DGAP04 100 PMP

Questão 1 de 99

1

Victor, the project manager, has several impulsive people on the project team and he knows that it will be important to establish clear expectations regarding acceptable behavior by project team members. A Develop Project Team tool or technique that he has decided to use is most likely:
A Ground rules.
B Interpersonal skills.
C Team building activities.
D Colocation.
Explanation:
Ground rules (Choice A) establish clear expectations regarding acceptable behavior by project team members. PMBOK® 9.3.2.4, pg 277

Selecione uma das seguintes:

  • A Ground rules.

  • B Interpersonal skills.

  • C Team building activities.

  • D Colocation.

Explicação

Questão 2 de 99

1

Which Project Management Process Group regularly measures progress and identifies variances from the project plan?

Selecione uma das seguintes:

  • A Planning

  • B Monitoring and Controlling

  • C Initiating

  • D Executing

Explicação

Questão 3 de 99

1

Lisa is the project manager for a new clothing line project. She has just learned that the workers at the sewing company her company usually contracts with have just gone on strike. She knows that, as a result, the only available sewing resources with another sewing company are extremely limited. Thankfully, Lisa and her manager have just decided to purchase a new project management software tool that will enable Lisa to manage her project with the latest technology. Lisa and her team should:

Selecione uma das seguintes:

  • A Hire a consultant.

  • B Increase the duration of the project by 15% to account for the limited resources.

  • C Consider using the critical chain method of schedule network analysis.

  • D Fast track the project.

Explicação

Questão 4 de 99

1

Sharon, the project manager, realizes her group of stakeholders is unable, at this early stage of the project, to define the scope more precisely. She tells the group, "Let's stop for now. We can come back to this later when we know more of the details." Sharon's decision is based on what project characteristic?

Selecione uma das seguintes:

  • A Scope creep

  • B Progressive elaboration

  • C Burnout

  • D Bad project management

Explicação

Questão 5 de 99

1

John decides to raise the grade level of the product of his project. He is affecting:

Selecione uma das seguintes:

  • A The project quality.

  • B The project scope.

  • C The project benchmarks.

  • D The quality baseline.

Explicação

Questão 6 de 99

1

There is a new project at an automobile manufacturing company that requires input from many stakeholders in eight countries. Clearly, the project manager (Ananya) is going to require the support of these stakeholders. On top of that, if she doesn’t manage their expectations, the project will experience difficulties. Which of the following BEST addresses what Ananya will need to do?

Selecione uma das seguintes:

  • A Communicate with the stakeholders constantly and consistently throughout the project life cycle; update the stakeholders on the status of all project changes

  • B Minimize resistance by recognizing stakeholders at monthly meetings; provide regular project status updates

  • C Communicate through email often, record issues and manage expectations so stakeholders will not be disappointed and then disrupt the project

  • D Have the stakeholders periodically review the list of project requirements to 1) make sure their expectations are included, and 2) minimize the number of change requests

Explicação

Questão 7 de 99

1

A bar chart in which each bar represents a variable, and the height shows the frequency, is called a:

Selecione uma das seguintes:

  • A Frequency chart.

  • B Control chart.

  • C Flowchart.

  • D Histogram.

Explicação

Questão 8 de 99

1

Scott, one of your team members, needs to know when other team members will be in the office so he can schedule a meeting. What project document might help him?

Selecione uma das seguintes:

  • A Resource calendar

  • B Resource breakdown structure (RBS)

  • C Responsibility matrix

  • D Organization chart

Explicação

Questão 9 de 99

1

Which of the following is NOT an objective of the Control Risks process?

Selecione uma das seguintes:

  • A Determine if project assumptions are still valid

  • B Determine if analysis shows an assessed risk has changed or can be retired

  • C Determine if risk management policies are being followed

  • D Determine methods to eliminate all residual risks

Explicação

Questão 10 de 99

1

When Gale left the company, Anna replaced her as project manager. The project deliverables include a system to track medical paperwork through the billing process. Anna is from the information technology department and is not familiar with some of the medical terminology used by her teams. Where should she look for definitions of these terms?

Selecione uma das seguintes:

  • A Enterprise environmental factors list

  • B Project charter

  • C Project term list

  • D Communications management plan

Explicação

Questão 11 de 99

1

Which of the following statements about requested changes is true?

