The project team is planning an upgrade to an electrical capacity for the manufacturing facility. During planning, the team members are confronted with the cost options for a new circuit that helps minimize the usage on the machinery. They consider the cost of purchasing the circuit for the time they need to develop the project. After that, the customer would take over the costs of the circuit. They are also considering a long-term commitment that the customer can make with the utility provider, which would provide a less costly solution over the use of the system. What type of analysis is the team considering?