Gomez, Inc. began work in 2014 on contract #3814, which provided for a contract price of $14,400,000. Other details follow:
2014 2015
Costs incurred during the year $2,400,000 $7,350,000
Estimated costs to complete, as of December 31 7,200,000 0
Billings during the year 2,700,000 10,800,000
Collections during the year 1,800,000 11,700,000
Assume that Gomez uses the percentage-of-completion method of accounting. The portion of the total gross profit to be recognized as income in 2014 is