Prep 2

Questão 1 de 150

1

Which of the following is NOT an organizational process asset update during Close Project or Phase Process?

Selecione uma das seguintes:

  • a. Historical information.

  • b. Final deliverable.

  • c. Formal acceptance forms.

  • d. Project files.

Explicação

Questão 2 de 150

1

Project Manager and Operations can intersect during:

Selecione uma das seguintes:

  • a. Ending of each phase or iteration.

  • c. During each project team evaluation.

  • d. Only during final training.

Explicação

Questão 3 de 150

1

A project manager wants to determine how his Project is doing at the end of sixth month. The actual total expense of the Project is $720,000. He have work for $620,000. The planned Budget for this length of time was $600,000. He finds that:

Selecione uma das seguintes:

  • a. There is not enough information to determine how the Project is doing.

  • b. The project is slightly ahead and cost overrun.

  • c. The Project is behind schedule and with savings.

  • d. The Project is on track.

Explicação

Questão 4 de 150

1

Influencing and Negotiation are examples of:

Selecione uma das seguintes:

  • a. Conflict management.

  • b. Project performance appraisals

  • c. .Interpersonal skills.

  • d. Problem solving

Explicação

Questão 5 de 150

1

You are the Project manager for employee time management Project. As part of the work, the Project team is considering four different applications providing different functionality and reports. Which of the following will be you biggest concern?

Selecione uma das seguintes:

  • a. Schedule delay.

  • b. Scope creep.

  • c. Low quality.

  • d. Over Budget.

Explicação

Questão 6 de 150

1

An estimating technique that uses a statistical relationship between historical data and other variables (for example, square footage in construction, lines of code in software development) is known as:

Selecione uma das seguintes:

  • a. Parametric Estimating

  • b. Analogous Estimating

  • c. Bottom-up Estimating

  • d. Historical Analysis

Explicação

Questão 7 de 150

1

Success of which of the following is measured in terms of benefits realization?

Selecione uma das seguintes:

  • a. Operations

  • b. Portfolios

  • c. Programs

  • d. Projects

Explicação

Questão 8 de 150

1

Which of the following is NOT a valid tool for risk identification??

Selecione uma das seguintes:

  • a. The Delphi Technique

  • b. Assumptions analysis

  • c. Pareto chart

  • d. SWOT analysis

Explicação

Questão 9 de 150

1

While a Project management plan is one of the primary documents, other documents are used to direct support it. Some of them are:

Selecione uma das seguintes:

  • a. Quality management plan

  • b. Basis of estimates, cost and schedule forecast, Issue log.

  • c. Process improvement plan

  • d. Requirements management plan and Configuration management plan.

Explicação

Questão 10 de 150

1

You are the Project manager of a software development project that has an approved Budget of $2,000,000. The Project started six months ago and has a total actual cost of $650,000 till now. After six months, the project suffered a really big change. The team must begin again analysis phase. The $650,000 is:

Selecione uma das seguintes:

  • a. Design cost.

  • b. Earned Value.

  • c. Sunk cost.

  • d. Cost variance.

Explicação

Questão 11 de 150

1

All of the following are required to establish cost baseline EXCEPT:?

Selecione uma das seguintes:

  • a. Estimate Activity Resources

  • b. Control Cost

  • c. Estimate Cost

  • d. Determine Budget

Explicação

Questão 12 de 150

1

You were invited to a meeting by a manager. When you entered the room you saw sitting there the key user working on your Project. The manager tells you that she has discusssed with the key user a change to the functionality being developed by your Project: they both agree that it should be changed from manual entry to system generated entry. He then asks you to fill out the required form and get it signed. What is going on?

Selecione uma das seguintes:

  • a. You are working like Coordinator

  • b. The management is actively involved in the Project.

  • c. This is a good example of integrated change control.

  • d. Manager is concerned with satisfying key stakeholders.

Explicação

Questão 13 de 150

1

Thinking about identification of stakeholders for a project, which of the following statements is incorrect?

Selecione uma das seguintes:

  • a. Project may get into trouble if negative stakeholders are ignored.

  • b. Stakeholders with a positive approach help project manager succeed.

  • c. Stakeholders only can be individuals who participate in project task, like project team.

  • d. Various stakeholders may have opposing views on a project.

Explicação

Questão 14 de 150

1

A project manager works with various stakeholders including stakeholders who do not support the project, mainly to overcome the resistance and gain the trust of those stakeholders. Which of the following skills did he use?

Selecione uma das seguintes:

  • a. Management

  • b. Negotiating

  • c. Interpersonal.

  • d. Writing

Explicação

Questão 15 de 150

1

Which of the following BEST describes the difference between Project management process groups and Project life cycle phases?

Selecione uma das seguintes:

  • a. Project phases are repeated in Project management process groups but may also continue from one Project management process group to another.

  • b. Project management process groups are used in waterfall while Project phases are used in iterative.

  • c. Project management process groups are repeated in Project phases

  • d. Project management process groups and Project phases are the same thing.

Explicação

Questão 16 de 150

1

The configuration management system with integrated change control provides a standaridized, effective and efficient way to centrally manage approved changes and baselines within a project. Configuration control is focused on:?

Selecione uma das seguintes:

  • a. Identification and correction of problems arising in functional areas of project implementation.

  • b. Specification of both the deliverables and de processes while change control is focused on identifying, documenting and controlling changes to the project and the product baselines.

  • c. Test new systems.

  • d. Identifying, documenting, and controlling changes to the project and the product baselines while change control is focused on the specification of both the deliverables and the processes.

Explicação

Questão 17 de 150

1

A organizational structure is

Selecione uma das seguintes:

  • a. Part of the operation processes.

  • b. Part of the organizational system

  • c. An Organizational Process Asset.

  • d. A topic which depends of the project.

Explicação

Questão 18 de 150

1

If you are looking at the work performance data to determine the project’s performance, what should you do NEXT?

Selecione uma das seguintes:

  • a. Update the lessons learned document.

  • b. Identify areas of improvement and create corrective actions.

  • c. Send the information to project sponsor

  • d. Compare the information you receive of the team performance with baselines and identify variances.

Explicação

Questão 19 de 150

1

A project manager has just started a newly selected project and going through initial meeting with sponsor and other key stakeholders. One VicePresident (VP) who is a key stakeholder wants to know in this moment how much the project will cost and how long it will take. The project manager has just initiated the project and does not have details but still provides an estimate to the VP. Which technique did he use?

Selecione uma das seguintes:

  • a. Parametric estimate

  • b. Analogous estimate

  • c. Bottom- Up estimate

  • d. Ball park or personal estimate

Explicação

Questão 20 de 150

1

To maintain the project scope under control, the project manager need to use:

Selecione uma das seguintes:

  • a. Documentation.

  • b. Inspection

  • c. Audits

  • d. Variance Analysis

Explicação

Questão 21 de 150

1

A Project manager is in a meeting, trying to understand the governmental regulations use of water in this region. This is an example of:

Selecione uma das seguintes:

  • a. Enterprise environmental factor.

