faulkner.j
Quiz por , criado more than 1 year ago

A-Levels PRINCE2 (Question) Quiz sobre Foundation Questions 3, criado por faulkner.j em 12-06-2013.

406
1
0
faulkner.j
Criado por faulkner.j mais de 11 anos atrás
Fechar

Foundation Questions 3

Questão 1 de 63

1

Which of the following are a purpose of an Issue Report?
1. Document an off-specification
2. Record an issue resolution
3. Capture all problems or concerns within the project
4. Capture recommendations for handling a request for change

Selecione uma das seguintes:

  • 1,2,3

  • 1,2,4

  • 1,3,4

  • 2,3,4

Explicação

Questão 2 de 63

1

Which product establishes the baseline against which the project's actual performance is compared?

Selecione uma das seguintes:

  • Project Brief

  • Product Status Account

  • Project Initiation Document

  • Configuration Item Record

Explicação

Questão 3 de 63

1

Which is NOT identified when creating a product breakdown structure?

Selecione uma das seguintes:

  • Products to be created by internal resources

  • Products to be modified

  • Resources required to produce the products

  • Products to be created by an external third party

Explicação

Questão 4 de 63

1

Which statement regarding a project's outputs, outcomes and benefits is correct?

Selecione uma das seguintes:

  • All outputs have tangible benefits

  • Outcomes are the long term results of benefits

  • Outputs are changes in the way the project's products are used

  • Benefits are improvements resulting from project outcomes

Explicação

Questão 5 de 63

1

What process covers the acceptance and execution of project work by external suppliers?

Selecione uma das seguintes:

  • Controlling a Stage

  • Managing a Stage Boundary

  • Managing Product Delivery

  • Directing a Project

Explicação

Questão 6 de 63

1

Which is NOT a PRINCE2 integrated element?

Selecione uma das seguintes:

  • The Principles

  • The Techniques

  • The Themes

  • Tailoring to the project environment

Explicação

Questão 7 de 63

1

What is the goal of the 'Identify context' step within the recommended risk management procedure?

Selecione uma das seguintes:

  • Identify responses to risks identified in the Business Case

  • Understand the specific objectives that are at risk

  • Gather information about risks for inclusion in Highlight Reports to the Project Board

  • Identify the threats and opportunities that may affect the project's objectives

Explicação

Questão 8 de 63

1

Which is a purpose of the Project Product Description?

Selecione uma das seguintes:

  • Defines the reporting structure to be used by the project

  • Provides information on what the project is about and how it is to be managed

  • Describes what the project has to produce to obtain customer acceptance

  • Provides input to creation of the project mandate

Explicação

Questão 9 de 63

1

Which defines the sequence in which the products of a plan should be developed?

Selecione uma das seguintes:

  • Product Description

  • Product Breakdown Structure

  • Project Product Description

  • Product flow diagram

Explicação

Questão 10 de 63

1

If a Work Package is forecast to exceed its tolerances, how should a Team Manager inform The Project Manager?

Selecione uma das seguintes:

  • Raise an Exception Report

  • Issue an Exception Plan

  • Raise an Issue

  • Raise a risk

Explicação

Questão 11 de 63

1

What process enables an organisation to understand the work that needs to be done to deliver a project's products before it is approved?

Selecione uma das seguintes:

  • Directing a Project

  • Initiating a Project

  • Starting up a Project

  • Controlling a Stage

Explicação

Questão 12 de 63

1

Which is a purpose of Controlling a Stage process?

Selecione uma das seguintes:

  • Agree, perform and deliver project work

  • Draft a plan for the next stage

  • Agree stage tolerances

  • Take action to make sure that the stage remains within tolerance

Explicação

Questão 13 de 63

1

Which of the following roles can the Project Manager also perform?
1. Change Authority
2. Project Assurance
3. Project Support
4. Team Manager

Selecione uma das seguintes:

  • 1,2,3

  • 1,2,4

  • 1,3,4

  • 2,3,4

Explicação

Questão 14 de 63

1

Which is a responsibility of the Project Assurance role?

Selecione uma das seguintes:

  • Inform the Project Manager about the status of the project's products

  • Document the Project Board's reporting needs

  • Ensure the Project Manager is aware of the need to use any existing corporate standards

  • Inform corporate or programme management about the project's status

Explicação

Questão 15 de 63

1

When is it confirmed if a project's objectives have been achieved?

Selecione uma das seguintes:

  • During the Closing a Project process

  • During the final end stage assessment

  • During the Controlling a Stage process

  • During the Managing Product Delivery process

Explicação

Questão 16 de 63

1

Which is a definition of a risk cause?