Selecione uma das seguintes:

  • A They are processed for review and disposition through the Perform Integrated Change Control process

  • B They are an input to the Validate Scope process

  • C They are necessary to complete Validate Scope

  • D They are rarely used because the scope on every project remains relatively constant

Explicação

Questão 12 de 99

1

Which of these statements related to the Conduct Procurements process is FALSE?

Selecione uma das seguintes:

  • A Analytical techniques can help organizations identity the readiness of a vendor to provide the desired end state.

  • B On complex procurements, where source selection will be made based on seller responses to previously defined weighted criteria, a formal evaluation review process will be defined by the buyer’s procurement policies.

  • C Advertising in trade publications is a good place to start to build a list of potential sellers.

  • D Procurement negotiations conclude with a contract document that can be executed by both buyer and seller.

Explicação

Questão 13 de 99

1

Which of the following is an input to the Direct and Manage Project Work process?

Selecione uma das seguintes:

  • A Approved change requests

  • B Project management information system

  • C Work performance information

  • D Implemented preventive actions

Explicação

Questão 14 de 99

1

A structured, independent review to determine whether project activities comply with organizational and project policies, processes and procedures is called a:

Selecione uma das seguintes:

  • A Quality audit.

  • B Management review.

  • C Process analysis.

  • D Status meeting.

Explicação

Questão 15 de 99

1

The development of requirements begins with an analysis of information contained in the:

Selecione uma das seguintes:

  • A Project charter and stakeholder register.

  • B Project management plan and requirements traceability matrix.

  • C Project charter and organizational process assets.

  • D Project management plan and change requests.

Explicação

Questão 16 de 99

1

Fran is a project manager who is validating her systems analyst's Define Scope work products. Which of the following work products should Fran expect to see?

Selecione uma das seguintes:

  • A Project constraints, project objectives, and a prioritized list of risks

  • B Project exclusions and acceptance criteria

  • C Project boundaries, a project scope description and scope baseline

  • Project scope statement, project cost requirements and a project team list

Explicação

Questão 17 de 99

1

You are ready to build a list of stakeholders for your project. Which of the following statements is FALSE?

Selecione uma das seguintes:

  • A Customers and buyers must be considered

  • B Those positively impacted by the project need little attention

  • C The state transportation department is a stakeholder for the city that is planning concrete sidewalks along a local highway

  • D The head of the PMO who is always interfering with your project work and slowing things down will be a stakeholder on your list

Explicação

Questão 18 de 99

1

By actively managing the contract and carefully wording the terms and conditions, what can be avoided?

Selecione uma das seguintes:

  • A Schedule rework

  • B Spelling errors

  • C Project risks

  • D Change requests

Explicação

Questão 19 de 99

1

In context of the Project Time Management Knowledge Area, which of the following processes would be the first to be executed?
A Estimate Activity Resources
B Sequence Activities
C Develop Schedule
D Estimate Activity Durations
Explanation:
The Sequence Activities process is the third of the seven processes that make up Project Time Management, but the first in the choices provided. PMBOK® 6, pg 143

Selecione uma das seguintes:

  • A Estimate Activity Resources

  • B Sequence Activities

  • C Develop Schedule

  • D Estimate Activity Durations

Explicação

Questão 20 de 99

1

Your team is working on a project to produce the next generation of cell phones. The marketing department contacts you to begin the advertising campaign. You know the technical risks are very high for this product. You should:

Selecione uma das seguintes:

  • A Help design the campaign.

  • B Monitor risks closely and keep marketing informed.

  • C Ask marketing to wait until the risk is at an acceptable level.

  • D Tell your sponsor.

Explicação

Questão 21 de 99

1

Estimates at completion (EAC) are typically based on an estimate to complete (ETC) the remaining work plus __________.

Selecione uma das seguintes:

  • A Earned value (EV)

  • B Planned value (PV)

  • C Actual costs (AC)

  • D Cost variance (CV)

Explicação

Questão 22 de 99

1

Decomposition is a technique used during Define Activities. It subdivides the project work packages into smaller, more manageable components called schedule __________.

Selecione uma das seguintes:

  • A Deliverables

  • B Units

  • C Activities

  • D Milestones

Explicação

Questão 23 de 99

1

A chart with points plotted for values of two potentially related variables is called a:

Selecione uma das seguintes:

  • A Scatter diagram.