  • b. A Project.

  • c. Government requirement.

  • d. A program.

Explicação

Questão 22 de 150

1

There is a serious defect in the finished product of a project that was completed a few months back and this results in a recall campaign to recall the defective products. What would be the best classification for these types of costs?

Selecione uma das seguintes:

  • a. Cost of Defects

  • b. Replacement of Costs

  • c. Recall Costs

  • d. Cost of Quality

Explicação

Questão 23 de 150

1

Which of the following is NOT an input to the Conduct Procurements?

Selecione uma das seguintes:

  • a. Activity Cost Estimating.

  • b. Source selection criteria.

  • c. Procurement statement of work.

  • d. Make -or-buy analysis.

Explicação

Questão 24 de 150

1

All of the following activities are included in Direct and Manage Project Work except:

Selecione uma das seguintes:

  • a. Create project deliverables.

  • b. Obtain, manage and use resources.

  • c. Establish communication channels external and internal to the project team.

  • d. Determine stakeholder communication requirements according to organizational culture.

Explicação

Questão 25 de 150

1

Which process includes the implementation of the approved changes to achieve the project objectives?

Selecione uma das seguintes:

  • a. Perform Integrated Change Control

  • b. Monitor and Control Project Work

  • c. Direct and Manage Project Work

  • d. Develop Project Management Plan

Explicação

Questão 26 de 150

1

Which of the following is an input to Control Stakeholder Engagement process?

Selecione uma das seguintes:

  • a. Work performance report

  • b. Work performance information

  • c. Work performance data

  • d. Work performance analysis.

Explicação

Questão 27 de 150

1

In order to calculate the estimate at completion (EAC), the following is typically needed:?

Selecione uma das seguintes:

  • a. Cost Performance Index (CPI) and the Actual Cost (AC)

  • b. Actual Cost (AC) and Estimate to Complete (ETC) the unfinished work.

  • c. Earned Value (EV) and the Actual Cost (AC).

  • d. Cost Performance Index (CPI), actual cost (AC), and the Earned Value (EV).

Explicação

Questão 28 de 150

1

The project team has just started breaking down the components of the Web development project in to smaller pieces that can easier manage. After doing this, what level of decomposition will they ultimately stop at:

Selecione uma das seguintes:

  • a. Validate Scope

  • b. Define Scope

  • c. Work packages

  • d. Define activities

Explicação

Questão 29 de 150

1

A Project manager have the responsability to satisfy the needs of?

Selecione uma das seguintes:

  • a. Task needs, team needs and individual needs.

  • b. Excursively the customer needs.

  • c. The needs that sponsor defined.

  • d. The needs of team.

Explicação

Questão 30 de 150

1

You have a seller working on a Time and Material contract. As per contract, two resources will work for 12 months on the project for a total cost of $180,000. However, the project took longer than expected and by the time it was completed, the two resources have been on the project for 18 months with a total cost of $250,000. What went wrong?

Selecione uma das seguintes:

  • a. Just like an initiative for finishing earlier, a penalty should have been proposed for delay

  • b. A maximum amount and time limit should have been established under the contract.

  • c. Fixed price contract, which is good for these kind of situations, should have been used.

  • d. Nothing went wrong since this was Time and Material contract under which resources charged for the time they worked on the project.

Explicação

Questão 31 de 150

1

What is an histogram?

Selecione uma das seguintes:

  • a. An Histogram is the same as a Pareto chart and shows the aggregation of defects

  • b. An Histogram is a pie chart that shows the distribution of inspections during the execution phase

  • c. An Histogram is a bar graph that shows data out of control

  • d. An Histogram can show the number of defects by source or by component.

Explicação

Questão 32 de 150

1

Which of the following is the information about the group of stakeholders included in the project charter?

Selecione uma das seguintes:

  • a. Stakeholders who are very interested in the project.

  • b. Stakeholders who will be directly involved in the project work.

  • c. Stakeholders who are affected by the project.

  • d. Executive level stakeholders.

Explicação

Questão 33 de 150

1

A project manager is analyzing and evaluating non-conformities. He is planning to use the 80/20 principle. What does this represent?

Selecione uma das seguintes:

  • a. 80% of the problems are caused by 20% of the causes

  • b. 80% of the problems can be resolved while the remaining 20% have no solution

  • c. 20% of the problems can be resolved while the remaining 80% have no solution

  • d. 20% of the problems are caused by 80% of the causes

Explicação

Questão 34 de 150

1

A project implemented several steps to improve customer satisfaction but the result from the next survey remained the same as before. How can the results be analyzed to find out why the steps did not make any improvement?

Selecione uma das seguintes:

  • a. Draw a control chart to see how many surveys results are outside limits.

  • b. Using root cause analysis to find what is still causing customer dissatisfaction.

  • c. Create a Pareto Chart to see what is the biggest dissatisfaction customer is having.

  • d. Perform quality audit to verify quality measurements.

Explicação

Questão 35 de 150

1

You are the project manager of a project and have come up with a bar graph of problems and their frequencies. This kind of chart is called a :?

Selecione uma das seguintes:

  • a. Deming chart

  • b. Pareto chart

  • c. Ishikawa diagram

  • d. Control chart

Explicação

Questão 36 de 150

1

A project-s approved Budget is $250,000 and planned Budget to date is $150,000, Actual Cost is $130,000. What will be the Cost Performance Index when Schedule Performance Index is 0.8?

Selecione uma das seguintes:

  • a. 120,000

  • b. 30,000

  • c. 1.08

  • d. 0.92

Explicação

Questão 37 de 150

1

Disputes may arise between a buyer and a seller on a contract. There are several techniques that can be used to resolve such disputes. Which of the following is the sequence from most favorable to leas favorable technique to be used?

Selecione uma das seguintes:

  • a. Litigation, Mediation, Arbitration, Confirmation,

  • b. Negotiation, Mediation, Arbitration, Litigation.

  • c. Negotiation, Escalation, Mediation, Arbitration.

  • d. Negotiation, Arbitration, Mediation, Litigation.

Explicação

Questão 38 de 150

1

Which of the following is an input to Manage Team?

Selecione uma das seguintes:

  • a. Project assignments defining the specific roles of the team.

  • b. Change request.

  • c. Work performance data.

  • d. Work performance standards.

Explicação

Questão 39 de 150

1

A common way of representing the stakeholder management strategy is a _____________.?

Selecione uma das seguintes:

  • a. Communication strategy

  • b. Stakeholder register

  • c. Stakeholder analysis matrix

  • d. Power/interest grid

Explicação

Questão 40 de 150

1

You are managing a gas pipeline river crossing project. The project involves drilling piles in the river bed to build a bridge to cross the gas pipeline over the river. The company have three large trailers for project execution. This trailers are consider:

Selecione uma das seguintes:

  • a. An organizational process asset of Direct and Manage Project Work.

  • b. Part of the seller equipment.

  • c. An Enterprise Environmental Factor of Direct and Manage Project Work.

  • d. A contingency reserve.

