List the set of tasks which if completed will get the project exactly 75% complete?
Task N 10 hours, Task O 5 hours, Task P 7 hours, Task Q 4 hours, Task R 20 hours,
Task S 12 hours, Task T 19 hours, Task U 15 hours, Task V 8 hours.