  • B Control chart.

  • C Flowchart.

  • D Histogram.

Explicação

Questão 24 de 99

1

Which of the following is an example of an organizational process asset that may be an input to the project charter?

Selecione uma das seguintes:

  • A Government or industry standards

  • B Marketplace conditions

  • C Company culture and structure

  • D Templates

Explicação

Questão 25 de 99

1

A group of unrelated projects that are grouped together to facilitate effective management to meet strategic business objectives could be called a __________.

Selecione uma das seguintes:

  • A Project

  • B Portfolio

  • C Program

  • D Strategic plan

Explicação

Questão 26 de 99

1

__________ is the realized cost incurred for the work performed on an activity during a specific time period.

Selecione uma das seguintes:

  • A Planned value (PV)

  • B Actual cost (AC)

  • C Cost variance (CV)

  • D Earned value (EV)

Explicação

Questão 27 de 99

1

What process must precede Manage Communications?

Selecione uma das seguintes:

  • A Project Communications Management

  • B Control Communications

  • C Control Stakeholder Engagement

  • D Plan Communications Management

Explicação

Questão 28 de 99

1

What is the unique and verifiable product, result or capability to perform a service that is identified in planning and must be produced to complete the project work?

Selecione uma das seguintes:

  • A Project management plan

  • B Deliverable

  • C Work performance data

  • D Project charter

Explicação

Questão 29 de 99

1

Which Project Management Process Group defines and refines objectives, and plans the course of action required to attain the objectives?

Selecione uma das seguintes:

  • A Planning

  • B Closing

  • C Initiating

  • D Executing

Explicação

Questão 30 de 99

1

All of the following are inputs to the Identify Stakeholders process EXCEPT:

Selecione uma das seguintes:

  • A Stakeholder management plan.

  • B Enterprise environmental factors.

  • C Procurement documents.

  • D Project charter.

Explicação

Questão 31 de 99

1

In a virtual team environment, __________ becomes increasingly important.

Selecione uma das seguintes:

  • A Quality control

  • B Communication planning

  • C Cost planning

  • D Scope planning

Explicação

Questão 32 de 99

1

During Plan Stakeholder Management, expert judgment can be obtained through all of the following EXCEPT:

Selecione uma das seguintes:

  • A Focus groups

  • B Status meetings

  • C Surveys

  • D Individual consultations

Explicação

Questão 33 de 99

1

All of the following can be updated as a result of Control Quality EXCEPT:
.

Selecione uma das seguintes:

  • A Quality metrics.

  • B Organizational process assets.

  • C Project management plan.

  • D Project documents

Explicação

Questão 34 de 99

1

Jeanette developed the project's communications management plan as one of the first deliverables in her project. Now, six months into the project, it seems like there is a lot of confusion about who needs what information about the project. It has gotten to the point that Jeanette's new boss and her latest project sponsor act like they don't even understand the project. What do you think Jeanette could have done differently?

.

Selecione uma das seguintes:

  • A Organizational changes should have been anticipated and logged in the risk register.

  • B Jeanette should have stopped the project when the sponsor changed, in order to give the new sponsor a chance to learn about the project.

  • C The communications management plan should have been reviewed regularly throughout the project and revised as needed to ensure it is still useful

  • D Jeanette should have re-planned the project.

Explicação

Questão 35 de 99

1

Triangular distribution and beta distribution are two formulas used with :

Selecione uma das seguintes:

  • A Parametric estimating.

  • B Analogous estimating.

  • C Three-point estimates.

  • D Bottom-up estimating.

Explicação

Questão 36 de 99

1

As the project manager of one of your team members, you inadvertently overhear a discussion in the lunch room between her and her boss. They are having a discussion about your team member's performance. You are shocked to hear that the manager suggests to her that her performance assessment would improve if she would consider updating her wardrobe to more trendy, snugger fitting clothes. What should you do?

Selecione uma das seguintes:

  • A You should do nothing. He was probably joking and didn't really mean it.

  • B You should call the manager afterwards to express your disappointment in his behavior.

  • C You should immediately report the incident to a human resources representative and to the manager's manager.

  • D You should pretend you didn't hear the conversation, as you were not supposed to overhear that discussion.