Explicação

Questão 41 de 150

1

A market demand, a business need, and/or legal requirement are examples of:

Selecione uma das seguintes:

  • a. Reasons to hire a project manager

  • b. Reasons projects are iniciated

  • c. Reasons people or businesses become stakeholders

  • d. Reasons to sponsor a project

Explicação

Questão 42 de 150

1

A project schedule has activities and milestones. What do you know about milestones?

Selecione uma das seguintes:

  • a. Activities are summed up into milestones.

  • b. Milestones are required to created a valid schedule.

  • c. WBS work packages are also know as milestones.

  • d. Milestones can be a sponsor’s requirements.

Explicação

Questão 43 de 150

1

Which of the following normally provides the summary milestone schedule?

Selecione uma das seguintes:

  • a. Project requirements document.

  • b. Business case.

  • c. Project scope statement.

  • d. Project charter.

Explicação

Questão 44 de 150

1

Mr. PM has been working on the Enterprise learning management system Project for 10 months with a fairly large team. Yesterday, the new system was made available to the whole organization with only one glitch viz. The mass email with incorrect login and password was sent out to all the employees. The Project team worked on the issue diligently and within 4 hours sent out the correct email to everyone. Mr. PM met his manager on his way to the office this morning. The manager remarked “I am very disappointed”. What could be the reason?

Selecione uma das seguintes:

  • a. Mr. PM did not go through Integrated Change Control Process to fix the issue.

  • b. Mr. PM did not mention his manager«s name in the email sent out to the whole organization thanking the team for hard work.

  • c. The manager had received regular updates from Mr. PM on the preventive measures being taken to ensure email goes out smoothly to the whole organization but still a supposedly prevented defect occurred.

  • d. Mr. PM did not ask manager`s permission if the problem should be fixed or not.

Explicação

Questão 45 de 150

1

You are the Project manager for process automation project of a fast food company with 20 restaurants. As part of the work, the project team is collecting requirements of different functionality. Which of the following will be you biggest concern?

Selecione uma das seguintes:

  • a. Schedule delay.

  • b. Scope creep.

  • c. Quality assurance.

  • d. Close Procurements.

Explicação

Questão 46 de 150

1

The inflation in a country is an important aspect when sponsor and project manager are reviewing a Project Charter. It is consider:

Selecione uma das seguintes:

  • a. A requirement of the project success.

  • b. A measurable objective.

  • c. An Organizational Process Asset.

  • d. An Enterprise Environmental Factor.

Explicação

Questão 47 de 150

1

The Cost Performance Baseline is a time phased budget and is used as a basis to measure, monitor and control overall cost performance of the project. It is usually displayed in the form of:?

Selecione uma das seguintes:

  • a. A Z curve

  • b. An inverted S curve

  • c. Pie-chart

  • d. An S-curve

Explicação

Questão 48 de 150

1

A Project manager is managing three project simultaneously. These three projects, A, B, and C are related to each other, Project A is to customize a software application X, Project B is to deploy X to the whole organization and C is to train users according to their roles in X. How would you describe the situation??

Selecione uma das seguintes:

  • a. This is an operational work and should not be considered Project.

  • b. He is managing one Project, which has three phases.

  • c. Project B should start after Project A and Project C after Project B.

  • d. He is managing a program with three inter-related projects.

Explicação

Questão 49 de 150

1

What does consultants, professionals and technical associations provide during project execution?

Selecione uma das seguintes:

  • a. Deliverable status

  • b. Work performance data

  • c. Expert judgment

  • d. Issue management procedures

Explicação

Questão 50 de 150

1

What is the process of random selection and inspection of a work product?

Selecione uma das seguintes:

  • a. Control Charting

  • b. Flow Charting

  • c. Statistical Sampling

  • d. Inspection

Explicação

Questão 51 de 150

1

A project manager issued a purchase order to a seller to provide catering service during a major event. The event is three day meeting to be held for requirements gathering. The project manager is in which of the following processes?

Selecione uma das seguintes:

  • a. Plan Procurement Management

  • b. Prepare Procurements

  • c. Conduct Procurements

  • d. Control Procurements.

Explicação

Questão 52 de 150

1

Which of the following processes best facilitates lessons learned document?

Selecione uma das seguintes:

  • a. Plan Communications Management.

  • b. Identify Stakeholders.

  • c. Manage Quality

  • d. Plan Quality Management.

Explicação

Questão 53 de 150

1

The team is in the process of completing the Work Breakdown Structure of the project. Once they have completed this, which of the following can they begin to work on?

Selecione uma das seguintes:

  • a. Estimate Cost

  • b. Develop Schedule

  • c. Estimate Activity Durations

  • d. All of the answers

Explicação

Questão 54 de 150

1

What tool does Project Manager could use if he wants to reduce the sensivility of product performance to variations caused by environmental differences?

Selecione uma das seguintes:

  • a. Design of Experiments (DOE)

  • b. Benchmarking

  • c. Statistical Sampling

  • d. Pareto Diagram

Explicação

Questão 55 de 150

1

A project's approved Budget is $250,000 and planned Budget to date is $150,000. What will be the Schedule Variance when Schedule Performance Index is 0.8?

Selecione uma das seguintes:

  • a. 50,000

  • b. 30,000

  • c. -50,000

  • d. -30,000

Explicação

Questão 56 de 150

1

A team member is really confused about the priorities of their assigned job because he receives orders from Project Manager and from functional Manager, and doesn't know to whom listen. He is living the typical effect of:

Selecione uma das seguintes:

  • a. The Matrix structure in organization communication problems.

  • b. The organizational process assets of the project.

  • c. The inexperience.

  • d. The lack of requirements management process.

Explicação

Questão 57 de 150

1

Which of the following is NOT a typical characteristic of a project management office (PMO)?

Selecione uma das seguintes:

  • a. Developing and managing project management methodology and standards.

  • b. Coaching and training project managers.

  • c. Managing projects resources and assigning project tasks.

  • d. Defining and maintaining vendor engagement processes.

Explicação

Questão 58 de 150

1

Which is the main difference between project expediter and project coordinator??

Selecione uma das seguintes:

  • a. The expediter have more responsibility than the coordinator

  • b. A project expediter works as staff assistant and coordinator works in operational activities.

  • c. Project coordinators have power to make some decision, have some authority

  • d. Project coordinator have less work than project expediter.

Explicação

Questão 59 de 150

1

What is the output of a decision tree analysis?

Selecione uma das seguintes:

  • a. List of decisions that can be made.

  • b. Expected monetary value of each option.

  • c. Recommended corrective actions.

  • d. Cost of managing the risk that was analyzed,

Explicação

Questão 60 de 150

1

Your project has completed its 50% deliverables and is in the middle of execution. You created a stakeholder register during initiating process which was then used to create a stakeholder management strategy. You have been managing stakeholders according to this strategy. Now, you have recently become aware of a highly influential stakeholder that has not been identified in the stakeholder register. What is the BEST course of action?

Selecione uma das seguintes:

  • a. Ask the project sponsor if this person be included in the stakeholder register.

