[1] Gleim #: 1.1.1 -- Source: CMA 691 3-2
Each organization plans and budgets its operations for slightly different reasons. Which one of
the following is not a significant reason for planning?

Selecione uma das seguintes:

  • Providing a basis for controlling operations.

  • Forcing managers to consider expected future trends and conditions.

  • Ensuring profitable operations.

  • Checking progress toward the objectives of the organization.

Explicação

Questão 2 de 100

1

[2] Gleim #: 1.1.2 -- Source: CMA 697 3-11
When developing a budget, an external factor to consider in the planning process is

Selecione uma das seguintes:

  • A change to a decentralized management system.

  • The implementation of a new bonus program.

  • New product development.

  • The merger of two competitors.

Explicação

Questão 3 de 100

1

[3] Gleim #: 1.1.3 -- Source: CMA 692 3-11
Which one of the following is usually not cited as being an advantage of a formal budgetary
process?

Selecione uma das seguintes:

  • Forces management to evaluate the reasonableness of assumptions used and goals
    identified in the budgetary process.

  • Ensures improved cost control within the organization and prevents inefficiencies.

  • Provides a formal benchmark to be used for feedback and performance evaluation.

  • Serves as a coordination and communication device between management and
    subordinates.

Explicação

Questão 4 de 100

1

[4] Gleim #: 1.1.4 -- Source: CIA 1194 III-54
The major objectives of any budget system are to

Selecione uma das seguintes:

  • Define responsibility centers, provide a framework for performance evaluation, and
    promote communication and coordination among organization segments.

  • Define responsibility centers, facilitate the fixing of blame for missed budget predictions,
    and ensure goal congruence between superiors and subordinates.

  • Foster the planning of operations, provide a framework for performance evaluation, and
    promote communication and coordination among organization segments.

  • Foster the planning of operations, facilitate the fixing of blame for missed budget
    predictions, and ensure goal congruence between superiors and subordinates.

Explicação

Questão 5 de 100

1

[5] Gleim #: 1.1.5 -- Source: CMA 1291 3-21
A planning calendar in budgeting is the

Selecione uma das seguintes:

  • Calendar period covered by the budget.

  • Schedule of activities for the development and adoption of the budget.

  • Calendar period covered by the annual budget and the long-range plan.

  • Sales forecast by months in the annual budget period.

Explicação

Questão 6 de 100

1

[6] Gleim #: 1.1.6 -- Source: CMA 1292 3-8
A budget manual, which enhances the operation of a budget system, is most likely to include

Selecione uma das seguintes:

  • A chart of accounts.

  • Distribution instructions for budget schedules.

  • Employee hiring policies.

  • Documentation of the accounting system software.

Explicação

Questão 7 de 100

1

[7] Gleim #: 1.1.7 -- Source: CIA 590 IV-14
One of the primary advantages of budgeting is that it

Selecione uma das seguintes:

  • Does not take the place of management and administration.

  • Bases the profit plan on estimates.

  • Is continually adapted to fit changing circumstances.

  • Requires departmental managers to make plans in conjunction with the plans of other
    interdependent departments.

Explicação

Questão 8 de 100

1

[8] Gleim #: 1.1.8 -- Source: CMA 692 3-7
The budget that describes the long-term position, goals, and objectives of an entity within its
environment is the

Selecione uma das seguintes:

  • Capital budget.

  • Operating budget.

  • Cash management budget.

  • Strategic budget.

Explicação

Questão 9 de 100

1

[9] Gleim #: 1.1.9 -- Source: CMA 697 3-20
Which one of the following best describes the role of top management in the budgeting
process? Top management

Selecione uma das seguintes:

  • Should be involved only in the approval process.

  • Lacks the detailed knowledge of the daily operations and should limit their involvement.

  • Needs to be involved, including using the budget process to communicate goals.

  • Needs to separate the budgeting process and the business planning process into two
    separate processes.

Explicação

Questão 10 de 100

1

[10] Gleim #: 1.1.10 -- Source: Publisher
An advantage of participative budgeting is that it

Selecione uma das seguintes:

  • Minimizes the cost of developing budgets.

  • Reduces the effect on the budgetary process of employee biases

  • Yields information known to management but not to employees.

  • Encourages acceptance of the budget by employees.

Explicação

Questão 11 de 100

1

[11] Gleim #: 1.1.11 -- Source: CMA 683 4-2
The primary role of the budget director and the budgeting department is to

Selecione uma das seguintes:

  • Settle disputes among operating executives during the development of the annual operating
    plan.

  • Develop the annual profit plan by selecting the alternatives to be adopted from the
    suggestions submitted by the various operating segments

  • Justify the budget to the executive committee of the board of directors.

  • Compile the budget and manage the budget process.

Explicação

Questão 12 de 100

1

[12] Gleim #: 1.1.12 -- Source: CMA 693 3-22
Which one of the following is not considered to be a benefit of participative budgeting?

Selecione uma das seguintes:

  • Individuals at all organizational levels are recognized as being part of the team; this results
    in greater support of the organization.

  • The budget estimates are prepared by those in direct contact with various activities.

  • Managers are more motivated to reach the budget objectives since they participated in
    setting them.

  • When managers set the final targets for the budget, senior management need not be
    concerned with the overall profitability of current operations.

Explicação

Questão 13 de 100

1

[13] Gleim #: 1.1.13 -- Source: CMA 1292 3-23
The budgeting technique that is most likely to motivate managers is

Selecione uma das seguintes:

  • Top-down budgeting.

  • Zero-based budgeting.

  • Program budgeting and review technique.

  • Bottom-up budgeting.

Explicação

Questão 14 de 100

1

[14] Gleim #: 1.1.14 -- Source: CMA 1292 3-13
When comparing performance report information for top management with that for lower-level
management,

Selecione uma das seguintes:

  • Top management reports are more detailed.

  • Lower-level management reports are typically for longer time periods.

  • Top management reports show control over fewer costs.

  • Lower-level management reports are likely to contain more quantitative data and less
    financial data.

Explicação

Questão 15 de 100

1

[15] Gleim #: 1.1.15 -- Source: CMA 0205
In the budgeting and planning process for a firm, which one of the following should be
completed first?

Selecione uma das seguintes:

  • Sales budget.

  • Financial budget.

  • Cost management plan.

  • Strategic plan.