Explicação

Questão 37 de 99

1

Most often, a format to document team member roles and responsibilities falls into these types EXCEPT:

Selecione uma das seguintes:

  • A Text-oriented.

  • B Matrix.

  • C Hierarchical.

  • D Three dimensional.

Explicação

Questão 38 de 99

1

An __________ is the expected total cost of completing all work expressed as the sum of the actual cost to date and the estimate to complete.

Selecione uma das seguintes:

  • A Estimate at completion (EAC)

  • B Estimate to complete (ETC)

  • C Actual cost (AC)

  • D Earned value (EV)

Explicação

Questão 39 de 99

1

Sanjay, the project manager for a new "green" product development effort, is unable to complete a detailed decomposition since a major product component will not be fully designed for another year. Given this, he decides it is best to use:

Selecione uma das seguintes:

  • A Critical path method.

  • B Contingency planning.

  • C Rolling wave planning.

  • D Idea/Mind mapping.

Explicação

Questão 40 de 99

1

All of the following are processes involved in Project Time Management EXCEPT:

Selecione uma das seguintes:

  • A Define Activities.

  • B Control Schedule.

  • C Create WBS.

  • D Estimate Activity Durations.

Explicação

Questão 41 de 99

1

One of your fellow project managers won a trip around the world. You agreed to move her project forward while she was gone. Her notes direct you to start assembling the team for a Define Activities session. In an email to the team, you describe the meeting as:

Selecione uma das seguintes:

  • A Identifying the specific actions to be performed to produce the project deliverables.

  • B Identifying all of the deliverables required to complete the project.

  • C Identifying and documenting dependencies among schedule activities.

  • D Estimating the number of work periods that will be needed to complete the individual schedule activities.

Explicação

Questão 42 de 99

1

An intentional activity to modify a nonconforming product or product component is the definition for which output of the Direct and Manage Project Work process?

Selecione uma das seguintes:

  • A Implemented change requests

  • B implemented preventive actions

  • C Change requests covering defect repair

  • D Implemented corrective actions

Explicação

Questão 43 de 99

1

A project team is beginning to identify risks for the project. The customer declines the invitation to the risk identification session. He says talking about risk is planning to fail. The project manager should:

Selecione uma das seguintes:

  • A Start execution.

  • B Abandon the project.

  • C Inform senior management.

  • D Discuss the value of risk management with the customer.

Explicação

Questão 44 de 99

1

__________ includes managing communications to satisfy the needs of, and resolve issues with, project stakeholders.

Selecione uma das seguintes:

  • A Manage Communications

  • B Plan Communications Management

  • C Manage Stakeholder Engagement

  • D Control Communications

Explicação

Questão 45 de 99

1

Which of the following is an input to Develop Schedule?

Selecione uma das seguintes:

  • A Project schedule

  • B Schedule baseline

  • C Project management plan updates

  • D Project scope statement

Explicação

Questão 46 de 99

1

During a bidder conference, the project manager's role is:

.

Selecione uma das seguintes:

  • A To answer questions.

  • B To select a seller.

  • C To be the good guy.

  • D To establish requirement priorities

Explicação

Questão 47 de 99

1

Which of the following enterprise environmental factors should Sam focus on when planning stakeholder management?

Selecione uma das seguintes:

  • A Organizational culture

  • B Local politics

  • C Relationships

  • D Interpersonal skills

Explicação

Questão 48 de 99

1

__________ is the process of tracking identified risks, monitoring residual risks, identifying new risks, executing risk register plans, and evaluating their effectiveness during the project life cycle.

Selecione uma das seguintes:

  • A Plan Risk Management

  • B Control Risks

  • C Perform Quantitative Risk Analysis

  • D Identify Risks

Explicação

Questão 49 de 99

1

Question 50 of 100 (Scope) Go to Question:

An output of Collect Requirements is:

Selecione uma das seguintes:

  • A Work breakdown structure.

  • B Project management plan.

  • C Project scope statement.

  • D Requirements traceability matrix.

Explicação

Questão 50 de 99

1

The project manager's authority is moderate to high in a __________ organization.