  • b. Send a request to senior management asking for direction.

  • c. Update stakeholder register and stakeholder management strategy with the new information.

  • d. Inform the stakeholder that it is too late for him to be involved in the project as the stakeholder register was completed during initiating process.

Explicação

Questão 61 de 150

1

You are a Project manager working on new product development Project. You have a long-term contract with a reputed seller. Under the contract, the seller is charging you $50 per hour per resource engaged on your Project and $200 per week as overhead charges. You have a ­­­­­­­­­____________ contract with the seller.?

Selecione uma das seguintes:

  • a. Cost reimbursable.

  • b. Fixed Price.

  • c. Time and material.

  • d. Cost plus fixed fee.

Explicação

Questão 62 de 150

1

Which of the following is an input to Control Stakeholder Engagement process??

Selecione uma das seguintes:

  • a. Work performance report

  • b. Work performance information

  • c. Work performance data

  • d. Work performance analysis.

Explicação

Questão 63 de 150

1

A project manager is unsure of the difference between precision and accuracy and asks for your help in understanding the difference between the two terms. Which of these responses would be the best response to such a question?

Selecione uma das seguintes:

  • a. Precision is consistency that the value of a repeated set of measurements are clustered and have little scatter whereas accuracy is correctness that the measured value is very close to the true value

  • b. Accuracy is consistency that the value of a repeated set of measurements are clustered and have little scatter whereas precision is correctness that the measured value is very close to the true value

  • c. Accuracy and Precision are equivalent and normally specified in the SOW by the customer who issues the SOW

  • d. Accuracy is more important than precision. The project management team must decide the level of accuracy required

Explicação

Questão 64 de 150

1

Which is one objective of Critical Path Method (CPM)?

Selecione uma das seguintes:

  • a. Define the possible activity paths in the project.

  • b. Determine the amount of scheduling flexibility .

  • c. Identify the resources needed in critical activities.

  • d. Identify the most important activities, for example, director meetings.

Explicação

Questão 65 de 150

1

ABC company is a important manufacturing firm. They are looking for a experiment project manager for a critical project . They consult to you about that aspects the firm should consider in order to evaluate candidates for this important position. What recommendation would you do to them:

Selecione uma das seguintes:

  • a. To apply a really difficult knowledge exam to evaluate his knowledge in project management.

  • b. Prepare a real case and stress the candidate to evaluate his leadership in real situations. Personal skills are really important.

  • c. Evalate his conflict resolution habilities, because projects are conflictive situations, mainly during execution phase, when project plan could change.

  • d. To evaluate his knowledge in project management, their experience in applying this knowlege in real projects and his personal competences like leadership, communications, etc.

Explicação

Questão 66 de 150

1

For effective risk management, project risk ______________.?

Selecione uma das seguintes:

  • a. Should be identified whether they are expected to have positive or negative outcome.

  • b. Acceptance is the best strategy.

  • c. Should be identified, deeply analyzed and responded at the beginning of the project.

  • d. Should continue to be tracked even after it has occurred.

Explicação

Questão 67 de 150

1

Project manager and his team is talking about the stakeholders management and the must important objective of that. They conclude to assign more priority to:

Selecione uma das seguintes:

  • a. Visit all stakeholders identified to report project status

  • b. Send reports to key stakeholders.

  • c. Avoid conflicts among stakeholders.

  • d. Compromise them and manage their satisfaction.

Explicação

Questão 68 de 150

1

Which of the following are part of the Organizational Process Asset of Direct and Manage Project Work:

Selecione uma das seguintes:

  • a. Organizational culture.

  • b. Infrastructure, existing facilities and capital equipment.

  • c. Stakeholder risk tolerances.

  • d. Communication requirements defining allowed communication media, record retention and security requirements.

Explicação

Questão 69 de 150

1

When managing a medical research project, what should you focus on during the Executing processes?

Selecione uma das seguintes:

  • a. Measuring progress.

  • b. Performing the Project work.

  • c. Conflict resolution.

  • d. Coordinating human and other resources.

Explicação

Questão 70 de 150

1

Organizational Process assets that are updated during the Close Project or Phase process are:?

Selecione uma das seguintes:

  • a. Business case.

  • b. Project management plan, expert judgment.

  • c. Project management plan, project calendars

  • d. Project charter

Explicação

Questão 71 de 150

1

Which of the following will have the BIGGEST impact in making project a success?

Selecione uma das seguintes:

  • a. Expert level technical knowledge.

  • b. Clear roles and responsibilities.

  • c. Co-located project team

  • d. Highly experienced project manager

Explicação

Questão 72 de 150

1

What is an output of the Close Procurements process that the buyer provides to the seller?

Selecione uma das seguintes:

  • a. A copy of the lessons learned document

  • b. Written notice of acceptance of all deliverables and completion of contract.

  • c. Project management plan updates

  • d. Letter of appreciation to the seller.

Explicação

Questão 73 de 150

1

You and your team celebrate, as part of the management process, a weekly meeting to review their practices about work, communication and project team management. The main objective of it is:

Selecione uma das seguintes:

  • a. To gain confidence from the key stakeholders

  • b. To evaluate the team

  • c. To achieve the project objectives and contribute to organizational learning.

  • d. To collect work performance data.

Explicação

Questão 74 de 150

1

A project manager is working on office space refresh project. While using earned value technique, he determines that the project will run over budget by $2,000 if current performance trend continues. The project manager has used ­­­­­­­­­­___________ characteristics to identify the issue.?

Selecione uma das seguintes:

  • a. Interpersonal

  • b. Knowledge

  • c. Problem solving

  • d. Earned Value.

Explicação

Questão 75 de 150

1

When the project manager is looking for providers, one source selection criteria are all except:

Selecione uma das seguintes:

  • a. Management approach and experience

  • b. Past performance and references.

  • c. The format of SOW they use.

  • d. Product cost and life cycle cost

Explicação

Questão 76 de 150

1

The technique of comparing actual or planned project practices to those of other projects to generate ideas for improvement and to provide a basis by which to measure performance is known as:?

Selecione uma das seguintes:

  • a. Workbench

  • b. Benchmarking

  • c. Quality Control

  • d. Best Practices

Explicação

Questão 77 de 150

1

A project manager wants to determine how his Project is doing at the end of sixth month. The actual total expense of the Project is $720,000. The planned Budget for this length of time was $600,000. He finds that:

Selecione uma das seguintes:

  • a. The Project is over-budget.

  • b. There is not enough information to determine how the Project is doing.

  • c. The Project is a head of Schedule.

  • d. The Project is on track.

Explicação

Questão 78 de 150

1

Status reports, memos and information notes are examples of:

Selecione uma das seguintes:

  • a. Work Performance Information.

  • b. Project management Plan Updates.

  • c. Work performance reports.

  • d. Project Management Information System (PMIS).

Explicação

Questão 79 de 150

1

A project is estimated to cost $50,000 with a timeline of 50 days. After 25 days, the porject manager finds that 50% of the project is complete and Actual costs are $50,000. What is the Cost Performance Index (CPI)?

