Prince2 Foundation Questions

Questão 1 de 75

1

Which are purposes of initiating a project process?
1. Establishes a firm base for the project
2. Ensures there is clear understanding of the work involved to deliver the project’s products
3. Avoids commitment of funds before it is appropriate to do so
4. Makes Sufficient information available to define and prepare the Project Brief

Selecione uma das seguintes:

  • 1,2,3

  • 1,2,4

  • 1,3,4

  • 2,3,4

Explicação

Questão 2 de 75

1

A purpose of the Managing a stage Boundary Process is to provide the Project Board with information needed to ratify the [?] for the project?

Selecione uma das seguintes:

  • Agreed tolerance levels

  • Resource requirements

  • Continued business justification

  • Resource availability

Explicação

Questão 3 de 75

1

What is an objective of Managing a stage boundary Process?

Selecione uma das seguintes:

  • Enables the project board to commit resources and expenditure required for the initiation stage.

  • Maintain focus on required outcome

  • Provides a controlled break between those managing the project and those creating the products

  • Ensures a periodic review is held to sign-off the products created within the completed stage

Explicação

Questão 4 de 75

1

Which statement does NOT define a characteristic of a project?

Selecione uma das seguintes:

  • Has a higher degree of risk than the other business activities

  • Involves people with different skills introducing a change that will impact others outside of the team

  • Has a life span that usually covers the delivery of the desired outcomes and the realization to the benefits

  • A temporary management structure created for the implementation of business products

Explicação

Questão 5 de 75

1

Which fact is true of project assurance but not quality assurance?

Selecione uma das seguintes:

  • Responsible for monitoring the conduct of the project

  • Independent of the project manager

  • Appointed as part of the management team

  • Responsible for reviewing the project for compliance with corporate standards

Explicação

Questão 6 de 75

1

Basing projects on a ‘management by exception’ framework provides which benefit?

Selecione uma das seguintes:

  • Promotes consistency of project work

  • Project is not seen as an end its self

  • Clarity of what a project will deliver, why, when and by whom

  • Efficient and economic use of management time

Explicação

Questão 7 de 75

1

How does the controlling a stage process support the learn from experience principle?

Selecione uma das seguintes:

  • Supports the Project Manager in ensuring products are delivered within the tolerances agreed with the Project Board

  • Encourages the Project Manger to review the progress of the stage and log any lessons

  • Requires escalation of issues and risks to the project board which threatens the stage or project tolerances

  • Recommends a Work Package is created to deliver products that require specific skills

Explicação

Questão 8 de 75

1

Which theme provides information on what is required, how it will be achieved and by whom?

Selecione uma das seguintes:

  • Organization

  • Plans

  • Business Case

  • Quality

Explicação

Questão 9 de 75

1

The purpose of which theme is to establish ways to check that a project will still provide the expected benefits?

Selecione uma das seguintes:

  • Business Case

  • Change

  • Progress

  • Quality

Explicação

Questão 10 de 75

1

What is the purpose of Managing Product Delivery Process?

Selecione uma das seguintes:

  • Controls the link between the Project Manager and the Team Manager(s)

  • Tracks the progress of a stage through the consolidation of checkpoints reports

  • Provides a link between the work of the Project Manager and the project

  • Maintains a focus on the delivery of benefits throughout the stage

Explicação

Questão 11 de 75

1

Which role is responsible for capturing the customer’s quality expectations?

Selecione uma das seguintes:

  • Project Manager

  • Executive

  • Senior Supplier

  • Senior User

Explicação

Questão 12 de 75

1

Which product forms the ‘contract ‘between the Project Manager and the Project Board?

Selecione uma das seguintes:

  • Project Plan

  • Project Product Description

  • Project Initiation Documentation

  • Project Brief

Explicação

Questão 13 de 75

1

What is a product Description used for in controlling a Stage Process?

Selecione uma das seguintes:

  • Demonstrating that a product meets its quality criteria through the method specified

  • Forming part of a Work Package that is passed to a supplier for creation

  • Developing the product(S) to the defined quality criteria

  • Obtaining approval for completed products from authorities identified therein

Explicação

Questão 14 de 75

1

Which role is responsible for authorizing and monitoring work to be completed and for taking corrective action within a stage?

