3.9 Boiler procedures

Questão 1 de 10

1

In order to avoid scale formation and corrosion in the _____, the make up water for the feedwater supply must be properly treated

Selecione uma das seguintes:

  • dearator

  • boiler

  • furnace

  • tank

Explicação

Questão 2 de 10

1

When examining the waterside surfaces, the inspector looks for signs of corrosion, pitting and ________ of the metal.

Selecione uma das seguintes:

  • bulging

  • blistering

  • cracking

  • wearing

Explicação

Questão 3 de 10

1

During the high-pressure flush, the blowdown valves should be disconnected, if possible, to prevent them from getting plugged with _________

Selecione uma das seguintes:

  • water

  • dirt

  • rust

  • scale

Explicação

Questão 4 de 10

1

Moisture absorbing material should be placed on trays inside the drums to absorb moisture from the ________

Selecione uma das seguintes:

  • metal

  • tubes

  • air

  • fuel

Explicação

Questão 5 de 10

1

Inert gas, such as nitrogen, is connected to the drum vent to maintain approximately ______ kpa, positive pressure.

Selecione uma das seguintes:

  • 100

  • 35

  • 325

  • 500

Explicação

Questão 6 de 10

1

When the pressure in the boiler steam drum drops to ______kPa, the drum vents are to be opened to avoid the formation of a vacuum within the boiler.

Selecione uma das seguintes:

  • 170

  • 500

  • 35

  • 1000

Explicação

Questão 7 de 10

1

Which of the following is not a common cause of furnace explosions

Selecione uma das seguintes:

  • failure to purge the furnace adequately before start-up

  • admission of fuel to main burner before pilot flame or other ignition source is established.

  • Loss of id fan

  • attempting to light one burner off other burners, in operation

  • incorrect amount of air supplied to the burner can resulting in incomplete combustion

Explicação

Questão 8 de 10

1

The operator must be familiar with manual operation of the ______system, in case of a system failure

Selecione uma das seguintes:

  • generator

  • water

  • control

  • air

Explicação

Questão 9 de 10

1

___________ storage is preferable for boilers that are out of service for an extended period of time or in locations where freezing temperatures.

Selecione uma das seguintes:

  • Dry

  • Short

  • Wet

  • Long

Explicação

Questão 10 de 10

1

In order for the gauge glass to show the correct level, all connections to the gauge glass and the water column, must be ______ to ensure they are clear and free from obstructions.

Selecione uma das seguintes:

  • tight

  • purged

  • blowndown

  • unblocked

Explicação