Selecione uma das seguintes:

  • A Functional

  • B Projectized

  • C Strong matrix

  • D Balanced matrix

Explicação

Questão 51 de 99

1

All of the following are tools or techniques for Control Costs EXCEPT:

Selecione uma das seguintes:

  • A Funding limit reconciliation.

  • B To-complete performance index.

  • C Earned value management.

  • D Performance reviews.

Explicação

Questão 52 de 99

1

Stacy needs to develop a communications management plan for her project. Which of the following is a tool or technique that will help her with that task?

Selecione uma das seguintes:

  • A Communications management plan

  • B Communications requirements analysis

  • C Project scope statement

  • D Work performance reports

Explicação

Questão 53 de 99

1

The risk of failing to achieve a project's objectives is greatest __________.

Selecione uma das seguintes:

  • A At the start of the project

  • B In the middle of the project

  • C Near the end of the project

  • D After the project is completed

Explicação

Questão 54 de 99

1

Which of the following statements is TRUE?

Selecione uma das seguintes:

  • A Organizations should fund 100% of the project budget at initiation.

  • B Funding usually occurs at the end of the project.

  • C Funding usually occurs in incremental amounts during the life of the project.

  • D Management reserves are the responsibility of the project manager.

Explicação

Questão 55 de 99

1

You have 232 stakeholders on your project. You also have a lot of project information that changes on a daily basis. It just so happens that you have access to a company website. What communication method will support you the best in terms of making your information available to the masses?

Selecione uma das seguintes:

  • A Pull communication

  • B Push communication

  • C Interactive communication

  • D Open communication

Explicação

Questão 56 de 99

1

All of the following are outputs of the Control Stakeholder Engagement process EXCEPT:

Selecione uma das seguintes:

  • A Work performance information.

  • B Change requests.

  • C Project management plan updates.

  • D Stakeholder register.

Explicação

Questão 57 de 99

1

Tracking team member performance, providing feedback, resolving issues, and managing changes to optimize project performance are all a part of:

Selecione uma das seguintes:

  • A Control Quality.

  • B Develop Project Team.

  • C Acquire Project Team.

  • D Manage Project Team.

Explicação

Questão 58 de 99

1

Root cause analysis is used with:

Selecione uma das seguintes:

  • A Control charts.

  • B Quality audits.

  • C Process analysis.

  • D Botanical projects.

Explicação

Questão 59 de 99

1

Your colleague insists that working with stakeholders is easy. You have worked on many projects during your career, and know differently based on experience. One of the practices you use to help you effectively manage stakeholders is to classify them. You decide to use the salience model. Which of the answer choices lists stakeholder groupings you are likely to be using?

Selecione uma das seguintes:

  • A Power, influence

  • B Influence, impact

  • C Power, legitimacy, urgency

  • D Keep satisfied, manage closely, monitor, keep informed

Explicação

Questão 60 de 99

1

The quality management plan relates to the Plan Quality Management process in what way?

Selecione uma das seguintes:

  • A It is a tool or technique

  • B It is an output

  • C It is an input

  • D It is not part of Plan Quality Management

Explicação

Questão 61 de 99

1

When the Control Communications process identifies changes, what process will be triggered?

Selecione uma das seguintes:

  • A Plan Communications Management

  • B Perform Integrated Change Control

  • C Control Quality

  • D Project Scope Management

Explicação

Questão 62 de 99

1

Andre's project team has finished their last major deliverable and the customer has accepted it. His team consisted of five local employees and fifteen contract team members. What is the next logical process?

Selecione uma das seguintes:

  • A Control Procurements

  • B Close Procurements

  • C Conduct Procurements

  • D Close Project or Phase

Explicação

Questão 63 de 99

1

You have been assigned as the project manager for the parking lot resurfacing at a very prestigious, top quality health facility in Arizona. The project is moving along better than expected and you are feeling quite confident that you will be finished 2 days ahead of schedule. During your daily morning walk-over of the completed work, you notice that in one area, the concrete appears to be "popping" leaving what looks like little pock marks on the surface. You immediately suspect that there is a defect in the concrete that was used in that section. Which organizational process asset would you reference first to help you determine your BEST course of action?

Selecione uma das seguintes:

  • A Project files from prior projects

  • B Issue and defect management database

  • C Communication requirements

  • D Process measurement database

Explicação

Questão 64 de 99

1

The process of obtaining the human resources needed to complete the project is:
.

