Questão 1 de 150

1

QUESTION 17( EXAME 3)
You are a consulting project manager with over 15 years experience running software development projects. You have been engaged to manage a finance application project for a new customer. However on the first day onsite at the customer's headquarters you are told the project has been cancelled, but there is a need for a project manager to manage a major infrastructure project to deploy a large number of servers and storage devices. The customer asks if you would be interested in leading this project. You have never managed this type of project before but would be interested in the challenge. Which of the follow is the best response?

Selecione uma das seguintes:

  • A. Do not mention your lack of experience, but ask for more information about the project. After reviewing the information and see that you could probably wing the project, accept the project.

  • B. Accept the job with the caveat you can bring in any needed resources to work on the project, then hire a project manager you know that works in this area to handle the implementation details.

  • C. Decline the opportunity, citing your lack of experience and knowledge in this area.
    .

  • D. Do not mention your lack of experience and accept the job

Explicação

Questão 2 de 150

1

QUESTION 18
A Project manager estimates the work to be accomplished in the near term in detail, at a low level of the Work Breakdown structure (WBS); while he estimates work far in the future as WBS components, that are at a relatively high level of the WBS. What is this technique called?

Selecione uma das seguintes:

  • A. Decomposition

  • B. Rolling wave planning

  • C. Scope Creep

  • D. Earned value planning

Explicação

Questão 3 de 150

1

QUESTION 19
Negative risks can either be ______, transferred, or mitigated as a countermeasure.

Selecione uma das seguintes:

  • A. enhanced

  • B. avoided

  • C. exploited

  • D. ignored

Explicação

Questão 4 de 150

1

QUESTION 20
The WBS represents all product and project work. The total work at the lowest levels should roll up to the higher levels so that nothing is left out and no extra work is performed. This is also called as:
e

Selecione uma das seguintes:

  • A. 100% rul

  • B. 80/20 rule

  • C. Pareto's rule

  • D. Ground rule

Explicação

Questão 5 de 150

1

QUESTAO 21 You are at work related social event and a colleague tells you another project manager has just hired her niece's engineering firm for a city public improvement project that you are managing. You know that this company's proposal did not meet the pre-defined selection criteria to be considered for award. What do you do?

Selecione uma das seguintes:

  • A. File a complaint with PMI.

  • B. Escalate the issue to the appropriate management.

  • C. Ask the project manager about what you have just heard. If your suspicions are confirmed, escalate the issue to the appropriate management.

  • D. Do nothing.

Explicação

Questão 6 de 150

1

QUESTAO 22: A project manager is just finishing a project that has not gone well. Apart from cost overruns and schedule overruns, there have been a lot of quality defects and the project required a lot of senior management intervention to finally reach completion. The project manager should now:

Selecione uma das seguintes:

  • A. Focus on closing the project and moving on to the next one. Lessons learned is not applicable to this project since it has done badly

  • B. Focus on presenting the data in positive light while ensuring that the reasons for the delays and problems are appropriately documented.

  • C. Mask bad data and only present good data since his performance appraisal will otherwise be impacted.

  • D. Document lessons learned from the project and update the lessons learned knowledge database.

Explicação

Questão 7 de 150

1

QUESTAO 23: In a matrix organization, where the team members report to both, a functional manager as well as a project manager, generally, whose responsibility is it to manage the dual reporting relationship?

Selecione uma das seguintes:

  • A. Functional manager

  • B. HR manager

  • C. Team members

  • D. Project Manager

Explicação

Questão 8 de 150

1

QUESTAO 24: A Resource Breakdown Structure (RBS) would be used to breakdown the project by type of resources. The RBS is an example of a:

Selecione uma das seguintes:

  • A. Linear chart

  • B. Matrix chart

  • C. Flow chart

  • D. Hierarchical chart

Explicação

Questão 9 de 150

1

QUESTAO 25: While managing a project, you decide to prepare an email for the project stakeholders describing the current project status. This is best described as an example of:

Selecione uma das seguintes:

  • A. Vertical communication

  • B. Nonverbal communication

  • C. Informal communication

  • D. Formal communication

Explicação

Questão 10 de 150

1

QUESTAO 26: QUESTION 26
Analogous Estimating is an estimation technique that use the values of parameters such as scope, cost, budget and duration from a previous similar activity as the basis of activity and is frequently used to estimate when there is a limited amount of information about the project. This is a form of:

Selecione uma das seguintes:

  • A. Gross value estimation

  • B. Function point estimation

  • C. Fixed point estimation

  • D. Precision Estimation

Explicação

Questão 11 de 150

1

QUESTÃO 27: During the execution of your project, you decide that you would like to have charts of your project status - cost and schedule, display certain key project data, and hold your project meetings in a specific conference room. Such a place would be called:

Selecione uma das seguintes:

  • A. Armageddon

  • B. War room

  • C. Battlefield

  • D. Ground zero

Explicação

Questão 12 de 150

1

QUESTAO 28: The document that formally authorizes a project is the:

Selecione uma das seguintes:

  • A. Project SOW

  • B. Project Plan

  • C. Project Charter

  • D. Project Scope Statement

Explicação

Questão 13 de 150

1

QUESTAO 29: You are managing a medium sized construction project, and are reviewing some invoices from the electrical contractor. You see that materials not required for your project have been included on the invoice. After making a few phone calls it becomes clear that one of your project resources asked one of the vendor's staff to add a few extra circuits to one part of the building. This change was never approved through the change management process. What do you do?

Selecione uma das seguintes:

  • A. Notify the manager of your project resource that he failed to follow proper processes.
    .

  • B. Refuse to pay the charges

  • C. Call a team meeting to determine how this will impact the project, then inform stakeholders of the impacts.

  • D. Immediately inform the project stakeholders of the unauthorized scope change. Then call a team meeting to determine the impact to the project.

Explicação

Questão 14 de 150

1

QUESTAO 30: You are presented with a situation in a project where you need to measure the performance of the project. Which of these techniques would suit your requirement?
A. Learned Value Technique

Selecione uma das seguintes:

  • A. Learned Value Technique

  • B. Earned Value Technique

  • C. Analogous Estimating

  • D. Expert Judgment

Explicação

Questão 15 de 150

1

QUESTAO 31: A manager asks you to evaluate four new projects that he has suggested for next year. You review the projects and notice that one is not really a project, but more an operational task. Which of these is not a project?

Selecione uma das seguintes:

  • A. Change the product to enable increased consumer usage

  • B. Manage a set of people for the next year to deliver the desired productivity results

  • C. Respond to a customer request for different product packaging

  • D. Resolve a space constraint issue by building a new addition to the plant

Explicação

Questão 16 de 150

1

QUESTAO 32: Which of the following Project Scope Management processes documents a configuration management system?

Selecione uma das seguintes:

  • A. Control Scope

  • B. Define Scope

  • C. Verify Scope

  • D. Plan Scope Management

Explicação

Questão 17 de 150

1

QUESTAO 33: The stakeholders of a project typically have:

Selecione uma das seguintes:

  • A. Positive objectives

  • B. Negative objectives

  • C. Conflicting objectives

  • D. Similar objectives

Explicação

Questão 18 de 150

1

QUESTAO 34: A project was estimated to cost $ 200,000 with a timeline of 10 months. Due to a shipment delay, the schedule was slightly delayed. This was however made up by receiving the first batch of materials for the project by air. The net result was that there was some additional cost in the project. At the end of the second month, the Project Manager reviews the project and finds that the project is 20% complete and Actual Costs are $ 50,000. The Estimate to complete (ETC) for the project would now be:

Selecione uma das seguintes:

  • A. $160,000

  • B. $210,000

  • C. $250,000

  • D. $200,000

Explicação

Questão 19 de 150

1

QUESTAO 35: You have a team of engineers working on your project. Two of the engineers have frequent disagreements. You ask them to resolve their differences through a discussion. However, that does not yield any results. Subsequently, you get involved and based on an analysis of the situation, suggest some changes in the way they work with each other. This still does not yield results and you find that the project schedule is beginning to suffer. What is you next course of action?

