The WBS and WBS dictionary are completed. The project team has begun working on identifying risks. The sponsor contacts the project manager, requesting that the responsability assignment matrix be issued. The project has a budget of US $100,000 and is taking place in three countries using 14 human resources. There is a little risk expected for the project, and teh project manager has managed many projects similar to this one. What is the next thing to do?
Selecione uma das seguintes: