal acceptance during scope verification

Explicação