Selecione uma das seguintes:

  • A. Take Disciplinary action, if required, since the needs of the project are not being met.

  • B. Don't do anything. Differences of opinion amongst the team members is a healthy situation

  • C. Speak to the two team members and ask them to resolve their conflict amicably.

  • D. Ensure that they work in different shifts so that they don't clash with each other.

Explicação

Questão 20 de 150

1

QUESTAO 37:While developing the project schedule, you find that the completion of a successor activity depends on the completion of its predecessor activity. What is this dependency called?

Selecione uma das seguintes:

  • A. Start-to-Finish

  • B. Start-to-Start

  • C. Finish-to-Start

  • D. Finish-to-Finish

Explicação

Questão 21 de 150

1

Which of the following is not a tool and technique of the Collect Requirements process?

Selecione uma das seguintes:

  • A. Group creativity techniques

  • B. Interviews

  • C. Questionnaires

  • D. Traceability matrix

Explicação

Questão 22 de 150

1

You are planning out the communications methods to use as part of stakeholder management. The most effective means for communicating and resolving issues with stakeholders is:

Selecione uma das seguintes:

  • A. Status reports.

  • B. Electronic mail.

  • C. Telephone calls.

  • D. Face-to-face meetings

Explicação

Questão 23 de 150

1

A project manager wishes to illustrate the connections between the work that needs to be done and the project team members. According to the PMBOK, the resulting document would be called:
A. Responsibility Assignment Matrix (RAM)

Selecione uma das seguintes:

  • A. Responsibility Assignment Matrix (RAM)

  • B. Resource Planning Chart (RPC)

  • C. Task Assignment Model (TAM)

  • D. Resource Assignment (RAC)

Explicação

Questão 24 de 150

1

Which of the following contains an extensive procurement changes approval process?

Selecione uma das seguintes:

  • A. Scope statement

  • B. Test plan

  • C. Requirements management plan

  • D. Contract change control system

Explicação

Questão 25 de 150

1

A project manager found that some of the project work was not done at the right time and was done in an improper sequence. What do you think was the likely issue?

Selecione uma das seguintes:

  • A. This is a project communications breakdown. The project manager needs to re-develop the communication management plan

  • B. The Project Scope document was not properly updated.

  • C. The Work Authorization System was not properly established in the project.

  • D. This is due to poor teamwork.

Explicação

Questão 26 de 150

1

A contract change control system should include:

Selecione uma das seguintes:

  • A. Vendor contact information, tracking systems, and approval levels necessary for authorizing changes

  • B. Paperwork, tracking systems, dispute resolution procedures, and approval levels necessary for authorizing changes

  • C. Information database, dispute resolution procedures, and approval levels necessary for authorizing changes

  • D. Tracking systems, legal ramifications for certain actions, and approval levels necessary for authorizing changes

Explicação

Questão 27 de 150

1

PMP Lite Mock Exam 4
QUESTION 1
Your project is slightly behind schedule, and you have not yet made a full impact assessment to make associated project changes to accommodate it. The weekly project status meeting is this afternoon, and because of your conference call schedule this morning you will not be able to complete the assessment to report to in the meeting. However, this is only a minor delay and you do not want anyone to worry unnecessarily. What is the best response?
.

Selecione uma das seguintes:

  • A. Use contingency reserves to compensate for the delay and report that progress is as planned

  • B. Report the actual status of the project in the meeting, and assure the project team that additional updates will be coming soon.

  • C. Inform the project team the progress is slightly behind schedule, and use the contingency reserves to cover the delay.

  • D. Say nothing about the delay at this time, and report that there are no major issues.

Explicação

Questão 28 de 150

1

You are involved as project manager in a fairly large-sized project. You are in the process of making a procurement decision and plan to go with a simple purchase order. However, you are doubtful whether this is the correct thing to do and decide to find out more details about the process to be followed. Based on your findings, which of the following would be correct?

Selecione uma das seguintes:

  • A. A simple purchase order is not appropriate for project. The project manager should always use the Request for Proposal (RFP) route.

  • B. Organizational process assets are guidelines available to the project. As project manager you have the final decision making authority and can decide whether to go in for a simple purchase order or not.

  • C. The value of the project is immaterial. As project manager, you have the final decision making authority to go in for a simple purchase order as long as you are contracting with an approved vendor

  • D. You would need to verify the policy constraints that form part of the Organizational process assets. Many organizations have policies that constrain procurement decisions and require use of a longer form of contract for projects above a certain value.

Explicação

Questão 29 de 150

1

Robert is currently identifying his project stakeholders. Which of the following is the key input to this process?

Selecione uma das seguintes:

  • A. Project charter

  • B. Cost management plan

  • C. Scope management plan

  • D. Stakeholder register

Explicação

Questão 30 de 150

1

A control chart is used to determine whether or not a process is stable or has predictable performance. When a process is within acceptable limits, the process need not be adjusted. What are the upper and lower control limits usually set as?

Selecione uma das seguintes:

  • A. + / - 3 sigma

  • B. + / - 6 sigma

  • C. + / - 2 sigma

  • D. + / - 1 sigma

Explicação

Questão 31 de 150

1

Robert is currently identifying his project stakeholders. Which of the following is the key input to this process?

Selecione uma das seguintes:

  • A. Project charter

  • B. Cost management plan

  • C. Scope management plan

  • D. Stakeholder register

Explicação

Questão 32 de 150

1

The Cost Management Plan is an output of the Plan Cost Management process. This plan is then integrated with other project plans in which of these processes?

Selecione uma das seguintes:

  • A. Develop Project Management Plan

  • B. Monitor and Control Project Work

  • C. Perform Integrated Change Control

  • D. Direct and Manage Project Work

Explicação

Questão 33 de 150

1

The three categories into which contracts can be broadly classified are:

Selecione uma das seguintes:

  • A. Cost-Reimbursable, Time and Material, Cost plus fixed fee

  • B. Fixed Price, Cost-Reimbursable and Lump Sum

  • C. Fixed Price, Cost-Reimbursable, Time and material.

  • D. Fixed Price, Time and Material, Lump Sum

Explicação

Questão 34 de 150

1

For any complex project, once the project stakeholders are identified, the next step is to classify these stakeholders based on their current and desired engagement levels. What is the benefit of classifying the project stakeholders?

Selecione uma das seguintes:

  • A. To help identify the project scope

  • B. To help populate the stakeholder register

  • C. To help define an approach strategy

  • D. It is a mandatory step in stakeholder analysis

Explicação

Questão 35 de 150

1

A ______ is a collection of projects or programs grouped together for strategic business needs.

Selecione uma das seguintes:

  • A. Portfolio

  • B. Management System

  • C. Enterprise

  • D. Array

Explicação

Questão 36 de 150

1

In a Finish to Start relationship between predecessor and successor activities, a project manager decides to schedule a successor activity 5 days before its predecessor is complete. This is accomplished by providing 5 days of:

Selecione uma das seguintes:

  • A. Lag

  • B. Load

  • C. Fast-tracking

  • D. Lead

Explicação

Questão 37 de 150

1

While managing a project, you decide to contract to an external enterprise. You enter into a contract where you pay the external enterprise a set amount (as defined by the contract), irrespective of the seller's costs. What would best describe this type of contract?

