A law firm would like to extensively renovate their existing office building, excluding the copy/print area, kitchen/cafeteria, and mechanical rooms. The client wants the effects of the renovation work to be minimized on their day-to-day activities, so the architect and the client decide to do the work in four phases.
• Restroom-1 must be renovated before the renovation of the Open Office Area.
• Conference Rooms must be renovated after the renovation of the Open Office Area.
• Conference Rooms must be renovated before the renovation of Offices 1,2,3 &4.
• Restroom 1 and 2 can not be renovated at the same time.
• Restroom-2 and Conference Rooms must be renovated at the same time.
• Restroom-1 & Lobby/Entry must be renovated at the same.