Selecione uma das seguintes:

  • The impact of a risk on the stage and project tolerance

  • The source of a risk

  • The overall effect of a risk on the Business Case

  • How likely a risk is to occur in a given project situation

Explicação

Questão 17 de 63

1

When would the Team Manager be required to produce a Checkpoint Report?

Selecione uma das seguintes:

  • When a Work Package is being negotiated

  • At the frequency agreed in the Work Package

  • On completion of the quality -checking activities for each product

  • When reviewing how a stage is progressing

Explicação

Questão 18 de 63

1

Which is a recommended quality review team role?

Selecione uma das seguintes:

  • Project Manager

  • Presenter

  • Project Support

  • Producer

Explicação

Questão 19 de 63

1

What PRINCE2 principle supports planning only to a level of detail that is manageable and foreseeable?

Selecione uma das seguintes:

  • Continued Business Justification

  • Manage by Exception

  • Focus on products

  • Manage by stages

Explicação

Questão 20 de 63

1

In which situation might the Controlling a Stage process be used?

Selecione uma das seguintes:

  • Managing a long initiation stage of a complex product

  • Managing the activities of a complex programme

  • Managing support activities following the handover of the products to the operational environment

  • Creating an Exception Plan to replace the current Stage Plan

Explicação

Questão 21 de 63

1

Which is a responsibility of the business representative on the Project Board?

Selecione uma das seguintes:

  • Setting tolerance levels for the project

  • Ensuring the project represents value for money

  • Confirming the project delivers the required functionality

  • Checking the required quality levels are achieved by the project's products

Explicação

Questão 22 de 63

1

Which Statement correctly describes the relationship between Project Assurance and Quality Assurance?

Selecione uma das seguintes:

  • Project Assurance provides assurance to the project's stakeholders whereas quality assurance provides assurance to the wider Corporate or Programme organisation.

  • They are both the responsibility of the Project Board, but Project Assurance may be delegated.

  • They are both independent of the project

  • Project Assurance and quality assurance are both the responsibility of corporate or programme management

Explicação

Questão 23 de 63

1

Which of the following assists the Project Board in assessing the project viability at certain points as defined in the Project Plan?

Selecione uma das seguintes:

  • Receiving regular Checkpoint Reports

  • Authorising one stage at a time

  • Creating Exception Reports when tolerances are threatened

  • Authorising project closure

Explicação

Questão 24 de 63

1

Which is a purpose of the Change Theme?

Selecione uma das seguintes:

  • Prevent change to anything agreed in the Project Initiation Documentation

  • Ensure any potential changes to base-lined products are controlled

  • Assess and control uncertainty

  • Assess changes to only the specialist products

Explicação

Questão 25 de 63

1

What product would confirm the version numbers of all products being developed within a given stage.

Selecione uma das seguintes:

  • Configuration Item Record

  • Product Status Account

  • Stage Plan

  • Work Package

Explicação

Questão 26 de 63

1

Which is a benefit of using PRINCE2?

Selecione uma das seguintes:

  • Stakeholders are kept out of planning and decision-making

  • Participants understand each other's roles and needs

  • Stakeholder are not involved in assuring the project work

  • All problems are escalated to all stakeholders

Explicação

Questão 27 de 63

1

In what product would a product's quality tolerance be defined?

Selecione uma das seguintes:

  • Project Product Description

  • Product Description

  • Stage Plan

  • Quality Management Strategy

Explicação

Questão 28 de 63

1

When should the Managing a Stage Boundary process be undertaken?

Selecione uma das seguintes:

  • Close to the end of a management stage

  • After the completion of each management stage

  • At the end of the final stage

  • At the end of project start-up

Explicação

Questão 29 de 63

1

Which is a purpose of a risk budget?

Selecione uma das seguintes:

  • To fund risk management activities defined in the risk management procedure

  • To fund the cost of analysing requests foe change while executing a Work Package

  • Funds set aside from the project budget to cover the costs of implementing risk responses

  • Funds sets aside from the project budget to cover the costs of identifying risks to the project

Explicação

Questão 30 de 63

1

Which role is part of the project team?

Selecione uma das seguintes:

  • Corporate or programme management

  • Quality assurance

  • Stakeholder

  • Business assurance

Explicação

Questão 31 de 63

1

Identify the missing word in the following sentence.
PRINCE2 management stages relate to the [?], which is a factor that differentiates them from technical stages.

Selecione uma das seguintes:

  • use a particular set of technical skills

  • use a specific set of Team Managers

  • Authorisation from corporate or programme management

  • Commitment of resources

Explicação

Questão 32 de 63

1

What principle is supported by the Project Product Description?