Selecione uma das seguintes:

  • A. FP-EPA

  • B. FFP

  • C. FPIF

  • D. CPFF

Explicação

Questão 38 de 150

1

Which of the following inaccurately describes a prototype?

Selecione uma das seguintes:

  • A. A prototype is tangible and allows stakeholders to fine-tune their expectations.

  • B. Requirements from a prototype are usually insufficient to move to the design phase.

  • C. Prototypes support the concept of progressive elaboration.

  • D. A prototype is a working model of the expected product.

Explicação

Questão 39 de 150

1

Susan is the project manager for a dam construction project. All project communications are recorded and documented for future reference. It has been decided that the project team will maintain last three months of project communication records at any given point in time. It has also been decided that the older communication records will be archived on a monthly basis. Where these records must be archived?

Selecione uma das seguintes:

  • A. Change log

  • B. Organizational process assets

  • C. Enterprise environmental factors

  • D. Issue log

Explicação

Questão 40 de 150

1

Which of these is not an information gathering technique used in the Identify Risks process?

Selecione uma das seguintes:

  • A. Interviewing

  • B. Root cause analysis

  • C. Brainstorming

  • D. Delta technique

Explicação

Questão 41 de 150

1

QUESTION 15
Which of the following is accurate regarding Project Integration Management?

Selecione uma das seguintes:

  • A. Project deliverables are not part of Integration Management

  • B. It involves the integration of process groups and not individual processes

  • C. The need for it becomes evident in situations where individual processes interact

  • D. It involves disregarding trade-offs and focuses on clearly articulating how accomplish all requirements by the deadline

Explicação

Questão 42 de 150

1

Which of the following is NOT a tool or technique of the Acquire Project Team process?

Selecione uma das seguintes:

  • A. Negotiation

  • B. Multi-criteria decision analysis

  • C. Pre-assignment

  • D. Conflict management

Explicação

Questão 43 de 150

1

A company you worked for several years ago is bidding on a project your new company will be starting in approximately 6 months. You have been selected to manage the project, and will be participating in the vendor selection processes. What should you do?

Selecione uma das seguintes:

  • A. Notify the stakeholders of your status and excuse yourself from the vendor selection process.

  • B. Provide the vendor selection committee with as much detail as you can remember about your former company so that the best decision can be reached.

  • C. Notify the project stakeholders of your status as a former employee of the bidding company, and comply with their preferences for how you participate in the vendor selection process.

  • D. Do nothing.

Explicação

Questão 44 de 150

1

While the five process groups are typically completed in order, they often overlap with each other throughout the project. Which two process groups do not overlap unless a project is canceled?

Selecione uma das seguintes:

  • A. Initiating and Closing

  • B. Initiating and Executing

  • C. Initiating and Monitoring and Control

  • D. Planning and Closing

Explicação

Questão 45 de 150

1

Which of the following is the correct logical sequence of the five process groups?

Selecione uma das seguintes:

  • A. Planning, Monitoring and Controlling, Initiating, Executing, Closing

  • B. Planning, Initiating, Executing, Monitoring and Controlling, Closing

  • C. Initiating, Monitoring and Controlling, Planning, Executing, Closing

  • D. Initiating, Planning, Executing, Monitoring and Controlling, Closing

Explicação

Questão 46 de 150

1

You have met with your project sponsor and have been told that the project MUST be completed by the end of the year, no exceptions. This should be included in the project scope statement as a:

Selecione uma das seguintes:

  • A. Project Constraint

  • B. Project Boundary

  • C. Project Acceptance Criteria

  • D. Project Assumption

Explicação

Questão 47 de 150

1

The change requests created as an output of the Monitor and Control Project Work process may be attributed to all of the following except:

Selecione uma das seguintes:

  • A. Preventive Action

  • B. Defect Repair

  • C. Project status update

  • D. Corrective Action

Explicação

Questão 48 de 150

1

Lee is the project manager of a project and is planning responses to a set of risks. As a direct response of implementing this risk response, he anticipates certain other risks to arise. These would be termed as:

Selecione uma das seguintes:

  • A. Secondary risks

  • B. Primary risks

  • C. Planned risks

  • D. Workaround

Explicação

Questão 49 de 150

1

You have been identified as the project manager for constructing a large shopping mall in your city. Which of the following are not necessarily stakeholders in your project?

Selecione uma das seguintes:

  • A. The suppliers of the project

  • B. The tenants of the shopping mall

  • C. A senior project manager in your organization who just completed a similar project.

  • D. The chief financial officer of your company who controls the project finances.

Explicação

Questão 50 de 150

1

Three strategies that typically deal with negative risks or threats are:

Selecione uma das seguintes:

  • A. Enhance, Share and Accept

  • B. Transfer, Exploit and Accept

  • C. Avoid, Transfer and Exploit

  • D. Avoid, Transfer and Mitigate

Explicação

Questão 51 de 150

1

Which of the Project Time Management processes involves identifying and documenting dependencies between schedule activities?

Selecione uma das seguintes:

  • A. Sequence Activities

  • B. Define Activities

  • C. Develop Schedule

  • D. Control Schedule

Explicação

Questão 52 de 150

1

What does it mean if the Earned Value is equal to Actual Cost?

Selecione uma das seguintes:

  • A. Schedule Variance Index is 1

  • B. Project is on budget and on schedule

  • C. There is no cost variance

  • D. There is no schedule variance

Explicação

Questão 53 de 150

1

Your project sponsor has asked you to add 30% contingency to your project budget as a hedge against any unforeseen costs that could exceed the currently forecasted expenses, but has not provided any additional detail about why this is required. What do you do?

Selecione uma das seguintes:

  • A. Add 30% to the management reserves.

  • B. Ask the sponsor to elaborate the risks that are behind the request.

  • C. Rebaseline the project budget.

  • D. Add 30% to the total budget.

Explicação

Questão 54 de 150

1

Steve is the project manager of a global project. He finds that of late, there has been a deterioration in the quality of communication between various team members across the globe. What would you term this?

Selecione uma das seguintes:

  • A. Noise

  • B. Encoding

  • C. Medium

  • D. Message

Explicação

Questão 55 de 150

1

You are the project manager managing a project to design a print head for dot matrix printers. In order to determine ideal settings for print quality, the quality manager of the company suggests trying out various scenarios for printing by varying certain parameters on the print head. Identifying such variables which influence the product or process under development is called:

Selecione uma das seguintes:

  • A. Benchmarking

  • B. Design of Experiments

  • C. Statistical Sampling

  • D. Brainstorming

Explicação

Questão 56 de 150

1

Which of the following statements best describes Time & Material (T&M) contracts?

Selecione uma das seguintes:

  • A. T&M contracts are hybrid type of contractual agreements that could contain aspects of both cost-reimbursable and fixed-price type arrangements

  • B. T&M contracts are the best form of contracts when the scope of work and the number of hours of work for a specific resource category is clearly known.

  • C. T&M contracts are the same as Fixed Price contracts except that the total value is calculated using Fixed rates and the effort data is available to the purchaser as well as the seller. Once this is agreed upon, it becomes the same as a Fixed Price project.

  • D. T&M contracts are very risky since the value of the project is not known. It is best to go in for a fixed price (FP) contract.

Explicação

Questão 57 de 150

1

When does the Close Project or Phase process need to be performed in case of multi-phased projects?

Selecione uma das seguintes:

  • A. The Close Project or Phase process needs to be done at the end of each phase of the project; however, it is left to the project manager's discretion on whether he/she wants to perform this process in between phases. It necessarily needs to be done at the end of the project.

