Tiffany Brown
Quiz por , criado more than 1 year ago

Kaplan Study Guide

11
1
0
Tiffany Brown
Criado por Tiffany Brown aproximadamente 8 anos atrás
Fechar

Kaplan - CDs 2009 [Cost Estimates] Chapter Quiz Questions

Questão 1 de 2

1

An architect's preliminary estimate of construction cost would consider all of the following EXCEPT:

I. labor and materials supplied by the owner.
II. cooling towers.
III. land acquisition costs.
IV. the architect's fee.
V. metal curtain wall systems

Selecione uma das seguintes:

  • A. I only

  • B. I and IV

  • C. None, everything would be considred

  • D. III and IV

Explicação

Questão 2 de 2

1

An architect who prepares a preliminary estimate of construction cost according to the subsystems method

Selecione uma das seguintes:

  • A. considers one set of subsystems for concrete buildings and a different set for steel buildings.

  • B. can easily analyse the cost of alternative exterior wall systems.

  • C. would most likely use this method during the schematic design phase.

  • D. would be performing an additional service under the AIA Agreement between Owner and Architect.

Explicação