Explicação

Questão 16 de 100

1

[16] Gleim #: 1.1.16 -- Source: CMA 0205
Which one of the following is most important to a successful budgeting effort?

Selecione uma das seguintes:

  • Experienced analysts.

  • Integrated budget software.

  • Reliable forecasts and trend analyses.

  • Top management support.

Explicação

Questão 17 de 100

1

[17] Gleim #: 1.1.17 -- Source: Publisher
An improperly executed budget process might have the effect(s) of

Selecione uma das seguintes:

  • Disregard of overall company goals.

  • Inflated budget requests.

  • Meeting short-term but not long-term goals.

  • All of the answers are correct.

Explicação

Questão 18 de 100

1

[18] Gleim #: 1.1.18 -- Source: Publisher
The major disadvantage of a budget produced by means of a top-down process is

Selecione uma das seguintes:

  • Impairment of goal congruence.

  • Lack of involvement by upper-level management.

  • Inconsistency with strategic plans.

  • Absence of a significant motivational effect.

Explicação

Questão 19 de 100

1

[19] Gleim #: 1.1.19 -- Source: Publisher
A budget helps a company control costs by setting cost guidelines. However, a budget also
performs the function(s) of

Selecione uma das seguintes:

  • Planning.

  • Motivating.

  • Communicating.

  • All of the answers are correct.

Explicação

Questão 20 de 100

1

[20] Gleim #: 1.1.20 -- Source: Publisher
Ineffective budget control systems are characterized by

Selecione uma das seguintes:

  • Use of budgets as a planning but not a control tool.

  • Use of budgets for harassment of individuals rather than motivation.

  • Lack of timely feedback in the use of the budget.

  • All of the answers are correct.

Explicação

Questão 21 de 100

1

[21] Gleim #: 1.1.21 -- Source: Publisher
Which of the following statements regarding budgets is false?

Selecione uma das seguintes:

  • Budgets present organizational plans in a formal, logical, and integrated manner.

  • Budgets are used only as a planning function.

  • Budgets may be developed for cash flows or labor usage.

  • A budget is a plan that contains a quantitative statement of expected results.

Explicação

Questão 22 de 100

1

[22] Gleim #: 1.1.22 -- Source: CMA 0408 2-001
All of the following are advantages of the use of budgets in a management control system
except that budgets

Selecione uma das seguintes:

  • Force management planning.

  • Provide performance criteria.

  • Promote communication and coordination within the organization.

  • Limit unauthorized expenditures.

Explicação

Questão 23 de 100

1

[23] Gleim #: 1.1.23 -- Source: CMA 0408 2-003
All of the following are criticisms of the traditional budgeting process except that it

Selecione uma das seguintes:

  • Makes across-the-board cuts when early budget iterations show that planned expenses are
    too high.

  • Incorporates non-financial measures as well as financial measures into its output.

  • Overemphasizes a fixed time horizon, such as one year.

  • Is not used until the end of the budget period to evaluate performance.

Explicação

Questão 24 de 100

1

[24] Gleim #: 1.1.24 -- Source: CMA 0408 2-005
The following sequence of steps is employed by a company to develop its annual profit plan:
Planning guidelines are disseminated downward by top management after receiving input
from all levels of management.
A sales budget is prepared by individual sales units reflecting the sales targets of the
various segments. This provides the basis for departmental production budgets and other
related components by the various operating units. Communication is primarily lateral with
some upward communication possible.
A profit plan is submitted to top management for coordination and review. Top
management’s recommendations and revisions are acted upon by middle management. A
revised profit plan is resubmitted for further review to top management.
Top management grants final approval and distributes the formal plan downward to the
various operating units.
This outline of steps best describes which one of the following approaches to budget
development?

Selecione uma das seguintes:

  • Imposed budgeting by top management.

  • Bottom-up approach.

  • Top-down approach.

  • Total justification of all activities by operating units

Explicação

Questão 25 de 100

1

[25] Gleim #: 1.1.25 -- Source: CMA 0408 2-006
All of the following are advantages of top-down budgeting as opposed to participatory
budgeting, except that it

Selecione uma das seguintes:

  • Increases coordination of divisional objectives

  • Reduces the time required for budgeting.

  • May limit the acceptance of proposed goals and objectives.

  • Facilitates implementation of strategic plans.

Explicação

Questão 26 de 100

1

[26] Gleim #: 1.1.26 -- Source: CMA 0408 2-007
In developing the budget for the next year, which one of the following approaches would
produce the greatest amount of positive motivation and goal congruence?

Selecione uma das seguintes:

  • Permit the divisional manager to develop the goal for the division that in the manager’s
    view will generate the greatest amount of profits.

  • Have senior management develop the overall goals and permit the divisional manager to
    determine how these goals will be met.

  • Have the divisional and senior management jointly develop goals and objectives while
    constructing the corporation’s overall plan of operation.

  • Have the divisional and senior management jointly develop goals and the divisional
    manager develop the implementation plan.

Explicação

Questão 27 de 100

1

[27] Gleim #: 1.1.27 -- Source: CMA 0408 2-008
Which one of the following is not an advantage of a participatory budgeting process?

Selecione uma das seguintes:

  • Coordination between departments.

  • Communication between departments.

  • Cost congruence.

  • Control of uncertainties.

Explicação

Questão 28 de 100

1

[28] Gleim #: 1.1.28 -- Source: CMA 0408 2-010
Which one of the following statements concerning approaches for the budget development
process is correct?

Selecione uma das seguintes:

  • The top-down approach to budgeting will not ensure adherence to strategic organizational
    goals.

  • To prevent ambiguity, once departmental budgeted goals have been developed, they should
    remain fixed even if the sales forecast upon which they are based proves to be wrong in the
    middle of the fiscal year.

  • With the information technology available, the role of budgets as an organizational
    communication device has declined.

  • Since department managers have the most detailed knowledge about organizational
    operations, they should use this information as the building blocks of the operating budget.

Explicação

Questão 29 de 100

1

[29] Gleim #: 1.1.29 -- Source: CMA 0408 2-011
Rock Industries has four divisions. In the quest to develop a more achievable budget for the
coming year, the chief executive officer has elected to develop the company’s budget by using
a decentralized bottom-up budget approach. Chip Jones is production manager in one of the
divisions. Jones’ involvement in the budget process this year will probably

Selecione uma das seguintes:

  • Be negligible.