Selecione uma das seguintes:

  • a. CPI is 1

  • b. CPI is 1.5

  • c. CPI is 2

  • d. CPI is 0.5

Explicação

Questão 80 de 150

1

Which of the following is NOT a valid tool for risk identification?

Selecione uma das seguintes:

  • a. Braingstorming

  • b. Assumptions analysis

  • c. Histogram chart

  • d. SWOT analysis

Explicação

Questão 81 de 150

1

If a project’s actual total cost is $300,000 against a total budget of $400,000 and the project is 75% complete, then what is the earned value?

Selecione uma das seguintes:

  • a. Cannot be determined from the information given.

  • b. 0.75

  • c. 300,000

  • d. 100,000

Explicação

Questão 82 de 150

1

A project manager has been assigned to a project that is in trouble. He is going to focus his attention on:

Selecione uma das seguintes:

  • a. Controlling procurement.

  • b. Schedule because on-time delivery is most important.

  • c. Communication because good communication ensure Project success.

  • d. Factors that have the biggest impact on meeting Project objectives.

Explicação

Questão 83 de 150

1

Business value is defined as:

Selecione uma das seguintes:

  • a. The cost of their buildings, infrastructure and furniture.

  • b. The net quantifiable benefit derived from a business endeavor. The benefit may be tangible, intangible or both.

  • c. The knowledge base and the experience of the project team

  • d. The cash flow at the end of the project.

Explicação

Questão 84 de 150

1

Which of the following is NOT an input to the Plan Procurement Management Process?

Selecione uma das seguintes:

  • a. Work performance data

  • b. Project scope statement

  • c. Work breakdown structure

  • d. Stakeholder register

Explicação

Questão 85 de 150

1

Which of the following statements is TRUE concerning functionality that is over and above the documented scope?

Selecione uma das seguintes:

  • a. It should be channeled back through the change control board to ensure that it gets documented into the project scope

  • b. Additional functionality should be leveraged to exceed customer expectations.

  • c. The final product should include all the functionality and only the functionality documented in the scope baseline.

  • d. Additional functionality should be issued by the customer, reviewed by the project manager and approved for implementation.

Explicação

Questão 86 de 150

1

One of the inputs you need to close a project is:
Direct and Manage project work activities include?

Selecione uma das seguintes:

  • a. Document analysis

  • b. Variance analysis

  • c. A final report

  • d. Configuration management knowledge base

Explicação

Questão 87 de 150

1

All of the following are correct statements about the contract change control system EXCEPT:?

Selecione uma das seguintes:

  • a. Buyer and seller both can submit a change request to the contract change control system.

  • b. Contract change control system is mainly used during the Control Procurements process

  • c. Contract change control system should be defined separately from the terms of the contract.

  • d. Contract change control system is an Enterprise Environmental Factor, and is part of the Project’s integrated change control system.

Explicação

Questão 88 de 150

1

The project manager and the project management team are in a meeting reviewing the scope baseline and the validated products to ensure competition of the project, and use for it a trend analysis method. Which process are the project manager doing?

Selecione uma das seguintes:

  • a. Validate Scope.

  • b. Define Scope.

  • c. Perform Integrated Change Control.

  • d. Close Project or Phase.

Explicação

Questão 89 de 150

1

When an organization rejects a project because it is not aligned to its strategy, they:

Selecione uma das seguintes:

  • a. Improve their revenue.

  • b. Reject a non profit projects.

  • c. Improve business value using Portfolio Mangement techniques.

  • d. Adverse to risk.

Explicação

Questão 90 de 150

1

All of the following are characteristics of the project management information system (PMIS) EXCEPT:

Selecione uma das seguintes:

  • a. Inculde a standardized set of automated tools available within the organization and integrated into a system.

  • b. It is used by the project management team to support generation of the project management plan, facilitate feedback as the document is developed, control changes to the project management plan, and release the approved document.

  • c. It is used by the project management team to monitor and control the execution of activities that are planned and scheduled in the project management plan. The PMIS is also used to create new forecasts as needed.

  • d. It is used by the project management team only to generate presentations to key stakeholders.

Explicação

Questão 91 de 150

1

Funding requirements for a project are usually in incremental amounts that are not continuous , and these appear as a step function in the graph depicting Cash flow, Cost baseline and Funding. Any gap at the end of the project, between funds allocated and the cost baseline and cash flow amounts represents:

Selecione uma das seguintes:

  • a. The amount of management reserve that was not used

  • b. The amount of management reserve that was not allocated

  • c. The cost overrun

  • d. Innefective utilization of funds

Explicação

Questão 92 de 150

1

You are the Project manager of a design build Project that has an approved Budget of $1,000,000. The Project started eight months ago and has a total actual cost of $650,000 till now. The $650,000 is the:

Selecione uma das seguintes:

  • a. Design cost.

  • b. Earned Value.

  • c. Expended cost.

  • d. Cost variance.

Explicação

Questão 93 de 150

1

A finales del mes de marzo, con unos seis meses de ejecución del proyecto, el cliente nos solicita comparar el desarrollo del trabajo con la línea base. Esta línea base servirá para realizar la comparación en el/los proceso/s de:?

Selecione uma das seguintes:

  • a. Validar el Alcance

  • b. Controlar el Alcance

  • c. Validar el Alcance y Controlar el Alcance

  • d. Revisar el Alcance y análisis de stakeholders

Explicação

Questão 94 de 150

1

Lucy is a project manager involved in the Estimate Costs process in the initiation phase of a project. Given the limited detail available to her, what would you expect the range of her estimate to be and what would you call such an estimate?

Selecione uma das seguintes:

  • a. -25% to +25%, Rough Order of Magnitude

  • b. -10 to +10% , Budgetary

  • c. -1% to +1%, Definitive

  • d. -25% to +75% , Order of Magnitude

Explicação

Questão 95 de 150

1

A business case includes all of the follow, except:

Selecione uma das seguintes:

  • a. Business needs

  • b. Analysis of the situation

  • c. Organizational culture.

  • d. Options identification

Explicação

Questão 96 de 150

1

You are a project manager working on a global project with project team members distributed in four continents. Which of the following can help you the MOST to be successful?

Selecione uma das seguintes:

  • a. Knowledge of local languages and customs

  • b. Instant messaging & email

  • c. Well developed virtual communications skills

  • d. Responsibility Assignment Matrix.

Explicação

Questão 97 de 150

1

Mr. PM and the project management team are learning project management best practices. The team are performing really well. They celebrated only one stakeholders identification session before project kick off. Their mentor is not satisfied with stakeholder management practices mainly because:

Selecione uma das seguintes:

  • a. Project Management Team didn`t identify all stakeholders.

  • b. Mr. PM did not explain to stakeholders the integrated change control.

  • c. Mr. PM and the team celebrated stakeholder identification only one time and this proces must be a continuous process throughout the project.

  • d. Mr. PM didn´t asked manager`s permission to change stakeholder list.