Selecione uma das seguintes:

  • Continued business justification

  • Focus on product

  • Learn from experience

  • Manage by stages

Explicação

Questão 33 de 63

1

Identify the missing word(s) in the following sentence.
Quality planning provides the definition of the required products with their [?] as a foundation for Project Board agreement.

Selecione uma das seguintes:

  • Customer's quality expectation

  • quality test results

  • quality criteria

  • owners

Explicação

Questão 34 de 63

1

Which is a definition for risk probability?

Selecione uma das seguintes:

  • Scale of the risk should it occur

  • Probable effect on the project delivering its objectives

  • Probable timeframe within which the risk may occur

  • A measure of the likelihood of the risk occurring

Explicação

Questão 35 de 63

1

Which is NOT an event-driven control?

Selecione uma das seguintes:

  • Highlight Report

  • Exception Report

  • Project Initiation Documentation

  • End of a stage

Explicação

Questão 36 de 63

1

Identify the missing words in the following sentence.
The Project Board will allocate tolerances [?] to the Project Manager.

Selecione uma das seguintes:

  • for each Work Package

  • for the project

  • for each management stage

  • for each technical stage

Explicação

Questão 37 de 63

1

Which is NOT a purpose of a Product Description?

Selecione uma das seguintes:

  • Define the time and cost needed to produce the product

  • Define the quality skills required to check the product

  • Define the function and appearance of the product

  • Define the development skills required to produce the product

Explicação

Questão 38 de 63

1

Which is a purpose of a Communication Management Strategy?

Selecione uma das seguintes:

  • Ensuring the project team can use the required reporting tools

  • Producing reports for the Project Board

  • Defining the Communication method between the Project Board and corporate or programme management

  • Ensuring stakeholders are aware of their responsibilities

Explicação

Questão 39 de 63

1

Identify the missing word(s) in the following sentence.
During the Controlling a Stage process , the [?] us checked for any new or revised threats and their possible impact on the Business Case.

Selecione uma das seguintes:

  • Benefits Review Plan

  • End Stage Report

  • Risk Register

  • Risk Management Strategy

Explicação

Questão 40 de 63

1

In what plan should project closure activities be planned?

Selecione uma das seguintes:

  • Closure Stage Plan

  • Stage Plan for the final management stage

  • Initiation Stage Plan

  • Team Plan

Explicação

Questão 41 de 63

1

Which role is ultimately in charge of the project?

Selecione uma das seguintes:

  • Corporate or programme management

  • The Executive

  • The Senior User

  • The Sponsor

Explicação

Questão 42 de 63

1

What is the recommended frequency for Project Board meetings during a delivery stage to check progress?

Selecione uma das seguintes:

  • Monthly

  • Weekly

  • At the frequency set down in the 'Controls' section of the Project Initiation Documentation (PID)

  • There are no regular meetings of the Project Board during the stages

Explicação

Questão 43 de 63

1

In the event of the Project Manager being given conflicting instructions, whose instruction should he or she follow?

Selecione uma das seguintes:

  • The Executive's as chair of the Project Board

  • The Senior User's, as the role responsible for delivering the benefits

  • The Senior Supplier's, as the role responsible for ensuring that the project is achievable

  • Property Assurance's, as the role responsible for checking the running of the Project

Explicação

Questão 44 de 63

1

In the activity 'Authorise Initiation', which of the following would the Project Board use to support its decision on whether to go ahead and start the project?

Selecione uma das seguintes:

  • Mandate

  • Project Brief

  • Project Initiation Documentation

  • Stage Plan for the first delivery stage

Explicação

Questão 45 de 63

1

In which activity would the Project Board instruct the Project Manager to shut down the project prematurely, should that be necessary?

Selecione uma das seguintes:

  • Authorise Initiation

  • Authorise emergency action

  • Give ad hoc direction

  • Authorise project closure

Explicação

Questão 46 de 63

1

Which role is responsible for approving the Project Brief?

Selecione uma das seguintes:

  • Executive

  • Senior User

  • Senior Supplier

  • All of the above roles working together

Explicação

Questão 47 de 63

1

In which PRINCE2 process are the members of the Project Board appointed?

Selecione uma das seguintes:

  • Starting Up a Project

  • Initiating a Project

  • Managing a Stage Boundary

  • Controlling a Stage

Explicação

Questão 48 de 63

1

Which of the following is NOT an objective of the process Directing a Project? To ensure that:

Selecione uma das seguintes:

  • There's authority to initiate the Project.

  • There's authority to deliver the project's products.

  • Corporate or programme management has an interface to the project.

  • The products being produced by the teams are delivered to expectations.