  • Require development of a production budget that is forwarded to the Budget Department.

  • Require development of a production budget after receiving the division’s projected sales
    forecast.

  • Require development of a production budget based on the prior year’s manufacturing
    activity.

Explicação

Questão 30 de 100

1

[30] Gleim #: 1.1.30 -- Source: CMA 0408 2-012
Marietta Thomas, Amador Corporation’s vice president of planning, has seen and heard it all.
She has told the corporate controller that she is “....very upset with the degree of slack that
veteran managers use when preparing their budgets.” Thomas has considered implementing
some of the following activities during the budgeting process.
1. Develop the budgets by top management and issue them to lower-level operating units.
2. Study the actual revenues and expenses of previous periods in detail.
Have the budgets developed by operating units and accept them as submitted by a
company-wide budget committee.
3.
4. Share the budgets with all employees as a means to reach company goals and objectives.
Use an iterative budgeting process that has several “rounds” of changes initiated by
operating units and/or senior managers.
5.
Which one of these activities should Amador implement in order to best remedy Thomas’
concerns, help eliminate the problems experienced by Amador, and motivate personnel?

Selecione uma das seguintes:

  • 1 only.

  • 2 and 3.

  • 2 and 4.

  • 2, 4, and 5.

Explicação

Questão 31 de 100

1

[31] Gleim #: 1.1.31 -- Source: CMA 0408 2-013
Budgeting problems where departmental managers are repeatedly achieving easy goals or
failing to achieve demanding goals can be best minimized by establishing

Selecione uma das seguintes:

  • Preventive controls.

  • A policy that allows managers to build slack into the budget.

  • Participative budgeting where managers pursue objectives consistent with those set by top
    management.

  • Better communication whereby managers discuss budget matters daily with their superiors.

Explicação

Questão 32 de 100

1

[32] Gleim #: 1.1.32 -- Source: CMA 0408 2-015
Which one of the following items would most likely cause the planning and budgeting system
to fail? The lack of

Selecione uma das seguintes:

  • Historical financial data.

  • Input from several levels of management.

  • Top management support.

  • Adherence to rigid budgets during the year.

Explicação

Questão 33 de 100

1

[33] Gleim #: 1.1.33 -- Source: CMA 0408 2-016
All of the following are disadvantages of top-down budgeting as opposed to participatory
budgeting, except that it

Selecione uma das seguintes:

  • May result in a budget that is not possible to achieve.

  • May limit the acceptance of proposed goals and objectives.

  • Reduces the communication between employees and management.

  • Reduces the time required for budgeting.

Explicação

Questão 34 de 100

1

[34] Gleim #: 1.1.34 -- Source: CMA 0408 2-017
Suboptimal decision making is not likely to occur when

Selecione uma das seguintes:

  • There is little congruence among the overall organization goals, the subunit goals, and the
    individual goals of decision makers.

  • Goals and standards of performance are set by the top management.

  • Guidance is given to subunit managers about how standards and goals affect them.

  • The subunits in the organization compete with each other for the same input factors or for
    the same customers.

Explicação

Questão 35 de 100

1

[35] Gleim #: 1.1.35 -- Source: CMA 0408 2-018
All of the following statements concerning standard costs are correct except that

Selecione uma das seguintes:

  • Time and motion studies are often used to determine standard costs.

  • Standard costs are usually set for one year.

  • Standard costs can be used in costing inventory accounts.

  • Standard costs are usually stated in total, while budgeted costs are usually stated on a perunit
    basis.

Explicação

Questão 36 de 100

1

[36] Gleim #: 1.1.36 -- Source: CMA 0408 2-019
One approach for developing standard costs incorporates communication, bargaining, and
interaction among product line managers; the immediate supervisors for whom the standards
are being developed; and the accountants and engineers before the standards are accepted by
top management. This approach would best be characterized as a(n)

Selecione uma das seguintes:

  • Imposed approach.

  • Centralized top-down approach.

  • Engineering approach.

  • Team development approach.

Explicação

Questão 37 de 100

1

[37] Gleim #: 1.1.37 -- Source: CMA 0408 2-020
When compared with ideal standards, practical standards

Selecione uma das seguintes:

  • Produce lower per-unit product costs.

  • Result in a less desirable basis for the development of budgets.

  • Incorporate very generous allowance for spoilage and worker inefficiencies.

  • Serve as a better motivating target for manufacturing personnel.

Explicação

Questão 38 de 100

1

[38] Gleim #: 1.1.38 -- Source: CMA 0408 2-021
Diana Stinson, Cherry Valley, Inc.’s factory manager, had lost her patience. Six months ago,
she appointed a team from the production and service departments to finalize the allocation of
costs and setting of standard costs. They were still feuding, so she hired Brennan and Rose, a
large consulting firm, to resolve the matter.
All of the following are potential consequences of having the standards set by Brennan and
Rose except that

Selecione uma das seguintes:

  • Brennan and Rose may not fully understand Cherry Valley’s manufacturing process,
    resulting in suboptimal performance.

  • Employees could react negatively since they did not participate in setting the standards

  • There could be dissatisfaction if the standards contain costs that are not controllable by the
    unit held responsible.

  • The standards may appear to lack management support

Explicação

Questão 39 de 100

1

[39] Gleim #: 1.1.39 -- Source: CMA 0408 2-022
Jura Corporation is developing standards for the next year. Currently XZ-26, one of the
material components, is being purchased for $36.45 per unit. It is expected that the
component’s cost will increase by approximately 10% next year and the price could range from
$38.75 to $44.18 per unit, depending on the quantity purchased. The appropriate standard for
XZ-26 for next year should be set at the

Selecione uma das seguintes:

  • Current actual cost plus the forecasted 10% price increase.

  • Lowest purchase price in the anticipated range to keep pressure on purchasing to always
    buy in the lowest price range.

  • Highest price in the anticipated range to ensure that there are only favorable purchase price
    variances.

  • Price agreed upon by the purchasing manager and the appropriate level of company
    management.

Explicação

Questão 40 de 100

1

[40] Gleim #: 1.1.40 -- Source: CMA 0408 2-023
Which one of the following will allow a better use of standard costs and variance analysis to
help improve managerial decision-making?

Selecione uma das seguintes:

  • Company A does not differentiate between variable and fixed overhead in calculating its
    overhead variances.

  • Company B uses the prior year’s average actual cost as the current year’s standard.