Explicação

Questão 98 de 150

1

If you have to choose one of the following as NOT being a project, which one will it be??

Selecione uma das seguintes:

  • a. Building a 10 ft. x 15 ft. shed in your backyard.

  • b. Creating a project management office in the IT department.

  • c. Increasing parking spaces from 300 to 400 in a parking lot.

  • d. Shipping 10 times larger than usual order received through internet.

Explicação

Questão 99 de 150

1

Which of the following tools is used during Plan Quality?

Selecione uma das seguintes:

  • a. Control Charts

  • b. Scatter Diagram

  • c. Mind maping

  • d. Cause and Effect Diagram

Explicação

Questão 100 de 150

1

Thinking about identification of stakeholders for a project, which of the following statements is incorrect?

Selecione uma das seguintes:

  • a. Project may get into trouble if negative stakeholders are ignored.

  • b. Stakeholders with a positive approach help project manager succeed.

  • c. Various stakeholders may have opposing views on a project.

  • d. Manage the expectations of positive stakeholders should have a higher priority than the negative stakeholders.

Explicação

Questão 101 de 150

1

Which one of the following is NOT an input to Develop Project Charter process?

Selecione uma das seguintes:

  • a. Enterprise environmental factors

  • b. Expert judgment

  • c. Business case

  • d. Statement of work

Explicação

Questão 102 de 150

1

Which project management process will you use if you find out that the task needed to accomplish a work package are not valid?

Selecione uma das seguintes:

  • a. Integrated change control

  • b. Corrective action

  • c. Preventive action

  • d. Monitor and control project work

Explicação

Questão 103 de 150

1

The project team has decided that a preventive action must be taken to solve an possible deviation. What are they referring to?

Selecione uma das seguintes:

  • a. They are referring to an activity that can help eliminate performance of the desired state.

  • b. They are referring to an activity that can help lessen the chances of negative outcomes of actions.

  • c. They are referring to an activity that can help repair the chances of negative impacts.

  • d. They are referring to an activity that can help improve performance back to the desired state.

Explicação

Questão 104 de 150

1

What is an output of Control Procurements process?

Selecione uma das seguintes:

  • a. Work performance report

  • b. Work performance information

  • c. Resource calendars

  • d. Source selection criteria

Explicação

Questão 105 de 150

1

As Project manager for a new product development Project, you read a report on hot costumer trends for the next decade. You realize that your product lacks some of those aspects. After review and discussion with the business and the marketing department, changes were approved to the product specifications. Why did this charge occur?

Selecione uma das seguintes:

  • a. Because an external factor has impacted your Project.

  • b. Because scope was not well defined.

  • c. Because your Project Budget does not allow lavish spending

  • d. Because requirements were incorrect

Explicação

Questão 106 de 150

1

What happens in the Monitor and Control Project Work process?

Selecione uma das seguintes:

  • a. Planned work as per Project management plan is completed.

  • b. Actual project performance is compared with the baselines.

  • c. Actual project performance is compared with schedule performance baseline.

  • d. Planned Project performance is compared with the Budget baseline.

Explicação

Questão 107 de 150

1

Which of the following relates to Root Cause Analysis?

Selecione uma das seguintes:

  • a. Process Analysis

  • b. Performance Measurements

  • c. Quality Audits

  • d. Quality control measurements

Explicação

Questão 108 de 150

1

Project manager is preparing the procurement issues. He is finding out what kind of construction permissions they must have to develop the project. He is considering:

Selecione uma das seguintes:

  • a. The organizational process assets of the project.

  • b. How to prepare the final budget of the project.

  • c. Enterprise Environmental Factors of the project.

  • d. He is preparing to select sellers.

Explicação

Questão 109 de 150

1

Which of these are not inputs to the Determine Budgets process??

Selecione uma das seguintes:

  • a. Cost Baseline, Requirements traceability matrix

  • b. Project schedule, contracts

  • c. Basis of estimates, Activity cost estimates

  • d. Project schedule, Resource calendars

Explicação

Questão 110 de 150

1

Right after you received final deliverable approval from the sponsor of your Project, you were assigned to a new Project and asked to skip the closing process for current Project. For which kind of Project can you skip the closing processes?

Selecione uma das seguintes:

  • a. Large Projects.

  • b. Administrative Projects.

  • c. Closing processes should not be skipped for any kind of Project.

  • d. Small projects.

Explicação

Questão 111 de 150

1

A characteristic of the Project Life Cycle is:

Selecione uma das seguintes:

  • a. Always are identical, in all kind of industries

  • b. Risk and uncertainly are highest at the end of the project

  • c. Cost and staffing levels are low at the start, peak as the work is carried out, and drop rapidly as the project draws to a close.

  • d. The cost and staffing are the same regardless of the type of project

Explicação

Questão 112 de 150

1

A Project manager working on highway extension Project finds out that noise barriers are required to be approved by the provincial highway authority before the work can proceed. The company does have a defined process and forms to go through the approval process. This defined process can be called as?

Selecione uma das seguintes:

  • a. Enterprise Environmental Factor.

  • b. A Project.

  • c. Government requirement.

  • d. A program.

Explicação

Questão 113 de 150

1

Which of the following is not part of the Project Management Plan?

Selecione uma das seguintes:

  • a. Configuration management plan.

  • b. Basis of estimates.

  • c. Risk management plan.

  • d. WBS dictionary.

Explicação

Questão 114 de 150

1

You are the project manager of a network replacement Project for a 40-floor office building. You plan to hire a contractor to pull the old cables out and then install the new cables. The work has to be done in such a way to have minimum to zero disruption to the tenant organization during business hours, hence you need to hire a well experienced reputed firm. You contract the procurement department to develop a list of firms that have the capability to do the work. What are you referring to?

Selecione uma das seguintes:

  • a. Develop evaluation criteria.

  • b. Negotiating a contract.

  • c. Solicitation package to be sent out to prospective sellers.

  • d. Qualified sellers list

Explicação

Questão 115 de 150

1

What is the name of the technique that examines the problems experienced within the project, limitations faced, and the feeling of non-value-added work?

Selecione uma das seguintes:

  • a. Scatter diagram.

  • b. Quality audit.

  • c. Process analysis.

  • d. Quality assurance.

Explicação

Questão 116 de 150

1

Acquiring, training, and managing team members that have been assigned to the project are part of which process??

Selecione uma das seguintes:

  • a. Direct and Manage Project Work.

  • b. Acquire Project Team.

  • c. Monitor and Control Project Work.

  • d. Manage Team.

Explicação

Questão 117 de 150

1

As a project manager, you periodically do project performance reviews to compare cost performance over time, schedule activities or work packages over-running and under-running budget, milestones due, and milestones met. Which of the following is not a valid technique that you would use for performance-reporting?