  • B. The Close Project or Phase process is done at the end of the project in case the work is contracted out to external performing organizations.

  • C. The Close Project or Phase process needs to performed at the end of the project and involves closing out the entire project scope.

  • D. The Close Project or Phase process needs to be performed at the end of each phase of the project and involves closing out the portion of project scope applicable to that phase.

Explicação

Questão 58 de 150

1

A project manager is about to start on a new project. Where would he find details about his authority level in the project?

Selecione uma das seguintes:

  • A. Organizational Process Assets

  • B. The Project Charter

  • C. The PMBOK

  • D. The Scope statement

Explicação

Questão 59 de 150

1

Which of the following is not true about the WBS?

Selecione uma das seguintes:

  • A. The project team must be involved in developing the WBS

  • B. The WBS must represent all product and project work.

  • C. WBS should focus on activities rather than deliverables

  • D. WBS is usually represented in a hierarchical fashion

Explicação

Questão 60 de 150

1

Which of the following is accurate regarding the Estimate Activity Resources process?

Selecione uma das seguintes:

  • A. It produces project resource calendars as the output

  • B. It determines dependencies that may require a lead or lag to define the relationship

  • C. This process is coordinated independent of the Estimate Cost process

  • D. It involves determining what and how many resources will be used

Explicação

Questão 61 de 150

1

In a project, Activity A has a duration of 4 days and begins on the morning of Monday the 4th. The successor Activity, B, has a Finish-to-Start (FS) relationship with A. The Finish-to-Start relationship has 2 days of lag, and Activity B has a duration of 3 days. If Saturday and Sunday are non working days, which of the following statements is true?

Selecione uma das seguintes:

  • A. Total elapsed days (completing both activities) is 7 days

  • B. Activity B will be completed by the end of day on Thursday, 14th

  • C. Activity B will be completed by the end of day on Friday, 15th.

  • D. Activity B will be completed by the end of day on Tuesday, 12th

Explicação

Questão 62 de 150

1

What is the BEST way to make an accurate forecasting of ETC?

Selecione uma das seguintes:

  • A. EAC - AC

  • B. BAC – EV

  • C. Manual forecasting of cost of the remaining work.

  • D. (BAC – EV)/CPI

Explicação

Questão 63 de 150

1

Which of the following is not a valid instance of Risk Transference?

Selecione uma das seguintes:

  • A. Use of a Cost Reimbursable contract

  • B. Warranties

  • C. Fixed Price contracts

  • D. Performance bonds

Explicação

Questão 64 de 150

1

Under which of the following scenarios would you not use a Decision tree?

Selecione uma das seguintes:

  • A. When some future scenarios are unknown.

  • B. When you need to look at the implications of not choosing certain alternatives.

  • C. When the future scenarios are known.

  • D. When the outcomes of some of the actions are uncertain.

Explicação

Questão 65 de 150

1

You have been assigned as a project manager of a new project to be executed out of New York. However, you determine that the project requires a Global Positioning Systems Expert who is not available within the company in New York. On doing a little checking, you determine that the company has an expert based in London, who is suitable for the project. However, the London based employee is not willing to relocate to New York for the project. In such a case:

Selecione uma das seguintes:

  • A. Write to the manager of the London based employee and inform him that the employee needs to be convinced to relocate to New York due to project requirements.

  • B. You would look at the option of moving ahead with the project by using a virtual team.

  • C. Manage the project without the key resource and flag this as a risk.

  • D. Co-location of resources is a key factor for the success of projects. As per PMI guidelines, you will not be able to proceed with the project since the resources is not available in New York.

Explicação

Questão 66 de 150

1

PMP Lite Mock Exam 5

QUESTAO 1You are managing a project to manufacture widgets for a customer. The customer has come to the factory to examine the product, and determines that while the product itself meets its requirements, the manner in which about half the widgets have been packaged does not meet requirements and is insisting they be repackaged. This re-work will require considerable time, resources, and cost to complete. The investigation into how and why the packaging was problematic, revealed that no process was developed to govern how the widget was to be placed in the packaging. The result is that the assembly line workers developed their own processes for packaging. What do you do?

Selecione uma das seguintes:

  • A. Notify the project stakeholders immediately and accept responsibility for the failure to develop and implement a packaging process.

  • B. Pursue formal disciplinary action against the assembly line manager and the quality manager.

  • C. Contact the legal department.

  • D. Crash the project.

Explicação

Questão 67 de 150

1

When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where must this information be documented?

Selecione uma das seguintes:

  • A. Human resource management plan

  • B. RACI chart

  • C. Resource calendar

  • D. Resource Breakdown Structure (RBS)

Explicação

Questão 68 de 150

1

A project's financial management reserve is identified in which process:

Selecione uma das seguintes:

  • A. Estimate Costs

  • B. Determine Budget

  • C. Control Costs

  • D. Estimate Activity Resources

Explicação

Questão 69 de 150

1

Which of these is not a component of the scope baseline that is contained in the project management plan?

Selecione uma das seguintes:

  • A. Work Breakdown Structure (WBS)

  • B. Requirements documentation

  • C. WBS Dictionary

  • D. Project Scope Statement

Explicação

Questão 70 de 150

1

John has been assigned to design a new car model for a well-known car manufacturer. The project has a small number of key stakeholders and John is planning to meet all of them in person in order to understand their requirements and expectations. Which of the following is not a project key stakeholder?

Selecione uma das seguintes:

  • A. Project sponsor.

  • B. Project manager.
    .

  • C. Customer.

  • D. Competitor.

Explicação

Questão 71 de 150

1

Project stakeholders are individuals and organizations that are actively involved in the project or have an interest in it. Which of the following is not a stakeholder?

Selecione uma das seguintes:

  • A. Customer.

  • B. Project Sponsor.

  • C. Competitor.

  • D. Project Manager.

Explicação

Questão 72 de 150

1

You have landed your dream job, as project manager working in an exotic sports car factory. Your project involves coming up with a smoother ride for the car. You have tasked the engineers to determine which type of suspension and what type of tires will provide the best ride and the most reasonable cost. This relates to which of the following processes?

Selecione uma das seguintes:

  • A. Control Risks.

  • B. Perform Quality Assurance.

  • C. Control Quality.

  • D. Plan Quality Management.

Explicação

Questão 73 de 150

1

The Manage Communications process requires which of the following inputs to determine which project management information system is available to manage project communications?

Selecione uma das seguintes:

  • A. Communications Management Plan.

  • B. Enterprise Environmental Factors.

  • C. Organizational Process Assets.

  • D. Work Performance Reports.

Explicação

Questão 74 de 150

1

You are about to contract out a project to a service provider. However, at the time of awarding the contract, you are not sure of the total effort involved. Since the scope of work cannot be accurately estimated, you want to agree the per unit rates for difference services. Which of the following would best suit your purpose?

Selecione uma das seguintes:

  • A. Cost-Plus-Fixed-Fee (CPFF).

  • B. Time & Material (T&M).

  • C. Fixed Price (FP).

  • D. Cost-Plus-Incentive-Fee (CPIF).

Explicação

Questão 75 de 150

1

The Identify Stakeholders process has four inputs. Three of them are project charter, enterprise environmental factors and organizational process assets. What is the fourth one?

Selecione uma das seguintes:

  • A. Procurement documents.

  • B. Stakeholder register.

  • C. Stakeholder engagement matrix.

  • D. Stakeholder management plan.

Explicação

Questão 76 de 150

1

As an experienced PMP, you have found that running a WBS meeting is tricky because you need to find a balance between decomposition and excessive decomposition. When items are excessively decomposed it leads all of the following, EXCEPT:

Selecione uma das seguintes:

  • A. It breaks the 100% rule.