Selecione uma das seguintes:

  • Project Manager

  • Project Support

  • Project Assurance

  • Team Manager

Explicação

Questão 15 de 75

1

Which of the following is a baseline management product?

Selecione uma das seguintes:

  • Benefit Review Plan

  • Issue Register

  • Highlight Report

  • Product Status Account

Explicação

Questão 16 de 75

1

What is an objective of the Closing a Project process?

Selecione uma das seguintes:

  • Checks that all the project’s products have been signed off by the users

  • Prepares for the final stage of the project

  • Captures the customer’s quality expectations

  • Ensures that all benefits have been achieved

Explicação

Questão 17 de 75

1

Which process covers the authority to initiate a project?

Selecione uma das seguintes:

  • Starting up a project

  • Initiating a project

  • Directing a project

  • Managing a stage boundary

Explicação

Questão 18 de 75

1

What is a stated purpose of the Closing a Project process?

Selecione uma das seguintes:

  • Define the procedure for handing over products

  • Provide a fixed point at which acceptance for the project product is confirmed

  • Capture the lessons identified during the last stage

  • Confirm all project benefits have been achieved

Explicação

Questão 19 de 75

1

What does a Product Description contain?
1. A breakdown of the individual parts that make up the product
2. The management stage in which the product is to be created
3. Details of the individuals responsible for reviewing the product
4. Any allowable deviation from the specifies quality criteria

Selecione uma das seguintes:

  • 1,2,3

  • 1,2,4

  • 1,3,4

  • 2,3,4

Explicação

Questão 20 de 75

1

Two Management products are given to the Project Board after the end of the process Starting Up a Project. The first is the Project Brief. What is the second?

Selecione uma das seguintes:

  • The Benefit Review Plan

  • The Risk Register

  • A stage Plan

  • The Project Product Description (PPD)

Explicação

Questão 21 de 75

1

The Lessons Log is used during the process Starting Up a Project to:

Selecione uma das seguintes:

  • Record details of things learned in the past that need to be taken into account of in this project

  • Record what will need to be recorded in this project to pass on to future projects.

  • Record who will need to be responsible in this project fro recording any lessons learned, and who will be responsible for passing that information on.

  • All of the above.

Explicação

Questão 22 de 75

1

Which of these logs and Registers is created in Starting Up a Project?

Selecione uma das seguintes:

  • Issues Register

  • Project Log

  • Quality Register

  • Daily Log

Explicação

Questão 23 de 75

1

Which two roles are appointed first in Starting Up a Project?

Selecione uma das seguintes:

  • Senior User and Project Manager

  • Senior Supplier and Senior User

  • Executive and Senior User

  • Executive and Project Manager

Explicação

Questão 24 de 75

1

Which of these questions is answered by the process Starting Up a Project?

Selecione uma das seguintes:

  • Do the Benefits Outweigh the costs of the project?

  • Do we have a viable and worthwhile project?

  • Does the Product Breakdown Structure reflect the full extent of the project?

  • Have all the risks been documented and the associated risk actions approved?

Explicação

Questão 25 de 75

1

Which of these is NOT covered in the process Starting Up a Project

Selecione uma das seguintes:

  • Appointing the Project Board

  • Appointing Project Support

  • Appointing Programme Management

  • Appointing Project Assurance

Explicação

Questão 26 de 75

1

What's the difference between the Business Case included in the Project Brief and the one included later on in the Project Initiation Document (PID)

Selecione uma das seguintes:

  • The project brief is not included in the Project Brief at all/

  • It's less detailed than the version in the PID

  • It's more detailed in the PID version, to support initial decision making.

  • There's no difference: The Project Brief version is carried forward into the PID.

Explicação

Questão 27 de 75

1

Which of the following statements accurately reflects an important aim of the process 'Starting Up a Project?

Selecione uma das seguintes:

  • To do the minimum necessary in order to decide whether it's worthwhile initiating a project.

  • To document all aspects of a project in detail to allow Initiation, if approved, to proceed on a sound basis.

  • To build in delay to the start of Initiation and so provide a cooling off period where managers can consider whether the project is really justified

  • To carry out thorough risk analysis to prevent a high risk project ever being taken forward into Initiation.

Explicação

Questão 28 de 75

1

Which of the following is a true statement?

Selecione uma das seguintes:

  • Starting Up a Project is the first stage in any Prince2 Project.