Selecione uma das seguintes:

  • a. Trend Analysis

  • b. Earned Value Performance

  • c. Variance Analysis

  • d. Integration Analysis

Explicação

Questão 118 de 150

1

A Sara le han pedido que se haga cargo del desarrollo e implementación de un sistema de planificación de recursos organizacionales para su empresa. Sara ha enviado una solicitud para reunirse con el patrocinador del proyecto y discutir sobre la planificación de la gestión de los interesados. El patrocinador piensa que tal planificación no es importante en proyectos internos como el que está llevando Sara; sin embargo él piensa que únicamente con planificar bien la gestión del alcance, el cronograma y los costos es suficiente para este tipo de proyectos. El patrocinador le ha pedido a Sara describir el objetivo de la reunión. ¿Cuál de las siguientes es la mejor respuesta para el patrocinador??

Selecione uma das seguintes:

  • a. El objetivo de la reunión es desarrollar el registro de los interesados del proyecto.

  • b. El objetivo de la reunión es la de desarrollar las estrategias para efectivamente gestionar las expectativas de los interesados en el proyecto y lograr su participación eficaz durante el proyecto.

  • c. El objetivo de la reunión es cumplir con los estándares dictados por el PMBOK.

  • d. El objetivo de la reunión es la de identificar y clasificar a las interesados del proyecto.

Explicação

Questão 119 de 150

1

Which of the following is an input to Manage Stakeholder Engagement process??

Selecione uma das seguintes:

  • a. Issue log

  • b. Change log

  • c. Change request

  • d. Work performance data

Explicação

Questão 120 de 150

1

Project Manager is calculating SPI and SV (Schedule Variance) in order to determine if the project is still within the tolerances defined by client. He will use this information to:

Selecione uma das seguintes:

  • a. Evaluate the project team.

  • b. Prepare a change request.

  • c. Define project forecast.

  • d. Prepare provider payments.

Explicação

Questão 121 de 150

1

You find it very valuable to attend the regular monthly Project management training session. Most Project managers at your office share your view and make effort to attend these sessions. It was mentioned in the last session that improvement in Project management practice has been observed since the start of these training sessions a year ago. The PMO manager is quite pleased with these results because:?

Selecione uma das seguintes:

  • a. Training, coaching and mentoring is one of the functions of PMO.

  • b. Stage gate review can be scheduled to enable Project to proceed to next phases.

  • c. Resources can be managed by Project managers.

  • d. More strategic projects can be initiated.

Explicação

Questão 122 de 150

1

You are working as a seller’s Project manager for a buyer on a cost reimbursable contract. The buyer wants to add scope to the current statement of work and also wants to change the contract to a Fixed Price one. You have all of the following options available EXCEPT:?

Selecione uma das seguintes:

  • a. Since the buyer wants a fixed prices contract, negotiate one that includes all the work that is still to be performed.

  • b. Negotiate a new Fixed Price contract for the additional scope but stay on cost reimbursable for the original statement of work

  • c. Negotiate with buyer to restart the whole Project with a fixed Price contract so that a dispute can be avoided.

  • d. Refuse to do the additional work but complete the original work under the cost reimbursable contract.

Explicação

Questão 123 de 150

1

Which of the following is an input to Manage Project Team?

Selecione uma das seguintes:

  • a. Work performance reports

  • b. Work performance information

  • c. Work performance data

  • d. Work performance standards

Explicação

Questão 124 de 150

1

A variance threshold for costs or other indicators to indicate the agreed amount of variation allowed is called:

Selecione uma das seguintes:

  • a. Variance limits

  • b. Control threshold

  • c. Cost limit

  • d. Acceptable Threshold

Explicação

Questão 125 de 150

1

The information of the project management plan used to control scope is all of follow, except:

Selecione uma das seguintes:

  • a. Change management plan

  • b. Expert judgement.

  • c. Configuration management plan.

  • d. Requirements management plan.

Explicação

Questão 126 de 150

1

Your project is mid-way through a delivery schedule. As project manager, you want to understand how much work is left. Which is the most accurate way to determine the remaining work to be done by the project team?

Selecione uma das seguintes:

  • a. Rolling wave method

  • b. Earned Value Analysis

  • c. A manual forecast

  • d. Future analysis

Explicação

Questão 127 de 150

1

An automotive designer uses a certain technique to determine which combination of suspension and tires will produce the most desirable ride characteristics at a reasonable cost. In order to do this, she works with a statistical framework and systematically changes all of the important parameters instead of changing the factors one at a time. This is known as:

Selecione uma das seguintes:

  • a. Design for X

  • b. Root cause analysis

  • c. Design of Quality

  • d. Design of Automobiles

Explicação

Questão 128 de 150

1

You are the project manager of a building construction project. One of the routine meetings you have is a weekly meeting with project team where each team member provides you with how much work they have completed on assigned task and what are the measurements from quality tests. What are these examples of?

Selecione uma das seguintes:

  • a. Time and cost estimating.

  • b. Earned value analysis.

  • c. Perform quality audits.

  • d. Work performance data.

Explicação

Questão 129 de 150

1

What does consultants and professionals and technical associations provide during project execution??

Selecione uma das seguintes:

  • a. Deliverable status

  • b. Work performance data

  • c. Expert judgment

  • d. Issue management procedures

Explicação

Questão 130 de 150

1

As a project manager on a software development project for a customer, you have received an advice from customer that they want deliverable-based invoices. This means you will have to track the costs by each piece of work done. The system within your organization is setup to capture costs by resources, which means the total cost of the project at a certain instance is derived from cost booked against the project of the resources. What should you do?

Selecione uma das seguintes:

  • a. Only track cost as requested by customer.

  • b. Follow internal procedures and refuse customer.

  • c. Track costs both ways to fulfill internal and external requirements.

  • d. Evaluate to find out cost of complying with customer's demand.

Explicação

Questão 131 de 150

1

Contingency Reserves are estimated costs to be used at the discretion of the project manager to deal with:?

Selecione uma das seguintes:

  • a. Inadequacies in the original estimate

  • b. Anticipated but not certain events

  • c. Unanticipated events

  • d. Anticipated and certain events

Explicação

Questão 132 de 150

1

You are in charge of a new important project with a lot of uncertainty scenarios in front. Which practice do you choose an why?

Selecione uma das seguintes:

  • a. Predictive approach.

  • b. Iterative scheduling with a backlog to define scope gradually

  • c. Leveling resources to avoid uncertainty assuring enough resources.

  • d. Standard deviation to tells your boss the state of the project.

Explicação

Questão 133 de 150

1

You were invited to a meeting by a manager. When you entered the room you saw sitting there the key user working on your Project. The manager tells you that she has discussed with the key user a change to the functionality being developed by your Project: they both agree that it should be changed from manual entry to system generated entry. He then asks you to fill out the required form and get it signed. What is going on?

Selecione uma das seguintes:

  • a. You are working as Project expediter.

  • b. The management is actively involved in the Project.

  • c. This is a good example of integrated change control.

  • d. Manager is concerned with satisfying key stakeholders.

Explicação

Questão 134 de 150

1

You have received a statement of work (SOW) from the customer. You will be using this SOW as an input when you are creating the project charter. Which of the following is NOT a reason why you received the SOW from the customer?

