You are the project manager responsible for your company's most expensive R&D project. The current SPI for your project is 1.06, and the current CPI for your project is 1.05. Your boss enters your office and informs you that the executive governance committee has decided to terminate your project due to recent market changes. You are surprised, but understand the importance of the business decision. During this conversation, your boss requests that you to set up a meeting with your contracted vendor to agree upon and document all of the work that has been completed up to this point. Your boss has just asked you to conduct _______________.
A Validate Scope.
B Define Scope.
C Conflict resolution.
D Contract administration.
Explanation:
The scope has already been defined, so Choice B is not correct. Choice C is not the best option since no conflict is suggested in the question. Choice D, contract administration, is not a PMBOK® process. If the project is terminated early, the Validate Scope process should be used to determine accepted deliverables and make updates to project documents. Choice A is the correct answer. PMBOK® 5.5, pgs 133-134
Selecione uma das seguintes: