schiggy98
Quiz por , criado more than 1 year ago

Quiz sobre quiz 12, criado por schiggy98 em 26-01-2016.

111
0
0
Sem etiquetas
schiggy98
Criado por schiggy98 mais de 8 anos atrás
Fechar

quiz 12

Questão 1 de 20

1

The three types of project control processes are:

Selecione uma das seguintes:

  • Easily understood because they have stayed the same for many years

  • Easily understood by all levels in the project team.

  • Cybernetic, go/no-go, and postcontrol

  • Not well-understood.

Explicação

Questão 2 de 20

1

The project manager’s primary function includes managing human resources and:

Selecione uma das seguintes:

  • Following orders from top management.

  • Project Management software.

  • Guarding physical and financial assets of the company

  • Charting and graphing project task completion.

Explicação

Questão 3 de 20

1

Because project milestones may not occur at periodic intervals, go/no-go controls
should be linked to the __________; not simply to the calendar.

Selecione uma das seguintes:

  • corporate budgeting process

  • actual plans and to the occurrence of real events

  • capital budgeting process

  • portfolio management review process

Explicação

Questão 4 de 20

1

Go/no-go controls operate __________.

Selecione uma das seguintes:

  • only at phase gate reviews

  • only when exceptions are detected

  • only when and if the controller uses them

  • continuously

Explicação

Questão 5 de 20

1

Identify the item that is NOT one of the three types of control processes described by
the authors.

Selecione uma das seguintes:

  • cybernetic control

  • robotic control

  • postcontrol

  • go/no-go control

Explicação

Questão 6 de 20

1

In order to control creative projects the project manager must adopt one or some
combination of three general approaches to the problem. Which of the following is NOT
one of these approaches?

Selecione uma das seguintes:

  • creativity check

  • personnel reassignments

  • process review

  • control of input resources

Explicação

Questão 7 de 20

1

Control is focused on three elements of a project. They are __________.

Selecione uma das seguintes:

  • scope, quality, and customer satisfaction

  • scope, cost, and time

  • cost, time, and customer satisfaction

  • performance, delivery, and cost

Explicação

Questão 8 de 20

1

The two fundamental objectives of control are the regulation of results and the
__________.

Selecione uma das seguintes:

  • refurbishing of organizational assets

  • distribution of organizational assets

  • procurement of organizational assets

  • stewardship of organizational assets

Explicação

Questão 9 de 20

1

An automatic control system containing a negative feedback loop is referred to as

Selecione uma das seguintes:

  • cybernetic

  • postcontrol

  • go/no-go

  • critical ratio

Explicação

Questão 10 de 20

1

Cybernetic control is reported to be the most common type of control system, and
consists of:

Selecione uma das seguintes:

  • Upper management weekly approvals

  • Automated reports to top management when the project goes out of control

  • An automatic adjustment of processes when deviations are detected

  • Cybernetic loops of feedback to the PM.

Explicação

Questão 11 de 20

1

Project control systems are very valuable to successful projects, and the typical cost of
the control systems is in the range of _________ percent of total project cost.

Selecione uma das seguintes:

  • 10 to 15%

  • 5 to 10%

  • 15-20%

  • 1 – 5%

Explicação

Questão 12 de 20

1

Cybernetic control systems are:

Selecione uma das seguintes:

  • Positive feedback loops

  • Negative feedback loops

  • Very difficult to implement

  • Relatively expensive and difficult to use.

Explicação

Questão 13 de 20

1

The stewardship of human resources requires __________ the growth and
development of people.

Selecione uma das seguintes:

  • mandating

  • controlling and maintaining

  • demolition

  • flattening

Explicação

Questão 14 de 20

1

When a client wants to increase the scope or functionality of a project, what should the
project design engineer reply?

Selecione uma das seguintes:

  • Of course it’s OK. The client is always right.

  • Upper management will decide.

  • We can probably do that for you, and I can prepare a new schedule and cost
    analysis to fit your new plan/goals.

  • OK and it will not cost you any more.

Explicação

Questão 15 de 20

1

The most common reason for scope creep is:

Selecione uma das seguintes:

  • Natural tendency of the client and project team to try to improve the original plan.

  • Engineering’s natural tendency to be perfectionists

  • Client’s unrealistic expectations for the design

  • Errors and omissions in the original project design

Explicação

Questão 16 de 20

1

Project Management control of physical assets includes

Selecione uma das seguintes:

  • Scheduling of maintenance and repair of all project equipment

  • PMs do not control physical assets, they schedule work.

  • Scheduling of maintenance, repair, and/or replacement of project equipment

  • Planning, scheduling, and graphing of project tasks & equipment

Explicação

Questão 17 de 20

1

Control systems commonly become out of balance because of:

Selecione uma das seguintes:

  • Too many project managers

  • Too few workers

  • Putting too much weight on easy-to-measure factors

  • Overemphasizing the seriousness of cost overruns

Explicação

Questão 18 de 20

1

In a cybernetic control system using a negative feedback loop, the speed or force with
which the control operates is, in general, __________ to the size of the deviation from
standard

Selecione uma das seguintes:

  • double

  • customary

  • reciprocal

  • proportional

Explicação

Questão 19 de 20

1

In order to gain user acceptance, the control system should appear to be __________.

Selecione uma das seguintes:

  • sensible

  • firm

  • enforced with sanctions

  • lenient

Explicação

Questão 20 de 20

1

When performing control, project managers need to be attentive to __________.

Selecione uma das seguintes:

  • avoiding directive behaviors

  • regulation and conservation equally

  • regulation more than conservation

  • maintaining laissez faire leadership

Explicação