Selecione uma das seguintes:

  • a. It was part of the proposal.

  • b. You requested information from the customer

  • c. It was part of the contract

  • d. It was part of the scope statement

Explicação

Questão 135 de 150

1

Which information flows from Direct and Manage Project Work process to Develop Project Management Plan process??

Selecione uma das seguintes:

  • a. Work performance information

  • b. Deliverables

  • c. Project management plan updates

  • d. No such information flow occurs.

Explicação

Questão 136 de 150

1

What is the purpose of reviewing a defect repair Which of the following BEST describes defect repair review?

Selecione uma das seguintes:

  • a. To ensure the defect was repaired properly and as required.

  • b. To ensure stakeholders are satisfied with the repair.

  • c. To create a Pareto chart to see the major reason for defect

  • d. To verify the extent of the repair as per scope defined in the Project Charter.

Explicação

Questão 137 de 150

1

What is the impact of noise on communication??

Selecione uma das seguintes:

  • a. Noise changes the message while being delivered.

  • b. Noise interferes with the understandings of the message by the receiver.

  • c. Noise impacts only if it is persistent.

  • d. Noise makes it hard to hear the communication since it is too loud.

Explicação

Questão 138 de 150

1

In order to calculate the Estimate To Complete (ETC), the following is typically needed:?

Selecione uma das seguintes:

  • a. Cost Performance Index (CPI) and the Actual Cost (AC).

  • b. Actual Cost (AC) and Estimate At Complete (EAC)

  • c. Earned Value (EV) and the Actual Cost (AC).

  • d. Cost Performance Index (CPI), actual cost (AC), and the Earned Value (EV).

Explicação

Questão 139 de 150

1

Which of the following is INCORRECT about conflicts??

Selecione uma das seguintes:

  • a. Conflicts should be resolved publicly to avoid any misunderstanding.

  • b. Conflicts happen all the time.

  • c. Most conflicts can be resolved using a collaborated approach

  • d. Conflicts should be attended when the project is beginning

Explicação

Questão 140 de 150

1

Which of the following is the BEST example of the use of coercive power by the Project manager?

Selecione uma das seguintes:

  • a. Project manager ask a resource Ò Come on. You know you owe me. Get me the report tomorrowÓ.

  • b. Project manager talking to a resource ñI want you to complete this report by end of tomorrowî

  • c. Project manager say to a resource ÒIf I do not get de document from you within two days, I will speak with your managerÓ.

  • d. Project manager asks a resource ÒShould I meet in person or just send her an email. Which is the right approach?Ó

Explicação

Questão 141 de 150

1

Which of the following in the project manager always responsible for??

Selecione uma das seguintes:

  • a. Meeting the project’s profit margin.

  • b. Prioritizing projects based on business need.

  • c. Writing performance reports for Project resources.

  • d. Selecting appropriate processes for the project.

Explicação

Questão 142 de 150

1

The agreement could be:

Selecione uma das seguintes:

  • a. A bill of materials

  • b. A contract, an SLA or a purchase order

  • c. A purchase policy

  • d. The most competitive cost estimate

Explicação

Questão 143 de 150

1

A project manager does not have much time to spend planning before the mandatory start date arrives. He therefore wants to move through planning as effectively as possible. Which of the following would you recommend?

Selecione uma das seguintes:

  • a. Make sure you have a signed project charter and then start scheduling and budgeting

  • b. Create a WBS and activity list then a network diagram and Gantt chart

  • c. Document all the known risks before you document the high level assumptions

  • d. Finalize the quality management plan before you determine quality metrics

Explicação

Questão 144 de 150

1

The project team has decided to perform an intentional activity that realigns the performance of the project work with the plan. The team is doing:

Selecione uma das seguintes:

  • a. A requirement of the project success.

  • b. A corrective action.

  • c. A preventive action

  • d. They are referring to an activity that can help improve performance back to the desired state.

Explicação

Questão 145 de 150

1

You are managing a gas pipeline river crossing project. The project involves drilling piles in the river bed to build a bridge to cross the gas pipeline over the river. The biggest risk you have identified and planned a response for was the delay in shipping and import of steel piles from abroad. There were two shipments planned a few months apart. First shipment was received at the docks on time. Three large trailers took off from the docks to the site, carrying enough piles for three weeks of work. It will take them one week to reach the site from the docs. All the teams and installation equipment was ready on south bank of the river on the day the shipment was to arrive. The shipment reached the site on time but on the north side of the river. It would take a whole week to bring it to south side as the bridge, which can accommodate the large trailers, was very far from the site. No one in the project time had imagined this as a risk. What do you think will be the BEST way to handle this situation?

Selecione uma das seguintes:

  • a. Add this to risk register, analyze and develop risk response, then communicate to make sure no more trailers get sent to he north side.

  • b. This should be handled as an issue and not as a risk.

  • c. Evaluate impact on this issue on project performance baselines.

  • d. Analyze this risk and use contingency reserve, which is for unplanned risks.

Explicação

Questão 146 de 150

1

An organization is highly reputed for deliverables quality. What would be an appropriate statement that BEST represent this situation?

Selecione uma das seguintes:

  • a. The organization has a low cost of quality.

  • b. Organization uses a standard quality management plan for all projects.

  • c. Organization’s Project schedules are highly robust.

  • d. The organization has a high cost of quality.

Explicação

Questão 147 de 150

1

A Project life cycle in which phases intentionally repeat one or more project activities to develop the product through a series of repeated cycles, adding functionality to product.

Selecione uma das seguintes:

  • a. Predictive life cycle.

  • b. Risk life cycle.

  • c. Iterative and incremental life cycle.

  • d. Adaptive life cycle.

Explicação

Questão 148 de 150

1

You are iniciating a new project and you and your team are in the middle of a meeting trying to identify the key stakeholders. Which documents are the better sources for do that:

Selecione uma das seguintes:

  • a. Business case and Benefit Management Plan

  • b. Project Charter

  • c. Issue log

  • d. Resource Breakdown Structure

Explicação

Questão 149 de 150

1

A project was terminated in the middle of execution when half of the deliverables have already been completed. If you are the project manager of this project, what will you do??

Selecione uma das seguintes:

  • a. Discuss with the sponsor of what can be done to keep the project running.

  • b. Perform scope validation of the completed deliverables.

  • c. Stop the work immediately and release project resources.

  • d. Send a detailed project status report to the sponsor on how well the project was doing.

Explicação

Questão 150 de 150

1

You have a seller working on a Time and Material contract. As per contract, two resources will work for 12 months on the project for a total cost of $180,000. However, the project took longer than expected and by the time it was completed, the two resources have been on the project for 18 months with a total cost of $250,000. What went wrong??

Selecione uma das seguintes:

  • a. Just like an initiative for finishing earlier, a penalty should have been proposed for delay

  • b. A maximum amount and time limit should have been established under the contract.

  • c. Fixed price contract, which is good for these kind of situations, should have been used.

  • d. Nothing went wrong since this was Time and Material contract under which resources charged for the time they worked on the project.

Explicação