  • Starting Up a Project is an optional theme in Prince2.

  • Starting Up a Project includes consideration of the way in which work will be conducted - the project approach.

  • Starting Up a Project ends with the production of the Project Initiation Document (PID).

Explicação

Questão 29 de 75

1

After Initiation and the production of the Project Initiation Document(PID), the Project Brief is:

Selecione uma das seguintes:

  • No Longer Maintained

  • Maintained as a section of the PID

  • Held in the Daily Log and kept up to date to serve as the Project Manager's overview

  • Used as a baseline for checks at the end to see whether the project satisfied it's original objectives.

Explicação

Questão 30 de 75

1

Which is one of the six aspects of project performance that needs to be managed?

Selecione uma das seguintes:

  • Accuracy

  • Reliability

  • Scope

  • Ease of use

Explicação

Questão 31 de 75

1

What theme ensures the project is desirable, viable and achievable?

Selecione uma das seguintes:

  • Organisation

  • Progress

  • Business Case

  • Risk

Explicação

Questão 32 de 75

1

What process is triggered by the Project Manager's request to initiate a project?

Selecione uma das seguintes:

  • Starting up a Project

  • Initiating a Project

  • Directing a Project

  • Managing a Stage Boundary

Explicação

Questão 33 de 75

1

The purpose of what theme is to establish mechanisms to monitor and compare actual achievements against those planned?

Selecione uma das seguintes:

  • Business Case

  • Change

  • Progress

  • Quality

Explicação

Questão 34 de 75

1

Which is an objective of the Closing a Project Process?

Selecione uma das seguintes:

  • Check that all the project's products have been accepted by the users.

  • Prepare for the final stage of the project

  • Capture the customer's quality expectations

  • Ensure that all benefits have been achieved

Explicação

Questão 35 de 75

1

Identify the missing words in the following sentence.

A purpose of the Managing a stage Boundary process is to provide the Project Board with sufficient information so that it can approve the [?] for the next stage.

Selecione uma das seguintes:

  • Work Packages

  • Exception Report

  • Stage Plan

  • Project Brief

Explicação

Questão 36 de 75

1

What theme provides information on what is required, how it will be achieved and by whom?

Selecione uma das seguintes:

  • Organisation

  • Plans

  • Business Case

  • Quality

Explicação

Questão 37 de 75

1

Which is recommended as a possible risk response type for an opportunity?

Selecione uma das seguintes:

  • Reduce

  • Transfer

  • Reject

  • Fallback

Explicação

Questão 38 de 75

1

Basing projects on a 'management by exception' principle provides which benefits?

Selecione uma das seguintes:

  • Promotes consistency of project work and staff mobility

  • Provides a common language

  • Clarity of what a project will deliver, why, when and by whom

  • Efficient and cost-effective use of management time

Explicação

Questão 39 de 75

1

Identify the missing words in the following sentence.

The purpose of the [?] process is to establish solid foundations for the project, enabling the organisation to understand the work that needs to be done to deliver the project's products.

Selecione uma das seguintes:

  • Initiating a Project

  • Starting up a project

  • Directing a Project

  • Managing a Stage Boundary

Explicação

Questão 40 de 75

1

Which is a purpose of the Managing Product Delivery process?

Selecione uma das seguintes:

  • Control the link between the Project Manager and the Team Manager(s)

  • Tracks the progress of a stage with the help of checkpoint reports

  • Provides a link between the work of the Project Manager and the Project Board

  • Maintains a focus on the delivery of benefits throughout the stage

Explicação

Questão 41 de 75

1

Which role is responsible for authorising and monitoring work to be completed and for taking corrective action within a stage?

Selecione uma das seguintes:

  • Project Manager

  • Project Support

  • Project Assurance

  • Team Manager

Explicação

Questão 42 de 75

1

Which fact is true of Project Assurance but not Quality Assurance?

Selecione uma das seguintes:

  • Responsible for monitoring the conduct of the project

  • Independent of the Project Manager

  • Appointed as part of the project management team

  • Responsible for reviewing the project for compliance with corporate standards

Explicação

Questão 43 de 75

1

What product forms the 'contract between the Project Manager and the Project Board for the project?

Selecione uma das seguintes:

  • Project Plan

  • Project Product Description

  • Project Initiation Document

  • Project Brief

Explicação

Questão 44 de 75

1

Which is NOT a characteristic of a project?