  • Company C investigates only negative variances.

  • Company D constantly revises standards to reflect learning curves.

Explicação

Questão 41 de 100

1

[41] Gleim #: 1.1.41 -- Source: CMA 0408 2-024
After performing a thorough study of Michigan Company’s operations, an independent
consultant determined that the firm’s labor standards were probably too tight. Which one of the
following facts would be inconsistent with the consultant’s conclusion?

Selecione uma das seguintes:

  • A review of performance reports revealed the presence of many unfavorable efficiency
    variances.

  • Michigan’s budgeting process was well-defined and based on a bottom-up philosophy.

  • Management noted that minimal incentive bonuses have been paid in recent periods.

  • Production supervisors found several significant fluctuations in manufacturing volume,
    with short-term increases on output being followed by rapid, sustained declines.

Explicação

Questão 42 de 100

1

[42] Gleim #: 1.2.42 -- Source: CMA 1291 4-27
Automite Company is an automobile replacement parts dealer in a large metropolitan
community. Automite is preparing its sales forecast for the coming year. Data regarding both
Automite’s and industry sales of replacement parts as well as both the used and new automobile
sales in the community for the last 10 years have been accumulated. If Automite wants to
determine whether its sales of replacement parts are dependent upon the industry sales of
replacement parts or upon the sales of used and new automobiles, the company should employ

Selecione uma das seguintes:

  • Simulation techniques.

  • Correlation and regression analysis.

  • Statistical sampling.

  • Time series analysis.

Explicação

Questão 43 de 100

1

[43] Gleim #: 1.2.43 -- Source: CMA 1285 5-27
The correlation coefficient that indicates the weakest linear association between two variables
is

Selecione uma das seguintes:

  • –0.73

  • –0.11

  • 0.12

  • 0.35

Explicação

Questão 44 de 100

1

[44] Gleim #: 1.2.44 -- Source: CMA 1289 5-14
Correlation is a term frequently used in conjunction with regression analysis and is measured
by the value of the coefficient of correlation, r. The best explanation of the value r is that it

Selecione uma das seguintes:

  • Is always positive.

  • Interprets variances in terms of the independent variable.

  • Ranges in size from negative infinity to positive infinity.

  • Is a measure of the relative relationship between two variables.

Explicação

Questão 45 de 100

1

[45] Gleim #: 1.2.45 -- Source: CMA 697 4-26
A regression equation

Selecione uma das seguintes:

  • Estimates the dependent variables.

  • Encompasses factors outside the relevant range.

  • Is based on objective and constraint functions.

  • Estimates the independent variable.

Explicação

Questão 46 de 100

1

[46] Gleim #: 1.2.46 -- Source: CIA 593 III-64
What coefficient of correlation results from the following data?
X Y
1 10
2 8
3 6
4 4
5 2

Selecione uma das seguintes:

  • A. 0

  • B. –1

  • C. +1

  • D. Cannot be determined from the data given.

Explicação

Questão 47 de 100

1

[47] Gleim #: 1.2.47 -- Source: CMA 1290 4-27
In the standard regression equation y = a + bx, the letter b is best described as a(n)

Selecione uma das seguintes:

  • Independent variable

  • Dependent variable.

  • Constant coefficient

  • Variable coefficient.

Explicação

Questão 48 de 100

1

[48] Gleim #: 1.2.48 -- Source: CMA 1290 4-28
The letter x in the standard regression equation is best described as a(n)

Selecione uma das seguintes:

  • Independent variable

  • Dependent variable

  • Constant coefficient.

  • Coefficient of determination

Explicação

Questão 49 de 100

1

[49] Gleim #: 1.2.49 -- Source: CIA 1194 II-46
In regression analysis, which of the following correlation coefficients represents the strongest
relationship between the independent and dependent variables?

Selecione uma das seguintes:

  • 1.03

  • –.02

  • –.89

  • .75

Explicação

Questão 50 de 100

1

[50] Gleim #: 1.2.50 -- Source: CIA 595 II-46
The internal auditor of a bank has developed a multiple regression model which has been used
for a number of years to estimate the amount of interest income from commercial loans. During
the current year, the auditor applies the model and discovers that the r 2 value has decreased
dramatically, but the model otherwise seems to be working okay. Which of the following
conclusions are justified by the change?

Selecione uma das seguintes:

  • Changing to a cross-sectional regression analysis should cause r 2 to increase.

  • Regression analysis is no longer an appropriate technique to estimate interest income.

  • Some new factors, not included in the model, are causing interest income to change.

  • A linear regression analysis would increase the model’s reliability.

Explicação

Questão 51 de 100

1

[51] Gleim #: 1.2.51 -- Source: Publisher
The least exact method for separating fixed and variable costs is

Selecione uma das seguintes:

  • The least squares method

  • Computer simulation

  • The high-low method

  • Matrix algebra.

Explicação

Questão 52 de 100

1

Jackson Co. has the following information for the first quarter of its year:
Machine Cleaning
Hours Expense
January 2,100 $ 900
February 2,600 1,200
March 1,600 800
April 2,000 1,000

[52] Gleim #: 1.2.52 -- Source: Publisher
(Refers to Fact Pattern #1)
Using the high-low method, what is Jackson’s variable cost of cleaning per machine hour?

Selecione uma das seguintes:

  • $.40

  • $.48

  • $2.00

  • $2.50

Explicação

Questão 53 de 100

1

[53] Gleim #: 1.2.53 -- Source: Publisher
(Refers to Fact Pattern #1)
Using the high-low method, what is Jackson’s fixed cost?

Selecione uma das seguintes:

  • $160

  • $320

  • $640

  • $1,040

Explicação

Questão 54 de 100

1

[54] Gleim #: 1.2.54 -- Source: Publisher
(Refers to Fact Pattern #1)
Jackson’s management expects machine hours for the month of May to be 1,400 hours. What is
their expected total cost for the month of May using the high-low method?