Selecione uma das seguintes:

  • A Plan Human Resource Management

  • B Manage Project Team.

  • C Acquire Project Team.

  • D Define Activities.

Explicação

Questão 65 de 99

1

__________ provide documentation about current project status compared to project forecasts.

Selecione uma das seguintes:

  • A Work performance reports

  • B Project organization charts

  • C Project staff assignments

  • D Individual performance assessments

Explicação

Questão 66 de 99

1

Comparing the cost of quality management activities against the cost of likely rework is called __________.

Selecione uma das seguintes:

  • A Benchmarking

  • B Design of Experiments

  • C Cost of quality (COQ)

  • D Cost-benefit analysis

Explicação

Questão 67 de 99

1

A cost management plan may contain:

Selecione uma das seguintes:

  • A Control thresholds, reporting formats, and units of measure.

  • B Level of accuracy, organizational procedure links, and cost forecasts.

  • C Rules of performance measurement, control thresholds, and reserve analysis.

  • D Units of measure, process descriptions, and activity cost estimates.

Explicação

Questão 68 de 99

1

EV/AC is the formula for:
).

Selecione uma das seguintes:

  • A Cost performance index (CPI).

  • B Schedule variance (SV).

  • C Cost variance (CV).

  • D Schedule performance index (SPI

Explicação

Questão 69 de 99

1

You are the project manager for a project that is co-developing a product with another company. You know that if you add a feature to the product of your project, the stock price of your client has a very high probability of rising. With this information, you suggest to your team to consider adding the feature. In addition, you are thinking about purchasing some of the stock. Should you buy the stock?

Selecione uma das seguintes:

  • A No, because you don't work for that company

  • B No, because buying the stock would represent a conflict of interest, and could possibly be considered Insider Trading

  • C Yes, because it is a great opportunity

  • D Yes, because no one has to know

Explicação

Questão 70 de 99

1

Jose's company has just won three contracts to install and configure its best-selling software system at three new client sites. Jose decides that he can manage the three project teams, at separate sites, concurrently. If he does, is Jose deviating from the PMBOK®?

Selecione uma das seguintes:

  • A No, because he can manage all three at once.

  • B Yes, because the endeavors are not projects since they are not unique.

  • C Yes. He is making a big mistake trying to manage three projects at once.

  • D No, because his software is best-selling, so the clients will want the systems sooner.

Explicação

Questão 71 de 99

1

Those processes required to establish the scope of the project are part of the:
.

Selecione uma das seguintes:

  • A Executing Process Group

  • B Initiating Process Group.

  • C Planning Process Group.

  • D Monitoring and Controlling Process Group.

Explicação

Questão 72 de 99

1

Chen has a set of very complex proposals to evaluate. His project needs a contracted real-time inventory management solution. What is his next BEST action?

Selecione uma das seguintes:

  • A Evaluate the proposals

  • B Award the project to the best proposal

  • C Form a multi-discipline review team

  • D Pick the lowest bid

Explicação

Questão 73 de 99

1

Work performance data is an important Control Risks input. Which of the following will you NOT find in work performance data?

Selecione uma das seguintes:

  • A Project deliverable status

  • B Costs incurred

  • C Team member performance assessments

  • D Schedule progress

Explicação

Questão 74 de 99

1

While preparing your status report, you discover that a task has an SPI value of 0.75. You realize that the task was underestimated and needs more resources. What should you prepare?

Selecione uma das seguintes:

  • A A variance analysis

  • B A change request

  • C Status update of risks and issues

  • D Forecasted completion

Explicação

Questão 75 de 99

1

Your team has planned their risk management approach, identified 50 risks and prioritized them. What is the BEST next step?

Selecione uma das seguintes:

  • A Perform qualitative analysis to rank risks

  • B Prepare risk responses

  • C Write a risk management plan

  • D Perform Quantitative Risk Analysis to determine risk impacts

Explicação

Questão 76 de 99

1

Fred has been asked by Nancy, the project's executive sponsor, to obtain the project stakeholders' formal acceptance of the completed project scope and associated deliverables. Fred has arranged a session to review which of the following with the stakeholders?