  • B. Inefficient use of resources.

  • C. Non productive management effort.

  • D. Decreased efficiency when performing work.

Explicação

Questão 77 de 150

1

You are the sponsor of a project that is designed to record phone calls for quality control purposes. You are in the process of writing the charter, what is NOT an input into this document?

Selecione uma das seguintes:

  • A. Organizational standard processes

  • B. Marketplace conditions

  • C. Government or industry standards

  • D. Project Scope Statement

Explicação

Questão 78 de 150

1

John, a project manager, for Code Crashers Inc. has been assigned a project where he must lead a group of inexperienced programmers in developing a software package that creates Material Safety Data Sheets (MSDS) for a chemical company. This is very similar to a project that his colleague, Peter, worked on in 2006, with some junior programmers. If John needs to come up with a rough order of magnitude estimate, what tool or technique should he use?

Selecione uma das seguintes:

  • A. Parametric Estimating.

  • B. Bottom Up Estimating.

  • C. Three-point estimate.

  • D. Analogous Estimating
    .

Explicação

Questão 79 de 150

1

You are an expatriate working in a foreign country and have been asked to offer a cash payment gift to the procurement manager at a company you are bidding on work for. How BEST should you interpret this request?

Selecione uma das seguintes:

  • A. Agree to provide the cash payment because the procurement manager controls whether your bid is accepted.

  • B. Inform the procurement manager that offering such a payment would violate your professional standards.

  • C. Base your interpretation of the request on an understanding of the norms of the country you are in.

  • D. Express your anger at the request and inform the procurement manager that this would never happen in your home country.

Explicação

Questão 80 de 150

1

Jonathan is managing a computer network deployment project at a university campus. Jonathan wants to involve the key project stakeholders in the scheduling of the major work packages. He sends out a meeting invitation to all key stakeholders for this brainstorming session. Which of the following types of communication methods has Jonathan selected for the brainstorming?

Selecione uma das seguintes:

  • A. Push communication

  • B. Interactive communication

  • C. Pull communication

  • D. One-sided communication

Explicação

Questão 81 de 150

1

QUESTION 16 (exame 5 )
The Project Managers have maximum authority in which type of organization?

Selecione uma das seguintes:

  • A. Weak Matrix

  • B. Strong Matrix

  • C. Functional

  • D. Balanced Matrix

Explicação

Questão 82 de 150

1

QUESTION 17
As the Project Manager on the construction of a new hotel you have developed a project management plan that you believe is realistic and will be formally approved. The organizational assets that influenced the development of the plan may include all of the following except:

Selecione uma das seguintes:

  • A. Project management plan templates

  • B. Risk register from a past project

  • C. Change control procedures

  • D. Business case for the project

Explicação

Questão 83 de 150

1

QUESTION 18
As part of your staffing management plan, you have developed a chart indicating the # of hours (Y axis) a senior programmer will be working over the months (X
axis) of the project. This is an example of what?

Selecione uma das seguintes:

  • A. Pareto Chart

  • B. Ishikawa Diagram

  • C. Resource Histogram

  • D. Staff Acquisition Chart

Explicação

Questão 84 de 150

1

QUESTION 19
Which of the following is a control tool that helps the project management team quantify and categorize defects according to sources?

Selecione uma das seguintes:

  • A. Scatter chart

  • B. Pareto diagram

  • C. Control chart

  • D. Cause and effect diagram

Explicação

Questão 85 de 150

1

QUESTION 20
While performing an audit on a project run by another project manager, a certified PMP, you find that project processes have not been followed, and that company
procurement policies have been repeatedly violated. What do you do?

Selecione uma das seguintes:

  • A. Develop a plan to deal with the associated problems.

  • B. Ask the project manager to explain why these things have happened.

  • C. Notify the appropriate management immediately.

  • D. File a complaint with PMI

Explicação

Questão 86 de 150

1

QUESTION 21
You have successfully passed your PMP exam and are leading a project to replace the storage devices in a data center. In the following week, you and your team
of experts will be meeting with a storage device vendor to discuss the status of their deliverables that are due at week's end. What management process do these
activities reflect?

Selecione uma das seguintes:

  • A. Plan Procurement Management

  • B. Control Procurements

  • C. Conduct Procurements

  • D. Close Procurements

Explicação

Questão 87 de 150

1

QUESTION 22
Alan is the project manager of a project with 6 stakeholders. If the number of stakeholders goes up to 8, how many additional channels does he have to manage?

Selecione uma das seguintes:

  • A. 2

  • B. 14

  • C. 13

  • D. 28

Explicação

Questão 88 de 150

1

QUESTION 23
The project management plan can best be described as:

Selecione uma das seguintes:

  • A. A list of tasks, activities, durations and resources in a software program (e.g., Microsoft Project)

  • B. Coordinating changes across the entire project

  • C. Integrating and coordinating all project plans to create a consistent, coherent document

  • D. Integrating and coordinating all project documents and stakeholder expectations

Explicação

Questão 89 de 150

1

QUESTION 24
Which of the following is not an example of a procurement document?

Selecione uma das seguintes:

  • A. Tender Notice

  • B. Risk Register

  • C. Request for Proposal (RFP)

  • D. Invitation for Negotiation

Explicação

Questão 90 de 150

1

QUESTION 25
Your company will receive a large bonus payment for completing a customer's project by a certain date. However, as the project manager, you know the project
will complete approximately 2 weeks after that date as it is currently scheduled. Your manager is insisting that you to do whatever it takes to finish the project by
that date, even if it means "cutting corners here and there." What do you do?

Selecione uma das seguintes:

  • A. Make a formal scope change request.

  • B. Fast track the project.

  • C. Explain to both your manager and the project stakeholders the impact that this schedule change could have on the project.

  • D. Compress the schedule

Explicação

Questão 91 de 150

1

QUESTION 26
An organization wishes to ensure that the opportunity arising from a risk with positive impact is realized. This organization should:

Selecione uma das seguintes:

  • A. Exploit the risk

  • B. Mitigate the risk

  • C. Accept the risk

  • D. Avoid the risk

Explicação

Questão 92 de 150

1

QUESTION 27
Your Vice President has asked you what the Estimate at Completion is going to be for a small project you are working on. You were given a budget of $30,000,
and to date you have spent $20,000 but only completed $10,000 worth of work. You are sure that the future work will be accomplished at the planned rate.

Selecione uma das seguintes:

  • A. $40,000

  • B. $30,000

  • C. $60,000

  • D. $10,000

Explicação

Questão 93 de 150

1

QUESTION 28
You have just sat through an exhausting change control meeting discussing a change in scope to the project you have been working on for the last 7 months. After
lengthy discussion the change in scope was approved. As the Project Manager you should now update all of the following documentation, EXCEPT:

Selecione uma das seguintes:

  • A. Scope Baseline

  • B. Requirements documentation

  • C. WBS Dictionary

  • D. Project charter

Explicação

Questão 94 de 150

1

QUESTION 29
You work at a software company that authors Material Safety Data Sheets (MSDS) for chemical companies. Prior to releasing the MSDS to the company you have
created a list of items to be reviewed to see that they appear on the document such as: chemical name, CAS#, protection required, what to do an emergency, etc.
This is an example of what type of tool?

Selecione uma das seguintes:

  • A. Checklist

  • B. Process Improvement Plan

  • C. Quality Management Plan

  • D. Quality Metrics

Explicação

Questão 95 de 150

1

QUESTION 30
A project team is required to prepare a monthly project update report for the project key stakeholders. This report must contain the current status of the
deliverables, information related to the recently approved change requests, project's health and the forecasted estimates. This report is an example of?