Selecione uma das seguintes:

  • $560

  • $650

  • $720

  • $760

Explicação

Questão 55 de 100

1

[Fact Pattern #2]
In preparing the annual profit plan for the
coming year, Wilkens Company wants to
determine the cost behavior pattern of the
maintenance costs. Wilkens has decided to use
linear regression by employing the equation y
= a + bx for maintenance costs. The prior
year’s data regarding maintenance hours and
costs and the results of the regression analysis
are as follows.
Average cost per hour $ 9.00
a 684.65
b 7.2884
Standard error of a 49.515
Standard error of b .12126
Standard error of the estimate 34.469
r 2 .99724
Hours of Maintenance
Activity Costs
January 480 $ 4,200
February 320 3,000
March 400 3,600
April 300 2,820
May 500 4,350
June 310 2,960
July 320 3,030
August 520 4,470
September 490 4,260
October 470 4,050
November 350 3,300
December 340 3,160
Sum 4,800 $43,200
Average 400 $ 3,600

[55] Gleim #: 1.2.55 -- Source: CMA 1290 4-29
(Refers to Fact Pattern #2)
Based upon the data derived from the regression analysis, 420 maintenance hours in a month
would mean that Wilkens Co.’s maintenance costs (rounded to the nearest dollar) would be
budgeted at:

Selecione uma das seguintes:

  • $3,780

  • $3,600

  • $3,790

  • $3,746

Explicação

Questão 56 de 100

1

[56] Gleim #: 1.2.56 -- Source: CMA 1290 4-30
(Refers to Fact Pattern #2)
The percentage of Wilkens Co.’s total variance that can be explained by the regression equation
is

Selecione uma das seguintes:

  • 99.724%

  • 69.613%

  • 80.982%

  • 99.862%

Explicação

Questão 57 de 100

1

[57] Gleim #: 1.2.57 -- Source: Publisher
(Refers to Fact Pattern #2)
If Wilkens Company uses the high/low method of analysis, the equation for the relationship
between hours of activity and maintenance cost would be

Selecione uma das seguintes:

  • y = 400 + 9.0x

  • y = 570 + 7.5x

  • y = 3,600 + 400x

  • y = 570 + 9.0x

Explicação

Questão 58 de 100

1

Alpha Company produces several different products and is making plans for the introduction of a
new product which it will sell for $6 a unit. The following estimates have been made for
manufacturing costs on 100,000 units to be produced the first year:
Direct materials $500,000
Direct labor $40,000 (the labor rate is $4/hour)
Overhead costs have not been established for the new product, but monthly data on total production
and overhead cost for the past 24 months have been analyzed using simple linear regression. The
following results were derived from the simple regression and provide the basis for overhead cost
estimates for the new product.
Dependent variable (y) -- Factory overhead costs
Independent variable (x) -- Direct labor hours
Computed values:
y-intercept $40,000
Coefficient of independent variable $2.10
Coefficient of correlation 0.953
Standard error of estimate $2,840
Standard error of regression coefficient 0.42
Mean value of independent variable $18,000
Coefficient of determination 0.908
[58] Gleim #: 1.2.58 -- Source: Publisher
(Refers to Fact Pattern #3)
What percentage of the variation in Alpha’s overhead costs is explained by the independent
variable?

Selecione uma das seguintes:

  • 90.8%

  • 42%

  • 48.8%

  • 95.3%

Explicação

Questão 59 de 100

1

Gleim #: 1.2.59 -- Source: Publisher
(Refers to Fact Pattern #3)
Alpha’s total overhead cost for an estimated activity level of 20,000 direct labor hours would be

Selecione uma das seguintes:

  • $42,000

  • $82,000

  • $122,000

  • $222,000

Explicação

Questão 60 de 100

1

[60] Gleim #: 1.2.60 -- Source: CIA 1194 III-59
The manager of the assembly department of a company would like to estimate the fixed and
variable components of the department’s cost. To do so, the manager has collected information
on total cost and output for the past 24 months. To estimate the fixed and variable components
of total cost, the manager should use

Selecione uma das seguintes:

  • Regression analysis

  • Game theory

  • Sensitivity analysis

  • Queuing theory

Explicação

Questão 61 de 100

1

Gleim #: 1.2.61 -- Source: CIA 1195 II-30
A division uses a regression in which monthly advertising expenditures are used to predict
monthly product sales (both in millions of dollars). The results show a regression coefficient for
the independent variable equal to 0.8. This coefficient value indicates that

Selecione uma das seguintes:

  • The average monthly advertising expenditure in the sample is $800,000.

  • When monthly advertising is at its average level, product sales will be $800,000.

  • On average, for every additional dollar in advertising you get $0.80 in additional sales.

  • Advertising is not a good predictor of sales because the coefficient is so small.

Explicação

Questão 62 de 100

1

[62] Gleim #: 1.2.62 -- Source: CMA 1289 4-11
All of the following are assumptions underlying the validity of linear regression output except

Selecione uma das seguintes:

  • The errors are normally distributed.

  • The mean of the errors is zero

  • Certainty.

  • The standard deviation of the errors is constant

Explicação

Questão 63 de 100

1

Gleim #: 1.2.63 -- Source: CMA 1292 3-3
In determining cost behavior in business, the cost function is often expressed as y = a + bx.
Which one of the following cost estimation methods should not be used in estimating fixed and
variable costs for the equation?

Selecione uma das seguintes:

  • Graphic method.

  • Simple regression.

  • High and low point method.

  • Multiple regression

Explicação

Questão 64 de 100

1

[64] Gleim #: 1.2.64 -- Source: CMA 0408 1-136
For cost estimation, simple regression differs from multiple regression in that simple regression
uses only

Selecione uma das seguintes:

  • One dependent variable, while multiple regression uses all available data to estimate the
    cost function

  • Dependent variables, while multiple regression can use both dependent and independent
    variables

  • One independent variable, while multiple regression uses more than one independent
    variable

  • One dependent variable, while multiple regression uses more than one dependent variable

Explicação

Questão 65 de 100

1

[65] Gleim #: 1.2.65 -- Source: CMA 0408 1-137
A company has accumulated data for the last 24 months in order to determine if there is an
independent variable that could be used to estimate shipping costs. Three possible independent
variables being considered are packages shipped, miles shipped, and pounds shipped. The
quantitative technique that should be used to determine whether any of these independent
variables might provide a good estimate for shipping costs is

Selecione uma das seguintes:

  • Flexible budgeting

  • Linear programming.

  • Linear regression

  • Variable costing

Explicação

Questão 66 de 100

1

[66] Gleim #: 1.2.66 -- Source: CMA 0408 1-138
Slawford Manufacturing developed the following multiple regression equation, utilizing many
years of data, and uses it to model, or estimate, the cost of its product.
Cost = FC + (a × L) + (b × M)
Where: FC = fixed costs
L = labor rate per hour
M = material cost per pound
Which one of the following changes would have the greatest impact on invalidating the results
of this model?