Selecione uma das seguintes:

  • A Verified deliverables

  • B Accepted deliverables

  • C Recommended corrective actions

  • D Work breakdown structure

Explicação

Questão 77 de 99

1

You have been assigned as the project manager of a project that will deliver templates and procedures for the development of a manufacturing process used by an external customer. Which of the following would be an input to developing the project charter?

Selecione uma das seguintes:

  • A Summary budget

  • B Subject matter expert

  • C Project approval requirements

  • D Contracts

Explicação

Questão 78 de 99

1

Why is it important to document requested contract changes?

Selecione uma das seguintes:

  • A To establish a record of non-compliance

  • B To maintain project records

  • C To update the contract

  • D Change requests can lead to a contract dispute

Explicação

Questão 79 de 99

1

Bill is a project manager for a construction design project. He and his team have completed the project's schedule network diagram and are currently determining which resources are needed for the project. Bill has learned that his stakeholders would like to incorporate a new material that the manufacturing department has invented for the foundation. He checks his budget and sees that he cannot afford to send any of his design team members to training or to hire an outside consultant. Bill's BEST option is to:
.

Selecione uma das seguintes:

  • A Tell the stakeholders that the new material cannot be used unless the budget is increased

  • B Identify a person from manufacturing who has knowledge about the new material, and add her to the project team.

  • C Add a 20% buffer to the schedule to account for the additional risk.

  • D Use a more inexpensive material for the windows.

Explicação

Questão 80 de 99

1

You are managing a large multinational project. Most of the team members live in a country that observes siesta in the early afternoon. That time of day equates to early morning for your time zone. When do you plan status conference calls?

Selecione uma das seguintes:

  • A Early morning, your time

  • B Early afternoon, their time

  • C Later afternoon, their time

  • D Alternate early morning your time and early afternoon their time

Explicação

Questão 81 de 99

1

What is the aspect of project management that includes collecting, measuring, and distributing performance information, and assessing measurements and trends to effect process improvements?

Selecione uma das seguintes:

  • A Performance collecting

  • B Monitoring

  • C Process assessment

  • D Project planning

Explicação

Questão 82 de 99

1

Peter has collected a list of resolved issues regarding one of the vendors. This list of resolved issues was sent to the project sponsor as directed by the communication plan. What was Peter doing?

Selecione uma das seguintes:

  • A Change management

  • B Project Risk Management

  • C Project Procurement Management

  • D The Control Communications process

Explicação

Questão 83 de 99

1

Which of the following addresses typical cost and staffing levels of the generic life cycle structure?
.
.

Selecione uma das seguintes:

  • A Cost and staffing levels are high during planning and execution, and start to taper off when project documents are archived.

  • B Cost and staffing levels steadily rise throughout project initiation and planning, and plateau during execution and closing

  • C Cost and staffing levels steadily rise throughout project execution, and then drop quickly after deliverables are accepted

  • D Cost and staffing levels steadily rise through project initiation and organizing and preparing, plateau during execution, and then drop quickly after deliverables are accepted.

Explicação

Questão 84 de 99

1

Before considering the project closed, which activity is performed by the project manager to ensure the objectives have been met?

Selecione uma das seguintes:

  • A Comparison of project costs against the project management plan

  • B Comparison of customer acceptance documentation against change requests

  • C Review of the scope baseline to ensure completion

  • D Comparison of the project management plan baseline against the project management plan

Explicação

Questão 85 de 99

1

Your internal customer wants the best website possible in order to attract the most customers. Your sponsor insists on using internal resources (who have never developed web pages) to save money. What is the BEST thing for you to do?

Selecione uma das seguintes:

  • A Outsource development

  • B Use internal resources

  • C Facilitate a meeting between the customer and sponsor to resolve the difference

  • D Tell senior management

Explicação

Questão 86 de 99

1

A portion of the project scope that will be included in a contract is a:

.

Selecione uma das seguintes:

  • A Procurement management plan.

  • B Procurement SOW.

  • C WBS.

  • D Scope statement

Explicação

Questão 87 de 99

1

Your company has issued a request for proposal (RFP) for a project, and your husband's company has responded to the bid.

Selecione uma das seguintes:

  • A Tell your management about the relationship.

  • B Inform management about the relationship and excuse yourself from the vendor selection activities.

  • C Provide information to the selection team.

  • D Inform PMI®.