Selecione uma das seguintes:

  • A. Milestone

  • B. Expert judgment

  • C. Work performance information

  • D. Work performance data

Explicação

Questão 96 de 150

1

QUESTION 31
You are the Project Manager for a large petroleum company and are in the process of writing the project charter for your sponsor. You have used the following as
inputs except:

Selecione uma das seguintes:

  • A. Business case for the project

  • B. Project statement of work

  • C. Work breakdown structure (WBS)

  • D. Project contract

Explicação

Questão 97 de 150

1

QUESTION 32
Which of these statements is accurate regarding quality management?

Selecione uma das seguintes:

  • A. Modern quality management complements project management

  • B. Overworking the team to meet requirements is not likely to increase attrition and rework

  • C. Quality and grade are essentially the same

  • D. Project requirements are turned into customer needs, wants, and expectations

Explicação

Questão 98 de 150

1

QUESTION 33
Which of the following processes produces a Risk Register?

Selecione uma das seguintes:

  • A. Perform Quantitative Risk Analysis

  • B. Plan Risk Management

  • C. Perform Qualitative Risk Analysis

  • D. Identify Risks

Explicação

Questão 99 de 150

1

QUESTION 34
The Risk Register contains details of all identified risks and current status. It is a document containing the results of:

Selecione uma das seguintes:

  • A. Plan Risk Responses

  • B. Identify Risks

  • C. Control Risks

  • D. Perform Qualitative Risk Analysis, Perform Quantitative Risk Analysis and Plan Risk Responses

Explicação

Questão 100 de 150

1

QUESTION 35
A co-worker mentions that another project manager regularly takes certain project resources to expensive dinners and expenses it to the company. However, this
project manager does not recognize or reward the contributions of any other project resources. What should you do?

Selecione uma das seguintes:

  • A. Do nothing.

  • B. Confront the project manager.

  • C. Implement a formal reward and recognition program on your own project.

  • D. Report this to the appropriate management

Explicação

Questão 101 de 150

1

QUESTION 36
You the project manager responsible for building a 100,000 sq. ft. data center. One of the schedule activities in your plan is to install the Computer Room Air
Conditioning (CRAC) units, however in order to start the installation of the units the raised floor in the data center must be completely installed first, so the units
have something to be bolted on to. This is an example of what type of dependency?

Selecione uma das seguintes:

  • A. External

  • B. Optional

  • C. Discretionary

  • D. Mandatory

Explicação

Questão 102 de 150

1

QUESTION 37
Robert wants to assign a risk owner for every project risk for which a risk response action has been planned. Where must he update this information?

Selecione uma das seguintes:

  • A. Human resource management plan

  • B. Risk register

  • C. Stakeholder register

  • D. Project charter

Explicação

Questão 103 de 150

1

QUESTION 38
You are analyzing the risk in a project and decide to do sensitivity analysis to determine which risks have the most potential impact on the project. You look at a
tool to help compare the relative importance of variables that have a high degree of uncertainty to those that are more stable. One such tool is:
A. Beta Distribution

Selecione uma das seguintes:

  • A. Beta Distribution

  • B. S-Curve

  • C. Control Chart

  • D. Tornado Diagram

Explicação

Questão 104 de 150

1

QUESTION 39
Which of these is accurate regarding the Develop Schedule process?

Selecione uma das seguintes:

  • A. Schedules are optimized such that all non-critical activities have a zero total float.

  • B. The critical path method is a schedule network analysis technique that is performed using the schedule model

  • C. Schedule compression shortens the project schedule while changing the project scope

  • D. Schedule network analysis is a technique that is carried out once the schedule is approved.

Explicação

Questão 105 de 150

1

QUESTION 40
A new CEO has come into your company and has promptly shut down your project because it no longer met the business needs of the company. While not
pleased with the decision, you document the level and completeness of the project to date. What activity or process is this part of?

Selecione uma das seguintes:

  • A. Close Project or Phase

  • B. Close Procurements

  • C. Control Scope

  • D. Validate Scope

Explicação

Questão 106 de 150

1

QUESTION 41
When a project is performed under contract, the contractual provisions will generally be considered as _____________ for the project.

Selecione uma das seguintes:

  • A. Constraints

  • B. Exclusions

  • C. Deliverables

  • D. Provisions

Explicação

Questão 107 de 150

1

QUESTION 42
You are the project manager responsible for building a 100,000 sq. ft. data center. One of the schedule activities in your plan is to install the Computer Room Air
Conditioning (CRAC) units, however in order to start the installation of the units the raised floor in the data center must be completely installed first. This is an
example of what type of precedence relationship?

Selecione uma das seguintes:

  • A. Finish to Finish

  • B. Start to Finish

  • C. Start to Start

  • D. Finish to Start

Explicação

Questão 108 de 150

1

QUESTION 43
The Manage Project Team process is part of what process group?

Selecione uma das seguintes:

  • A. Planning

  • B. Executing

  • C. Monitoring and Controlling

  • D. Closing

Explicação

Questão 109 de 150

1

QUESTION 44
You have been assigned a project where you are responsible for building a condo complex in a resort town. The project is expected to take 2 years to complete.
During your work breakdown structure meeting you have decomposed many deliverables into work packages and schedule activities, however there are some
work packages that will be occurring a year from now, so you have elected not to decompose those deliverables and work packages at this time. This is an
example of what tool and/or technique?

Selecione uma das seguintes:

  • A. Scope Creep

  • B. Poor Planning

  • C. Rolling Wave Planning

  • D. Time Delayed Decomposition

Explicação

Questão 110 de 150

1

QUESTION 45
A Probability and Impact Matrix contains risks prioritized according to their potential implications for meeting the project's objectives. The typical approach is:

Selecione uma das seguintes:

  • A. To use a look-up table or Probability and Impact Matrix with specific combinations of Probability and impact that lead to a risk being rated as "high", "moderate"
    or "low" importance. The importance for planning responses to the risk are usually set by the organization.

  • B. To create a Risk Breakdown Structure with the probabilities and Impacts listed on the individual boxes. The higher the risk, the closer it is towards the Start
    Node.

  • C. To use a look-up table or Probability and Impact Matrix with specific combinations of Probability and impact that lead to a risk being rated as "high", "moderate"
    or "low" importance. The importance for planning responses to the risk are usually set by the project manager.

  • D. To create a matrix with the Cost, Time, Scope and Quality on one axis and probability of occurrence on the other.

Explicação

Questão 111 de 150

1

QUESTION 46
You are attempting to estimate the resources required to put the server racks together in the new data center you are building. It has occurred to you that you may
be able to compress the schedule if you look at using power tools vs. hand tools to build the racks and use individuals who have worked on this brand of rack in the
past. This is an example of what type of resource estimating tool?

Selecione uma das seguintes:

  • A. Top Down Estimating

  • B. Bottom Up Estimating

  • C. Alternative Analysis

  • D. Published Estimating Data

Explicação

Questão 112 de 150

1

QUESTION 47
A project is contracted as a Time & Material (T&M) type of contract. The service provider initially estimates that the total effort involved would be about 1000 hours
of effort. The project is contracted at a rate of US$ 75 per hour of effort. If the project ended up with 1200 hours of effort, what would the contract payout be.

Selecione uma das seguintes:

  • A. US$ 75,000

  • B. US$ 90,000

  • C. US$ 82,500

  • D. US$ 120,000

Explicação

Questão 113 de 150

1

QUESTION 48
A project is contracted as a Cost-Plus-Incentive-Fee (CPIF) type of contract. The project is negotiated such that if the final costs are less than expected costs, the
sharing formula for cost savings is 75:25. The targeted cost is US$ 100,000 with an 8% incentive fee on the targeted cost. If the project comes in at US$ 80,000,
what would be the cost of the total contract?