Explicação

Questão 49 de 63

1

What is the final phrase in the following purpose statement. To enable the Project Board to be accountable for the project's success by making key decisions and exercising overall control while:

Selecione uma das seguintes:

  • Maintaining a low degree of risk exposure

  • Ensuring that the benefits specified in the Business Case can be delivered

  • Authorising spending only within the agreed financial tolerances (limits)

  • Delegating day-to-day management of the project to the Project Manager

Explicação

Questão 50 de 63

1

Which of the following is NOT an input into the activity 'Give ad hoc direction'?

Selecione uma das seguintes:

  • Highlight Report (the progress report from the Project Manager to the Board)

  • Exception Report (referral of something projected to go beyond the Project Manager's Authority)

  • Issue Report (a report setting down the detail of an issue being referred to the board)

  • End Stage Report (a report giving the board details such as the final cost of a stage just finishing)

Explicação

Questão 51 de 63

1

Which of the following does NOT form part of the Project Initiation Documentation (PID).

Selecione uma das seguintes:

  • Business Case

  • Project Plan

  • Risk Management Strategy

  • Stage Plan for the first delivery stage (the stage after the Initiation Stage)

Explicação

Questão 52 de 63

1

Which of the following strategies defines how change control will be carried out?

Selecione uma das seguintes:

  • Risk Management Strategy

  • Quality Management Strategy

  • Configuration Management Strategy

  • Communication Management Strategy

Explicação

Questão 53 de 63

1

Which of the following is an accurate definition of a stakeholder in PRINCE2?

Selecione uma das seguintes:

  • someone who's a member of the Project's Project Board

  • Someone who can affect, or be affected by, the project

  • Someone with financial responsibility for the project

  • Someone who's responsible for the delivery of business benefits

Explicação

Questão 54 de 63

1

Which of the following is used in PRINCE2 to record when business benefits will be measured?

Selecione uma das seguintes:

  • Benefits Register

  • Business Case

  • Benefits Review Plan

  • Project Cashflow

Explicação

Questão 55 de 63

1

Which of the following options name plans which are created in the process Initiating a project?

Selecione uma das seguintes:

  • Project Plan and Benefits Review Plan

  • Project Plan together with all Stage Plans

  • Project Plan and Business Plan

  • Benefits Review Plan and Team Plan

Explicação

Questão 56 de 63

1

Which of the following does PRINCE2 include as a section in the full Business Case?

Selecione uma das seguintes:

  • Benefits Review Plan

  • Benefits Realisation Schedule

  • Investment appraisal

  • Cost-benefit analysis

Explicação

Questão 57 de 63

1

Which role is responsible for producing the Project Initiation Documentation (PID)?

Selecione uma das seguintes:

  • Executive

  • Senior User

  • Sponsor

  • Project Manager

Explicação

Questão 58 de 63

1

What's the name of the progress report produced by the Project Manager in the Process Controlling a Stage?

Selecione uma das seguintes:

  • Stage Process Report

  • Highlight Report

  • Checkpoint Report

  • Stage Control Report

Explicação

Questão 59 de 63

1

Which of the following phrases is part of the purpose statement for the process Initiating a Project?

Selecione uma das seguintes:

  • To establish a clear organisation structure for the project

  • To produce a Stage Plan for each delivery stage to determine total cost

  • To ensure that all risks in the project have been identified and their management planned

  • To establish solid foundations for the project

Explicação

Questão 60 de 63

1

Progress reports, produced during each stage, are sent to Project Board members. What does the Project Manager check to see whether a copy should be sent to anyone else?

Selecione uma das seguintes:

  • Daily Log

  • Communication Plan

  • Issue Log

  • Communication Management Strategy

Explicação

Questão 61 de 63

1

Which of the following is NOT used as an input to the activity Prepare the Risk Management Strategy?

Selecione uma das seguintes:

  • Project Mandate

  • Project Brief

  • Lessons Log

  • Daily Log

Explicação

Questão 62 de 63

1

Why does the Project Manger check the Benefits Review Plan from time to time during a delivery stage?

Selecione uma das seguintes:

  • To update it with benefits achieved to date

  • To record who is responsible for specifying benefits

  • To enter details of dis-benefits identified in the Initiation Stage

  • To see whether any benefits reviews are due and, if so, arrange them

Explicação

Questão 63 de 63

1

Which of the following products are created in the process Initiating a Project?
1. Risk Register
2. Issue Register
3. Project Plan
4. Project Product Description

Selecione uma das seguintes:

  • 1,2,3

  • 1,2,4

  • 1,3,4

  • 2,3,4

Explicação