ASAP 8 Methodology Technical Solution Management Work Stream Quiz

Questão 1 de 5

1

The SAP Going Live Check is split into two sections: Analysis and Verification. What are the recommendations regarding delivery of these sessions?

(More than one answer is correct. Please choose the correct answers.)

Selecione uma ou mais das seguintes:

  • All sessions should be delivered before the project go-live.

  • All sessions should be delivered after the project go-live.

  • Going Live Analysis is conducted at minimum four weeks before the project go-live, during the realisation phase.

  • Going Live Verification is scheduled after the start of production, during the Go Live Support phase.

  • All sessions are delivered by certified consultants from SAP Active Global Support through a remote connection.

Explicação

Questão 2 de 5

1

Which are the deliverables of the Technical Solution Management work stream in the Realisation phase?

Selecione uma ou mais das seguintes:

  • Define General Settings and Master Data.

  • Quality Assurance Environment (QAS).

  • Technical Solution Design.

  • Technical Operations and Handover Plan.

  • SAP Going Live Check,

Explicação

Questão 3 de 5

1

What is the purpose of the Technical Solution Management work stream in the project preparation phase?

(One answer)

Selecione uma ou mais das seguintes:

  • To define General Settings and Master Data for the project.

  • To deliver QA and Production environments and finalize the development of the operations handbook.

  • To define and develop the Organisational and Production Support Readiness Check

  • To start preparation of essential technical and infrastructure deliverables that support the initial project planning of an SAP implementation project.

  • To prepare a strategy to hand off operations of the solution landscape to the post-production support organisation.

Explicação

Questão 4 de 5

1

Which are the tasks of the deliverable 'Development Environment (DEV)' in the Blueprint phase?

(More than one answer is correct. Please choose the correct answers.)

Selecione uma ou mais das seguintes:

  • Execute Technical Installation of SAP Products for DEV

  • Create master data in DEV environment - Master Data #1 - n

  • Conduct Design Review Service

  • Perform Manual Configuration in DEV

  • Import Configuration and Development Objects to QAS

Explicação

Questão 5 de 5

1

Which transaction code in SAP Solution Manager is used to set up project documentation standards?

(One answer)

Selecione uma ou mais das seguintes:

  • SOLAR01

  • RMMAIN

  • SOLAR02

  • SOLAR_PROJECT_ADMIN

  • SOLAR_LEARNING_MAP

Explicação