Selecione uma das seguintes:

  • A. US$ 108,000

  • B. US$ 93,000

  • C. US$ 112,000

  • D. US$ 91,400

Explicação

Questão 114 de 150

1

QUESTION 49
Organizations strongly influence the project framework. The PMBOK Guide recognizes which of the following types of organizations?

Selecione uma das seguintes:

  • A. Projectized, Functional.

  • B. Strong Matrix, Organic.

  • C. Weak Matrix, Pre-existing.

  • D. Functional, Transactional.

Explicação

Questão 115 de 150

1

QUESTION 50
During a work breakdown structure meeting you have decomposed the deliverables into work packages and created your WBS dictionary. However, you now want
to decompose the work packages to assist you in estimating, executing and control the project. These decomposed work packages are called?

Selecione uma das seguintes:

  • A. Work Packages can't be decomposed into smaller units

  • B. Activities

  • C. Milestones

  • D. Control Accounts

Explicação

Questão 116 de 150

1

(EXAME 6)
QUESTION 1
While having lunch with another project manager, he tells you that he underestimated the number of staff resources needed for his project by nearly 50%, but says
he has plenty of reserves to cover the costs. During the next staff meeting, the same project manager says he has nothing new to report for his project and that all
is progressing according to schedule. What do you do?

Selecione uma das seguintes:

  • A. Double check your own resource estimates.

  • B. File a complaint with PMI.

  • C. Do nothing.

  • D. Report this to the appropriate management.

Explicação

Questão 117 de 150

1

QUESTION 2
Accepted deliverables are an input to the Close Project or Phase process. These deliverables would have been accepted through which of the following
processes?

Selecione uma das seguintes:

  • A. Validate Scope

  • B. Control Quality

  • C. Control Scope

  • D. Perform Quality Assurance

Explicação

Questão 118 de 150

1

QUESTION 3
Which of the following is not accurate about the initial phase of a project?

Selecione uma das seguintes:

  • A. The highest uncertainty is at this stage of the project

  • B. The cost associated at the beginning of the project is highest

  • C. Stakeholders have maximum influence during this phase

  • D. Staffing levels are the highest at this stage

Explicação

Questão 119 de 150

1

QUESTION 4
As part of the Define Scope process, a project manager documented the specific project assumptions associated with the project scope in the project scope
statement. While reviewing this document, an experienced project manager pointed out that the project manager should also document:

Selecione uma das seguintes:

  • A. The date on which the assumption becomes invalid.

  • B. The assigned responsibility for each of the assumptions.

  • C. The potential impact of the assumptions if they proved to be false.

  • D. An Assumption Management Plan.

Explicação

Questão 120 de 150

1

QUESTION 5
Nancy has recently taken over a website development project. The project is already in execution and half of the project work has been completed. Nancy finds out
that the stakeholder register does not contain any information about key stakeholders from the buyer of the product. What is the potential root cause of this issue?

Selecione uma das seguintes:

  • A. Project stakeholders change over time.

  • B. The previous project manager was not competent.

  • C. This is an unknown risk that has just occurred.

  • D. The Identify Stakeholders process was not properly carried out in the past.

Explicação

Questão 121 de 150

1

QUESTION 6
Which process group corresponds to the "do" part of the plan-do-check-act cycle?

Selecione uma das seguintes:

  • A. Closing

  • B. Monitoring and Controlling

  • C. Planning

  • D. Executing

Explicação

Questão 122 de 150

1

QUESTION 7
The Control Procurements process ensures that the seller's performance meets contractual requirements and that the buyer performs according to the terms of
the contract. This process is part of which process group?

Selecione uma das seguintes:

  • A. Executing

  • B. Closure

  • C. Planning

  • D. Monitoring & Controlling

Explicação

Questão 123 de 150

1

QUESTION 8
You are currently leading a project and performing the work defined in the project management plan. This activity relates to which of the following processes?

Selecione uma das seguintes:

  • A. Direct and Manage Project Work

  • B. Validate Scope

  • C. Control Scope

  • D. Monitor and Control Project Work

Explicação

Questão 124 de 150

1

QUESTION 9
One of the configuration management activities in the project involved capturing, storing and reporting configuration information needed to manage products and
product information. This is known as:

Selecione uma das seguintes:

  • A. Configuration status accounting

  • B. Configuration auditing

  • C. Configuration verification

  • D. Configuration identification

Explicação

Questão 125 de 150

1

QUESTION 10
Sharon has recently been asked to manage the deployment of an enterprise resource planning system for her organization. Sharon has sent her project sponsor a
meeting request to discuss her project's stakeholder management plan. The sponsor believes that the stakeholder management planning is not relevant for such
internal projects. The sponsor believes that only the scope, schedule and cost management plans are sufficient for such projects. The sponsor has asked Sharon
to describe the objective of the meeting. Which of the following is the best response to this question?

Selecione uma das seguintes:

  • A. The objective of the meeting is to develop the project stakeholder register.

  • B. The objective of the meeting is to develop strategies to effectively keep the project stakeholder engaged and committed to the project.

  • C. The objective of the meeting is to conform to the PMBOK standards.

  • D. The objective of the meeting is to identify and classify project stakeholders.

Explicação

Questão 126 de 150

1

QUESTION 11
The paint on the exotic cars that are manufactured in your plant is bubbling after about a year of application. What would be the BEST tool for your team to use to
find potential causes of the peeling paint?

Selecione uma das seguintes:

  • A. Defect Repair Review

  • B. Ishikawa Diagram

  • C. Control Chart

  • D. Inspection

Explicação

Questão 127 de 150

1

QUESTION 12
You are meeting with your team, early in the project, and would like to address all the strengths, weakness, opportunities and threats the project is facing. What
tool should be used?

Selecione uma das seguintes:

  • A. SWOT Analysis

  • B. Interviewing

  • C. Delphi Technique

  • D. Brainstorming

Explicação

Questão 128 de 150

1

QUESTION 13
You are assigned to prepare the Procurement Management Plan for a project that involves setting up an org-wide supply chain management system. You are
looking for a guideline on what type of contracts you can use and what type of contract forms are to be used for this project. Which source will help you obtain this?

Selecione uma das seguintes:

  • A. Each project is unique so you will need to prepare the necessary documentation for this.

  • B. Department process repository

  • C. Organizational Process Assets

  • D. Integrated project Plan

Explicação

Questão 129 de 150

1

QUESTION 14
You are in charge of constructing the Ferris wheel in each town a carnival visits. However, this is something you have never done before and you are getting
different opinions from others on how long it takes. Joe, is new and has given you what you believe to be an optimistic estimate of 3 hours, Bill says it will take 10
hours, which seems too long to you and quite pessimistic. Lastly, Margie, who is the most experienced at this task is telling you it will take 8 hours. You are not sure
who to believe, so you decide to do a PERT estimation, based on this you have determined it will take how many hours to assemble the Ferris wheel.

Selecione uma das seguintes:

  • A. 7.5 hours.

  • B. 8 hours.

  • C. 21 hours.

  • D. 7 hours.

Explicação

Questão 130 de 150

1

QUESTION 15
Rosemary is the project manager at a pharmaceutical company. She begins her day by analyzing her team's work requirements. She then assigns daily tasks to
her team members over a centralized project management information system that then generates automatic task assignment notifications for the team members.
Which of the following types of communication methods has been selected by Rosemary?

Selecione uma das seguintes:

  • A. Formal, push communication.