Explicação

Questão 88 de 99

1

Outputs of the Acquire Project Team process include:

Selecione uma das seguintes:

  • A Human resource management plan, enterprise environmental factors and organizational process assets.

  • B Pre-assignment, negotiation, acquisition and virtual teams.

  • C Roles and responsibilities, project organization charts and staffing management plan.

  • D Project staff assignments, resource calendars and project management plan updates.

Explicação

Questão 89 de 99

1

Why is Project Procurement Management necessary?

Selecione uma das seguintes:

  • A To manage contracts

  • B To manage sellers

  • C To manage sponsors

  • D To purchase products or services from outside the project team

Explicação

Questão 90 de 99

1

An output of Control Scope is:

Selecione uma das seguintes:

  • A Accepted deliverables.

  • B Project charter.

  • C Project management plan updates.

  • D Project scope statement.

Explicação

Questão 91 de 99

1

Project cost control searches out causes of __________ variances.

Selecione uma das seguintes:

  • A Positive

  • B Positive and negative

  • C Negative

  • D Earned value (EV)

Explicação

Questão 92 de 99

1

Which of the following statements about Control Scope is false?

Selecione uma das seguintes:

  • A Control Scope is the process of monitoring the status of the project and product scope and managing changes to the scope baseline

  • B Control Scope assures all requested changes and recommended corrective actions are processed through the Perform Integrated Change Control process

  • C The Control Scope process is rarely needed, because changes are fairly uncommon

  • D Control Scope is used to manage the actual changes when they occur

Explicação

Questão 93 de 99

1

You are a senior project manager, who is responsible for mentoring a new project manager. You are both present in a project team meeting when one of the team members becomes frustrated. You approach the team member after the meeting and ask if there is any support that you can provide. The team member informs you that he is concerned about the level of trust other team members have with the project's third party partner. Later, in a one-on-one meeting with the new project manager, you inform her of the interaction, and ask her if she believes this is important to address. Her proper response would be:

Selecione uma das seguintes:

  • A It is important to ensure that everyone on the team does not feel intimidated.

  • B It is not important, because the team will likely not need to work with the third party partner ever again.

  • C It is important to improve feelings of trust and agreement among team members in order to raise morale, lower conflict, and increase teamwork.

  • D It is not important, because the team members will get the work done regardless of how they feel.

Explicação

Questão 94 de 99

1

During negotiations, your contract administrator tells a salesperson that they are stupid because they come from a rural part of the world. You should first:

Selecione uma das seguintes:

  • A Do nothing. The contract administrator is using a negotiation tactic.

  • B Tell the salesperson he's wearing an ugly tie.

  • C Change the subject.

  • D Tell management.

Explicação

Questão 95 de 99

1

One of your team members is responsible for updating the earned value analysis report. You notice that the SPI for a task is always greater than 1.0, even though the delivery date keeps slipping. What should you do?

Selecione uma das seguintes:

  • A Investigate the data

  • B Do the report yourself

  • C Discuss the results with the team member

  • D Inform the team member's manager

Explicação

Questão 96 de 99

1

You are halfway through phase one of a multiphase project. Your SPI is 1.03 and your CPI is 0.87. Your sponsor suggests that you review the current risk register with your primary stakeholders, as the nature of the risks may have changed. You remember seeing a description of this technique in the PMBOK® Guide. What was the technique called?

Selecione uma das seguintes:

  • A Risk audit

  • B Risk reassessment

  • C Variance analysis

  • D Contingent response strategy

Explicação

Questão 97 de 99

1

Andy takes his project notebook to every project meeting. This is an example of a/an:


Selecione uma das seguintes:

  • A Tool to manage communications.

  • B Communication activity.

  • C Push communication.

  • D Obsessive behavior.

Explicação

Questão 98 de 99

1

Your PMO buys software that will simulate project execution by computing duration and cost many times, varying the outcomes using statistics. What technique does this software employ?

Selecione uma das seguintes:

  • A Monte Carlo analysis

  • B Taguchi analysis

  • C Network analysis

  • D Gantt analysis

Explicação

Questão 99 de 99

1

A diagram used to identify causes of risks is called a/an:
.

Selecione uma das seguintes:

  • A Ishikawa diagram.

  • B Taguchi diagram.

  • C Gantt diagram.

  • D Fishbowl diagram

Explicação