Selecione uma das seguintes:

  • A significant reduction in factory overheads, which are a component of fixed costs.

  • Renegotiation of the union contract calling for much higher wage rates

  • A large drop in material costs, as a result of purchasing the material from a foreign source.

  • A significant change in labor productivity

Explicação

Questão 67 de 100

1

[67] Gleim #: 1.2.67 -- Source: CMA 0408 1-139
In order to analyze sales as a function of advertising expenses, the sales manager of Smith
Company developed a simple regression model. The model included the following equation,
which was based on 32 monthly observations of sales and advertising expenses with a related
coefficient of determination of .90.
Sales = $10,000 + (2.5 × Advertising expenses)
If Smith Company’s advertising expenses in one month amounted to $1,000, the related point
estimate of sales would be

Selecione uma das seguintes:

  • $2,500

  • $11,250

  • $12,250

  • $12,500

Explicação

Questão 68 de 100

1

[68] Gleim #: 1.2.68 -- Source: CMA 0408 1-140
The results of regressing Y against X are as follows:
Coefficient
Intercept 5.23
Slope 1.54
When the value of X is 10, the estimated value of Y is

Selecione uma das seguintes:

  • 6.78

  • 8.05

  • 20.63

  • 53.84

Explicação

Questão 69 de 100

1

[69] Gleim #: 1.3.69 -- Source: CMA 697 4-25
Corrigon Industries is preparing a bid for a special project requiring the production of 35,000
units. The engineering personnel have advised that the units can be produced in groups with the
first group consisting of 1,000 units. A review of prior experience indicates that the direct labor
time needed per unit will be progressively smaller by a constant percentage rate as experience
is gained in the production process. The quantitative method that would best estimate
Corrigon’s total cost for the project is

Selecione uma das seguintes:

  • Linear programming.

  • Dynamic programming.

  • Learning curve analysis.

  • Time series analysis.

Explicação

Questão 70 de 100

1

[70] Gleim #: 1.3.70 -- Source: CMA 1293 4-24
The average labor cost per unit for the first batch produced by a new process is $120. The
cumulative average labor cost after the second batch is $72 per product. Using a batch size of
100 and assuming the learning curve continues, the total labor cost of four batches will be

Selecione uma das seguintes:

  • $4,320

  • $10,368

  • $2,592

  • $17,280

Explicação

Questão 71 de 100

1

[Fact Pattern #4]
Moss Point Manufacturing recently
completed and sold an order of 50 units that
had costs as shown in the next column.
The company has now been requested to
prepare a bid for 150 units of the same
product.
Direct materials $ 1,500
Direct labor (1,000 hours × $8.50) 8,500
Variable overhead (1,000 hours ×
$4.00)*
4,000
Fixed overhead** 1,400
$15,400
*Applied on the basis of direct labor hours.
**Applied at the rate of 10% of variable cost.

[71] Gleim #: 1.3.71 -- Source: CMA 1288 5-19
(Refers to Fact Pattern #4)
If an 80% learning curve is applicable, Moss Point’s total cost on this order would be estimated
at

Selecione uma das seguintes:

  • $26,400

  • $32,000

  • $38,000

  • $41,800

Explicação

Questão 72 de 100

1

[72] Gleim #: 1.3.72 -- Source: CMA 1288 5-20
(Refers to Fact Pattern #4)
If Moss Point had experienced a 70% learning curve, the bid for the 150 units would

Selecione uma das seguintes:

  • Show a 30% reduction in the total direct labor hours required with no learning curve.

  • Include increased fixed overhead costs.

  • Be 10% lower than the total bid at an 80% learning curve.

  • Include 6.40 direct labor hours per unit at $8.50 per hour.

Explicação

Questão 73 de 100

1

[73] Gleim #: 1.3.73 -- Source: Publisher
A particular manufacturing job is subject to an estimated 90% learning curve. The first unit
required 50 labor hours to complete. What is the cumulative average time per unit after four
units are completed?

Selecione uma das seguintes:

  • 50.0 hours.

  • 45.0 hours.

  • 40.5 hours

  • 40.0 hours

Explicação

Questão 74 de 100

1

[74] Gleim #: 1.3.74 -- Source: Publisher
A particular manufacturing job is subject to an estimated 80% learning curve. The first unit
required 50 labor hours to complete. What is the cumulative average time per unit after eight
units are completed?

Selecione uma das seguintes:

  • 20.0 hours.

  • 25.6 hours.

  • 32.0 hours.

  • 40.0 hours

Explicação

Questão 75 de 100

1

[75] Gleim #: 1.3.75 -- Source: Publisher
A particular manufacturing job is subject to an estimated 80% learning curve. The first unit
required 50 labor hours to complete. If the learning curve is based on a cumulative average time
per unit assumption, what is the time required to complete the second unit?

Selecione uma das seguintes:

  • 30.0 hours.

  • 40.0 hours

  • 45.0 hours

  • 50.0 hours

Explicação

Questão 76 de 100

1

[76] Gleim #: 1.3.76 -- Source: CIA 1187 III-41
A learning curve of 80% assumes that direct labor costs are reduced by 20% for each doubling
of output. What is the incremental cost of the sixteenth unit produced as an approximate
percentage of the first unit produced?

Selecione uma das seguintes:

  • 41%

  • 31%

  • 51%

  • 64%

Explicação

Questão 77 de 100

1

[77] Gleim #: 1.3.77 -- Source: Publisher
Red Baron, Inc. is a new competitor in the production of airplane propellers. Red Baron has to
train its employees in the process of making propellers. To increase the speed of learning, Red
Baron will give a bonus to the employee with the lowest cumulative average time per unit after
eight units are completed. Lucy took 50 hours to complete the first unit, and she is subject to an
80% learning curve. Sally took 60 hours to complete the first unit, and she is subject to a 70%
learning curve. Marcy took 40 hours to complete the first unit, and she is subject to a 90%
learning curve. Patty took 55 hours to complete the first unit, and she is subject to a 75%
learning curve. Which employee will receive the bonus?