  • B. Informal, pull communication.
    .

  • C. Formal, pull communication.

  • D. Informal, push communication.

Explicação

Questão 131 de 150

1

QUESTION 16
A project manager colleague of yours is currently working under contract on a short term project. He has expressed some concerns about finding work after the
project ends. The project he is working on is currently ahead of schedule and he expects they will finish a month sooner than initially expected. What advice would
be appropriate to provide him?

Selecione uma das seguintes:

  • A. Slow down work on the project to have it finish on schedule.

  • B. Continue the work within the project's scope and possibly finish ahead of schedule.

  • C. Exaggerate his experience to the sponsor to try to get a project manager position for him on other upcoming projects.

  • D. Inform the client the project is behind schedule and it will have to be extended.

Explicação

Questão 132 de 150

1

QUESTION 17
You have just returned from the weekly change control board meeting where you presented the requested changes to the employee move project. You had five
change requests approved, however one rejected request. These are outputs of what process?

Selecione uma das seguintes:

  • A. Control Quality

  • B. Control Scope

  • C. Control Risks

  • D. Perform Integrated Change Control

Explicação

Questão 133 de 150

1

QUESTION 18
There are two activities on your schedule, which are: 1) Install server in lab 2) Move server into the data center. However, the second task can't start until the
server has run in the lab for 5 days without failure. This is an example of what?

Selecione uma das seguintes:

  • A. Fast Track

  • B. Lead

  • C. Crashing

  • D. Lag

Explicação

Questão 134 de 150

1

QUESTION 19
You just found out that a major subcontractor for your project consistently provides deliverables late. The subcontractor approaches you and asks you to continue
accepting late deliverables in exchange for a decrease in project costs. This offer is an example of:

Selecione uma das seguintes:

  • A. Forcing

  • B. Smoothing

  • C. Confronting

  • D. Compromise

Explicação

Questão 135 de 150

1

QUESTION 21
During your weekly status reports you are reporting the earned value for the project. This information is important for you and the stakeholders to gauge the
progress of the project. What process group are the cost and schedule control part of?

Selecione uma das seguintes:

  • A. Closing

  • B. Planning

  • C. Executing

  • D. Monitoring and Controlling

Explicação

Questão 136 de 150

1

QUESTION 22
You have your project team members record the time they spend on different activities during the day such as: programming, electrical, HVAC, etc. This is an
example of a tool and technique in what process?

Selecione uma das seguintes:

  • A. Manage Communications

  • B. Direct and Manage Project Work

  • C. Monitor and Control Project Work

  • D. Manage Project Team

Explicação

Questão 137 de 150

1

QUESTION 23
You are working with your team and are looking at the cost risks in the project. You are your team are currently creating a tornado diagram for the project risks.
This is done as a part of which of the following processes?

Selecione uma das seguintes:

  • A. Qualitative Risk Analysis

  • B. Risk Response Planning

  • C. Quantitative Risk Analysis

  • D. Control Risks

Explicação

Questão 138 de 150

1

QUESTION 24
Body language plays an important role in effective communications. This relates to which of the following communications dimensions?

Selecione uma das seguintes:

  • A. Nonverbal

  • B. Informal

  • C. Verbal

  • D. Formal

Explicação

Questão 139 de 150

1

QUESTION 25
You have taken over the management of a project from another project manager, who is a certified PMP. This project has been completed and is in the process of
closing. You discover that there is no project schedule. What do you do?

Selecione uma das seguintes:

  • A. Add this issue to the lessons learned database.

  • B. Do nothing.

  • C. Notify the appropriate management immediately.

  • D. Create a schedule.

Explicação

Questão 140 de 150

1

QUESTION 26
You are in the execution stage of your project and you have been informed that "corporate" will be sending in a team of consultants to review whether your project
activities comply with company's and PMI's policies, standards and procedures. This is an example of?

Selecione uma das seguintes:

  • A. Quality Audit.

  • B. Organizational Process Assets.

  • C. Process Analysis.

  • D. Recommended Corrective Actions.

Explicação

Questão 141 de 150

1

QUESTION 27
You are in the initiation phase of your project and believe the project can be completed for $100,000. However, you are an experienced project manager and know
that many things can happen between the initiation phase and the closure of the project. You have provided an estimate in the project charter of $75,000 -
$175,000. This is an example of?

Selecione uma das seguintes:

  • A. Narrow Estimate

  • B. Absolute Estimate

  • C. Rough Order of Magnitude Estimate

  • D. True Estimate

Explicação

Questão 142 de 150

1

QUESTION 28
PMBOK recognizes five process groups typical of almost all projects. Which of the following is not one of them?

Selecione uma das seguintes:

  • A. Executing

  • B. Monitoring and Controlling

  • C. Planning

  • D. Pre-Inception

Explicação

Questão 143 de 150

1

QUESTION 29
A technique that calculates multiple project durations with different sets of activity assumptions and variables is called:

Selecione uma das seguintes:

  • A. Process analysis

  • B. Theoretical Analysis

  • C. Simulation

  • D. Effect Analysis

Explicação

Questão 144 de 150

1

QUESTION 30
A project team is currently assessing the project stakeholder management plan for its validity. The project documents are essential inputs to this process. Which of
the following project documents must be used by the project team during this process?

Selecione uma das seguintes:

  • A. All project documents prepared during the project so far.

  • B. Project documents prepared during the project planning.

  • C. Project documents prepared during the project execution.

  • D. Project documents prepared during the project initiation.

Explicação

Questão 145 de 150

1

QUESTAO 31
A process that states how formal validation and acceptance of the completed project deliverables will be obtained is documented in the:

Selecione uma das seguintes:

  • A. Scope Management plan

  • B. Procurement Management plan

  • C. Risk Management Plan

  • D. Communications Management Plan

Explicação

Questão 146 de 150

1

QUESTION 32
The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives. This is created
as part of:

Selecione uma das seguintes:

  • A. Project Integration Management

  • B. Project Scope Management

  • C. Project Procurement Management.

  • D. Project Time Management.

Explicação

Questão 147 de 150

1

QUESTION 33
Which of the following Perform Quality Assurance techniques relates to root cause analysis and is used to identify a problem, discover the underlying causes, and develop preventive actions?

Selecione uma das seguintes:

  • A. Sensitivity Analysis

  • B. Expected monetary value analysis

  • C. Earned Value Analysis

  • D. Process Analysis

Explicação

Questão 148 de 150

1

QUESTION 34
The process of auditing the quality requirements and the results from quality control measurements to ensure appropriate quality standards and operational
definitions are used is the definition of:

Selecione uma das seguintes:

  • A. Quality assurance

  • B. Quality planning

  • C. Quality control

  • D. Scope validation

Explicação

Questão 149 de 150

1

QUESTION 35
Several of your resources report to another manager. You need them to participate in a series of project meetings over the next two weeks. How should you
handle this?

Selecione uma das seguintes:

  • A. Send meeting invitations to the project resources.

  • B. Provide a copy of the project charter to the other manager, showing that the resources on his team have been assigned to you for your project.

  • C. Request in advance resource participation from the other manager and the resources and communicate information about the timing and duration of the project
    meetings.

  • D. Shortly before each meeting, inform the other manager that his staff is required for your project meeting.

Explicação

Questão 150 de 150

1

QUESTION 36
A buyer has just received a final set of deliverables from the seller and finds that they do not conform to the specifications that were originally planned for. Ideally,
where would the buyer expect to find documentation on how to handle non-conforming deliverables?

Selecione uma das seguintes:

  • A. Communication Plan

  • B. The contract

  • C. Quality Plan

  • D. Scope Statement

Explicação