Chapters 5-9 T/F

Questão 1 de 50

1

Scope management is the function controlling a project in terms of its goals and objectives during the execution phase.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 2 de 50

1

The statement of work is a detailed narrative description of the work required for a project.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 3 de 50

1

A comprehensive statement of work includes an estimate of time and costs, resource requirements, and the scope of the work to be performed.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 4 de 50

1

Until a project has gone through work breakdown structure, it is impossible to determine the relationships among the constituent activities.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 5 de 50

1

The scope baseline is a document that provides a summary description of each reporting relationship along with a schedule for meetings and reports.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 6 de 50

1

A work package may be composed of one or more subdeliverables.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 7 de 50

1

A work package may consist of more than one milestone.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 8 de 50

1

Work authorization functions as the formal "It's OK to begin work," on the project.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 9 de 50

1

The terms lump-sum contract and turnkey contract are interchangeable.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 10 de 50

1

A lump-sum contract requires the customer to pay for the full delivered price of the project before any work is done.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 11 de 50

1

Team building and conflict management skills are two of the most important people skills that project managers can cultivate.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 12 de 50

1

The first step in assembling a project team is to talk to potential team members.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 13 de 50

1

If preferred project team members are not available, the project manager should notify top management of the consequences.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 14 de 50

1

Project managers are best able to promote a sense of enthusiasm within the project team when they create an environment that is challenging, supportive, and personally rewarding.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 15 de 50

1

High turnover among project team members is a key element of success since new team members will bring fresh perspectives and ideas to the group.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 16 de 50

1

Project team productivity is at its peak during the norming phase of group development.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 17 de 50

1

The punctuated equilibrium model suggests that groups spend the majority of their time in stasis.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 18 de 50

1

Cross-functional cooperation directly influences both the actual implementation of the project and the team members' assessment that the project experience was worthwhile.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 19 de 50

1

In general, a superordinate goal is a replacement goal for the goals of all functional groups involved in the project.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 20 de 50

1

Accessibility is the perception of the project team members that they are physically located in such a way that it is easy for them to interact.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 21 de 50

1

The risk is highest in the earliest phase of the project life cycle.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 22 de 50

1

Opportunity emerges from favorable project circumstances and risk from unfavorable events.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 23 de 50

1

As risk decreases in the project life cycle, opportunity increases

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 24 de 50

1

Risks can be quantified by multiplying the likelihood a failure will occur by the severity of the failure.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 25 de 50

1

Technical risk is the probability that the project will not perform to the required standards or produce substandard products or have excessive operating cost consumption.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 26 de 50

1

The probability that the investments made to fund the front-end activities will be lost due to project abandonment is financing risk.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 27 de 50

1

One approach to risk mitigation is simply to accept it.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 28 de 50

1

Risk cannot be transferred because ultimately your own project will suffer the consequences if the event occurs.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 29 de 50

1

Contingency reserves require a construction company to hold back some funds in an account just in case something happens that increases the overall project cost.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 30 de 50

1

The highest dollar value of reserves is typically task contingency.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 31 de 50

1

Direct costs are those clearly assigned to the aspect of the project that generated the cost.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 32 de 50

1

Material is an example of a cost that is recurring, variable and direct.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 33 de 50

1

An expedited cost is one that does not vary with respect to their usage.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 34 de 50

1

The term expedited cost has the same meaning as crashing cost in the project management milieu.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 35 de 50

1

An order of magnitude estimate is usually more accurate than a ballpark estimate.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 36 de 50

1

Comparative estimates are more accurate than definitive estimates when applied to the same project.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 37 de 50

1

A learning rate of 90% means that for every doubling of output, the time required by the activity falls by 10%.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 38 de 50

1

Function point analysis is a system for estimating the size of software projects based on the number of lines of code a typical programmer can write in a day.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 39 de 50

1

A common reason for cost overruns in a project is a low initial estimate of project cost.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 40 de 50

1

There is a tendency for different departments or functions to compete for scarce resources in a zero-sum game when bottom-up budgeting is used to develop a project budget.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 41 de 50

1

Preceding activities are those that must occur before others can be done.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 42 de 50

1

A backward pass is performed when it is necessary to undo some work that has been performed in order to complete it properly.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 43 de 50

1

A merge activity has two or more immediate predecessors.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 44 de 50

1

Float is always measured in exactly the same way as slack.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 45 de 50

1

The PERT technique assumes that durations are more deterministic.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 46 de 50

1

Burst activities are those with two or more successor activities.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 47 de 50

1

You must know the mean of an activity in order to determine its standard deviation.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 48 de 50

1

In assigning a value for the most pessimistic (b) duration, the project manager should estimate the duration of the activity to have a 99% likelihood that it will take b or less amount of time.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação

Questão 49 de 50

1

The late start time should be calculated using a forward pass through the network.

Selecione uma das seguintes:

  • T/F

  • Answer: FALSE

Explicação

Questão 50 de 50

1

Negative float exists when a project's critical path has been completed more quickly than anticipated.

Selecione uma das seguintes:

  • T/F

  • Answer: TRUE

Explicação