DGPO04 Stakeholders

Questão 1 de 20

1

The stakeholder register contains details related to the identified stakeholders including all of the following EXCEPT:

Selecione uma das seguintes:

  • A Stakeholder location.

  • B Phase in the life cycle with the most interest.

  • C Classifications such as resister.

  • D Contract negotiations.

Explicação

Questão 2 de 20

1

Your communications management plan assumed that all of your stakeholders would read their email to receive important project information. Since then, you have learned that executives' email is often read by their assistants. As a result, you changed your communications management plan to communicate important information in briefing meetings. Where else would you document the knowledge you gained?

Selecione uma das seguintes:

  • A Project charter

  • B Communications management plan

  • C Organizational process assets

  • D Enterprise environmental factors

Explicação

Questão 3 de 20

1

Inputs to the Identify Stakeholders process include:

Selecione uma das seguintes:

  • A Procurement documents

  • B Work performance data

  • C Project management plan

  • D Issue log

Explicação

Questão 4 de 20

1

The information from the project management plan that is used to control stakeholder engagement includes all of the following EXCEPT:

Selecione uma das seguintes:

  • A Addressing potential concerns that have not yet become issues need to be identified and discussed with stakeholders as soon as possible to assess associated project risks.

  • B How human resources requirements will be met, how roles and responsibilities, reporting relationships, and staffing management will be addressed and structured for the project.

  • C A change management plan that documents how changes will be monitored and controlled.

  • D How work will be executed to accomplish the project objectives.

Explicação

Questão 5 de 20

1

__________ includes managing communications to satisfy the needs of, and resolve issues with, project stakeholders.

Selecione uma das seguintes:

  • A Manage Communications

  • B Plan Communications Management

  • C Manage Stakeholder Engagement

  • D Control Communications

Explicação

Questão 6 de 20

1

General management skills related to harmonizing the group include __________.

Selecione uma das seguintes:

  • A Reporting on the work the team is doing and focusing on rewards and recognition

  • B Facilitating consensus, influencing people, negotiating agreements, modifying organizational behavior

  • C Documenting project status

  • D Tracking project progress

Explicação

Questão 7 de 20

1

Project documents that will likely be updated during stakeholder planning include the:

Selecione uma das seguintes:

  • A Schedule baseline and process improvement plan.

  • B Stakeholder management plan and change management plan.

  • C Change management plan.

  • D Project schedule and stakeholder register.

Explicação

Questão 8 de 20

1

All of the following are outputs of the Control Stakeholder Engagement process EXCEPT:

Selecione uma das seguintes:

  • A Work performance information.

  • B Change requests.

  • C Project management plan updates.

  • D Stakeholder register.

Explicação

Questão 9 de 20

1

As the consultant for the ACME Bicycle Corporation, one of your responsibilities is to capture, store, and distribute information to stakeholders about the project cost, schedule progress, and performance. You want to be certain to meet the terms of your contract, so what tool will you use to assist you with this responsibility?

Selecione uma das seguintes:

  • A A integrated change control system

  • B A contract change control system

  • C An information management system

  • D A weighting system

Explicação

Questão 10 de 20

1

Which of the following is an input to the Manage Stakeholder Engagement process?

Selecione uma das seguintes:

  • A Change log

  • B Project documents updates

  • C Change requests

  • D Organizational process assets updates

Explicação

Questão 11 de 20

1

Classification models used with the Identify Stakeholder analysis include all the following EXCEPT:

Selecione uma das seguintes:

  • A Salience model.

  • B Influence/impact grid.

  • C Influence/expectations grid.

  • D Power/influence grid.

Explicação

Questão 12 de 20

1

Jamie is a member of a project management team for a very large multinational development project. He is responsible for the Manage Stakeholder Engagement process for the project. Jamie will produce all of the following EXCEPT:

Selecione uma das seguintes:

  • A Change requests.

  • B Enterprise environmental factors.

  • C Organizational process assets updates.

  • D Project management plan updates.

Explicação

Questão 13 de 20

1

Which of the following enterprise environmental factors should Sam focus on when planning stakeholder management?

Selecione uma das seguintes:

  • A Organizational culture

  • B Local politics

  • C Relationships

  • D Interpersonal skills

Explicação

Questão 14 de 20

1

There are 23 communication channels in your project. You know how critical it is to engage stakeholders during the whole project and how important it is to understand engagement levels. Which of the following is NOT considered an engagement level classification?

Selecione uma das seguintes:

  • A Leading

  • B Unaware

  • C Clueless

  • D Resistant

Explicação

Questão 15 de 20

1

Which of the following is NOT a Manage Stakeholder Engagement benefit?

Selecione uma das seguintes:

  • A Increases the likelihood of project acceptance

  • B Addresses concerns that have not become issues

  • C Clarifies and resolves issues that have been identified

  • D Maximizes stakeholder change requests

Explicação

Questão 16 de 20

1

A grouping of stakeholders based on their level of authority and their active involvement is an example of a/an:

Selecione uma das seguintes:

  • A Power/interest grid.

  • B Power/influence grid.

  • C Influence/impact grid.

  • D Salience model.

Explicação

Questão 17 de 20

1

All of the following are inputs to the Identify Stakeholders process EXCEPT:
.

Selecione uma das seguintes:

  • A Stakeholder management plan.

  • B Enterprise environmental factors.

  • C Procurement documents

  • D Project charter.

Explicação

Questão 18 de 20

1

You are overwhelmed with all the organization process assets to consider when planning stakeholder management. You decide to start with the most powerful one. Which asset will you be focusing on?

Selecione uma das seguintes:

  • A Lessons learned

  • B Processes

  • C Policies

  • D Governing documents

Explicação

Questão 19 de 20

1

The Plan Stakeholder Management process is important because:

Selecione uma das seguintes:

  • A It helps effectively engage stakeholders throughout the project.

  • B PMBOK® requires it.

  • C It is a component of the project management plan.

  • D The stakeholders asked for it.

Explicação

Questão 20 de 20

1

The project stakeholder is:

Selecione uma das seguintes:

  • A The person or group of people assisting with matters such as project funding and clarifying scope questions.

  • B The person or group of people responsible for the project management activities.

  • C The person or group of people responsible for writing the project charter.

  • D The person or group of people actively involved in the project, or whose interests may be impacted by the project.

Explicação