Selecione uma das seguintes:

  • Lucy

  • Sally

  • Marcy

  • Patty

Explicação

Questão 78 de 100

1

[78] Gleim #: 1.3.78 -- Source: CMA 692 4-5
Lake Corporation manufactures specialty components for the electronics industry in a highly
labor intensive environment. Arc Electronics has asked Lake to bid on a component that Lake
made for Arc last month. The previous order was for 80 units and required 120 hours of direct
labor to manufacture. Arc would now like 240 additional components. Lake experiences an
80% learning curve on all of its jobs. The number of direct labor hours needed for Lake to
complete the 240 additional components is

Selecione uma das seguintes:

  • 360.0

  • 187.2

  • 307.2

  • 256.0

Explicação

Questão 79 de 100

1

[79] Gleim #: 1.3.79 -- Source: CMA 696 4-7
It is estimated that a particular manufacturing job is subject to an 80% learning curve. The first
unit required 50 labor hours to complete. What is the cumulative average time per unit after
completing four units?

Selecione uma das seguintes:

  • 50.0 hours

  • 40.0 hours

  • 32.0 hours

  • 30.0 hours

Explicação

Questão 80 de 100

1

[80] Gleim #: 1.3.80 -- Source: CMA 1291 4-22
A company plans to bid on a special project that calls for a total of 24,000 units. The units will
be produced in lots, with the first lot consisting of 750 units. Based on prior experience, the
direct labor time needed per unit of product will be progressively smaller by a constant
percentage rate as experience is gained in the manufacturing process. The quantitative method
that would best estimate the company’s total cost for the project is

Selecione uma das seguintes:

  • Learning curve techniques

  • Differential calculus

  • Discounted cash flow techniques.

  • Linear programming

Explicação

Questão 81 de 100

1

[81] Gleim #: 1.3.81 -- Source: CMA 1294 4-28
Seacraft, Inc. received a request for a competitive bid for the sale of one of its unique boating
products with a desired modification. Seacraft is now in the process of manufacturing this
product but with a slightly different modification for another customer. These unique products
are labor intensive and both will have long production runs. Which one of the following
methods should Seacraft use to estimate the cost of the new competitive bid?

Selecione uma das seguintes:

  • Expected value analysis.

  • Learning curve analysis.

  • Regression analysis

  • Continuous probability simulation.

Explicação

Questão 82 de 100

1

[82] Gleim #: 1.3.82 -- Source: CMA 1289 4-7
The technique used to predict the change in direct labor hours as a new process stabilizes is

Selecione uma das seguintes:

  • Simple regression

  • Multiple regression

  • Time series analysis

  • Learning curve analysis

Explicação

Questão 83 de 100

1

[Fact Pattern #5]
LCB, Inc. is preparing a bid to the Department of the Navy to produce engines for rescue boats. The
company has manufactured these engines for the Navy for the past 3 years on an exclusive contract
and has experienced the following costs:
Cumulative Total Cumulative Costs
Units Produced Materials Labor
10 $ 60,000 $120,000
20 120,000 192,000
40 240,000 307,200
At LCB, variable overhead is applied on the basis of $1.00 per direct labor dollar. Based on
historical costs, LCB knows that the production of 40 engines will incur $100,000 of fixed overhead
costs. The bid request is for an additional 40 units; all companies submitting bids are allowed to
charge a maximum of 25% above full cost for each order.
[83] Gleim #: 1.3.83 -- Source: CMA 688 5-9
(Refers to Fact Pattern #5)
In order to ensure that the company would not lose money on the project, LCB’s minimum bid
for the 40 units would be

Selecione uma das seguintes:

  • $760,800

  • $608,640

  • $885,800

  • $708,640

Explicação

Questão 84 de 100

1

Gleim #: 1.3.84 -- Source: CMA 688 5-7
(Refers to Fact Pattern #5)
LCB’s rate of learning on the 3-year engine contract is

Selecione uma das seguintes:

  • 75.5%

  • 79.0%

  • 80.0%

  • 62.6%

Explicação

Questão 85 de 100

1

[85] Gleim #: 1.3.85 -- Source: CMA 688 5-8
(Refers to Fact Pattern #5)
The maximum bid price that LCB, Inc. could submit to the Department of the Navy for the 40
units is

Selecione uma das seguintes:

  • $760,800

  • $608,640

  • $885,800

  • $708,640

Explicação

Questão 86 de 100

1

Donehart Corporation produces agricultural vehicles. Most of the component parts for these vehicles
are subcontracted to reliable vendors. The final assembly of all vehicles is accomplished at
Donehart’s plant. Donehart’s Engineering Department has developed a new fuel injection system
that can be produced in-house because of the availability of production capacity. The first production
run of the new fuel injection system has already been completed in-house. This 80-unit production
run took 60 direct labor hours per unit to produce based on the cumulative average labor hours per
fuel injection unit. Donehart has experienced an 80% learning curve with similar products, and this
experience indicates that learning tends to cease by the time 640 systems are produced. Donehart’s
direct labor cost (including employee benefits) is $18 per direct labor hour. Donehart’s management
must decide whether to continue producing the fuel injection system or to subcontract the work.
Donehart’s purchasing agent has received a proposal from Midland, Inc., a company specializing in
fuel injection systems. From past contracts, Midland has proven to be efficient and reliable. The
terms of Midland’s proposal are outlined below.
- Donehart must supply all materials required for the fuel injection system units.
- The first 80 units produced by Midland will require direct labor input at the rate of 56 hours per
unit. Current direct labor cost is $20 per hour.
- The direct labor cost charged to Donehart will be the hourly rate in effect at the time the work is
performed. Midland is currently negotiating its labor contract, which includes a 4% increase in
direct labor cost and should be applicable when Donehart signs the contract.
- A learning curve factor of 75% will be applied through the first 640 units produced, and all
benefits derived from the learning factor will accrue to Donehart.
- Donehart must pay the actual labor cost incurred plus a 5% margin.

[86] Gleim #: 1.3.86 -- Source: Publisher
(Refers to Fact Pattern #6)
If Donehart manufactures the units in-house, what is the average labor hours per unit after
manufacturing 640 units?

Selecione uma das seguintes:

  • 60

  • 30.72

  • 23.63

  • 23.04

Explicação

Questão 87 de 100

1

[87] Gleim #: 1.3.87 -- Source: Publisher
(Refers to Fact Pattern #6)
If Donehart manufactures the units in-house, how many total hours will it take to complete
1,000 units?

Selecione uma das seguintes:

  • 8,294.4 hours

  • 19,660.8 hours.

  • 24,330 hours

  • 27,955.2 hours

Explicação

Questão 88 de 100

1

[88] Gleim #: 1.3.88 -- Source: Publisher
(Refers to Fact Pattern #6)
If Donehart manufactures the units in-house, how much additional cost will the company incur
after the first batch in order to produce a total of 1,000 units?

Selecione uma das seguintes:

  • $416,793.60

  • $463,104

  • $503,193.60

  • $559,104

Explicação

Questão 89 de 100

1

[89] Gleim #: 1.3.89 -- Source: Publisher
(Refers to Fact Pattern #6)
If Donehart subcontracts the order to Midland, what is the total number of labor hours required
to produce the 640 units on the learning curve?

Selecione uma das seguintes:

  • 15,120 hours

  • 18,350 hours

  • 19,530 hours

  • 35,840 hours

Explicação

Questão 90 de 100

1

[90] Gleim #: 1.3.90 -- Source: Publisher
(Refers to Fact Pattern #6)
If Donehart subcontracts the order to Midland, how many hours will it take to complete a unit
after the initial 640 units on the learning curve are finished?

Selecione uma das seguintes:

  • 11.81 hours

  • 15.75 hours

  • 21.50 hours

  • 23.625 hours

Explicação

Questão 91 de 100

1

[91] Gleim #: 1.3.91 -- Source: Publisher
(Refers to Fact Pattern #6)
If Donehart subcontracts the order to Midland, how much additional cost will Donehart incur
after the first batch in order to obtain a total of 1,000 units?

Selecione uma das seguintes:

  • $302,400

  • $330,220.80

  • $390,600

  • $426,535.20

Explicação

Questão 92 de 100

1

[92] Gleim #: 1.3.92 -- Source: CIA 1193 III-69
Management of a bookkeeping company observed that the average time spent to perform
identical tasks using a new software package decreases as the number of tasks performed
increases. The following information on the use of the new software was collected.
Number of Total Time to Average Time
Tasks Perform All to Perform
Performed Tasks Each Task
1 10 minutes 10 minutes
2 18 minutes 9 minutes
4 32.4 minutes 8.1 minutes
If this learning effect continues, what is the average time to perform each of the first eight
tasks?

Selecione uma das seguintes:

  • 7.29 minutes.

  • 8.1 minutes

  • 6.56 minutes

  • 5.90 minutes

Explicação

Questão 93 de 100

1

[93] Gleim #: 1.3.93 -- Source: CMA 1289 4-10
Learning curves are best used to predict

Selecione uma das seguintes:

  • Unit material costs

  • Overhead variances

  • Total unit costs

  • Unit direct labor costs.

Explicação

Questão 94 de 100

1

[Fact Pattern #7]
Aerosub, Inc. has developed a new product for spacecraft that includes the production of a complex
part. The manufacture of this part requires a high degree of technical skill. Management believes
there is a good opportunity for its technical force to learn and improve as they become accustomed to
the production process. The production of the first unit requires 10,000 direct labor hours.
Management projects an 80% learning curve and wants to produce a total of eight units.
[94] Gleim #: 1.3.94 -- Source: CMA 0408 1-142
(Refers to Fact Pattern #7)
Upon completion of the eighth unit, Aerosub’s cumulative average direct labor hours required
per unit of the product will be

Selecione uma das seguintes:

  • 5,120 hours

  • 6,400 hours

  • 8,000 hours

  • 10,000 hours

Explicação

Questão 95 de 100

1

[95] Gleim #: 1.3.95 -- Source: CMA 0408 1-145
(Refers to Fact Pattern #7)
Upon completion of the eighth unit, Aerosub’s cumulative direct labor hours will be

Selecione uma das seguintes:

  • 29,520 hours.

  • 40,960 hours

  • 64,000 hours

  • 80,000 hours

Explicação

Questão 96 de 100

1

[96] Gleim #: 1.3.96 -- Source: CMA 0408 1-149
(Refers to Fact Pattern #7)
After completing the first unit, the estimated total direct labor hours Aerosub will require to
produce the seven additional units will be

Selecione uma das seguintes:

  • 30,960 hours

  • 40,960 hours.

  • 56,000 hours.

  • 70,000 hours.

Explicação

Questão 97 de 100

1

[97] Gleim #: 1.3.97 -- Source: CMA 0408 1-144
A manufacturing company has the opportunity to submit a bid for 20 units of a product on
which it has already produced two 10-unit lots. The production manager believes that the
learning experience observed on the first two lots will continue for at least the next two lots.
The direct labor required on the first two lots was as follows:
5,000 direct labor hours for the first lot of 10 units
3,000 additional direct labor hours for the second lot of 10 units
The learning rate experienced by the company on the first two lots of this product is

Selecione uma das seguintes:

  • 40.0%

  • 60.0%

  • 62.5%

  • 80.0%

Explicação

Questão 98 de 100

1

[Fact Pattern #8]
Proper Propeller, Inc. plans to manufacture a newly designed high-technology propeller for
airplanes. Proper Propeller forecasts that as workers gain experience, they will need less time to
complete the job. Based on prior experience, Proper Propeller estimates a 70% cumulative learning
curve and has projected the following costs.
Cumulative number Manufacturing Projections
of units produced Average cost per unit Total costs
1 $20,000 $20,000
2 14,000 28,000
[98] Gleim #: 1.3.98 -- Source: CMA 0408 1-148
(Refers to Fact Pattern #8)
If Proper Propeller produces eight units, the average manufacturing cost per unit will be

Selecione uma das seguintes:

  • $1,647

  • $6,860

  • $9,800

  • $14,000

Explicação

Questão 99 de 100

1

[99] Gleim #: 1.3.99 -- Source: CMA 0408 1-146
(Refers to Fact Pattern #8)
If Proper Propeller produces eight units, the total manufacturing cost will be

Selecione uma das seguintes:

  • $50,660

  • $54,880

  • $62,643

  • $112,000

Explicação

Questão 100 de 100

1

[100] Gleim #: 1.3.100 -- Source: CMA 0408 1-151
(Refers to Fact Pattern #8)
After completing production of the first propeller, the estimated cost for Proper Propeller to fill
an order for seven additional propellers is

Selecione uma das seguintes:

  • $34,880

  • $54,880

  • $92,000

  • $98,000

Explicação