Selecione uma das seguintes:

  • Has a higher degree of risk than business as usual

  • Involves people with different skills introducing a change that will impact others outside of the team

  • Has a lifespan that covers the delivery of the desired outcomes and the realisation of all the expected benefits

  • A temporary management structure created for the implementation of business products

Explicação

Questão 45 de 75

1

Which is an objective of the Managing a Stage Boundary Process?

Selecione uma das seguintes:

  • Enable the Project Board to commit resources and expenditure required for the initiation stage

  • Review and, if necessary, update the Project Initiation Documentation

  • Provides a break between those managing a project from those creating products

  • Ensure a periodic review is held to approve the products created within the completed stage

Explicação

Questão 46 de 75

1

How should a Team Manager escalate a suggestion for an improvement to a product?

Selecione uma das seguintes:

  • Include details in a Checkpoint Report

  • Include details in a Highlight Report

  • Raise an issue

  • Raise an Exception Report

Explicação

Questão 47 de 75

1

Which is a purpose of the Closing a Project Process?

Selecione uma das seguintes:

  • Define the procedure for handing over products

  • Provide a fixed point at which acceptance for the project product is confirmed

  • Define formal requirements for the acceptance, execution and delivery of project work

  • Confirm all project benefit have been achieved

Explicação

Questão 48 de 75

1

Which is an objective of the Starting up a Project Process?

Selecione uma das seguintes:

  • Confirm there are no known restrictions that would prevent the project from being delivered

  • Ensure all Team Managers understand their responsibilities

  • Get approval for the Project Plan from corporate or programme management

  • Prepare the Project Initiation Documentation for authority to initiate the project

Explicação

Questão 49 de 75

1

What process is used to provide an interface with corporate or programme Management?

Selecione uma das seguintes:

  • Managing Product Delivery

  • Directing a Project

  • Controlling a Stage

  • Managing a Stage Boundary

Explicação

Questão 50 de 75

1

Which is NOT a purpose of an End Project Report?

Selecione uma das seguintes:

  • Compare project achievements against what was originally agreed

  • Record information that will help future projects

  • Prompt the Project Board to authorise the next stage

  • Pass on details of any on-going risks for those who will maintain and operate the finished product

Explicação

Questão 51 de 75

1

Identify the missing word(s) in the following sentence.

If a base-lined product requires modification, the procedure should be applied in order to manage the modification.

Selecione uma das seguintes:

  • risk management

  • exception

  • issue and change control

  • quality control

Explicação

Questão 52 de 75

1

Which is a purpose of a Project Brief?

Selecione uma das seguintes:

  • Describe an agreed position from which the project can be started

  • Describe the information needs of the project's stakeholders

  • Describe the configuration management procedure that will be used by the project

  • Describe the reporting requirements of the Project Board

Explicação

Questão 53 de 75

1

Which is one of the four integrated elements within PRINCE2?

Selecione uma das seguintes:

  • Quality

  • Role descriptions

  • Processes

  • Product Descriptions

Explicação

Questão 54 de 75

1

Which of the following statements apply to a stage plan?
1. Is produced with the knowledge of earlier stages
2. Provides the basis for control by the Project Board
3. Is Produced close to the time when the planned events will take place.
4. Provides the basis for day-to-day control by the Project Manager

Selecione uma das seguintes:

  • 1,2,3

  • 1,2,4

  • 1,3,4

  • 2,3,4

Explicação

Questão 55 de 75

1

Identify the missing words in the following sentence.

Because the Project Board receives regular [?], there is no need for regular progress meetings.

Selecione uma das seguintes:

  • End Stage Reports

  • Checkpoint Reports

  • Exception Reports

  • Highlight Reports

Explicação

Questão 56 de 75

1

Which is a benefit of using the product-based planning technique?

Selecione uma das seguintes:

  • All the required products of the project will be delivered to time and cost

  • Clearly shows how long a project will take

  • It removes the need for activity-based planning

  • Reduces the risk of incorrectly scoping the project

Explicação

Questão 57 de 75

1

Are the following statements about the purpose of the Risk theme true or false?
1. The Risk theme identifies how to manage risks at the corporate or programme level of an organisation.
2. The Risk theme explains the risk management activities to use to improve the chances of a project delivering its objectives

Selecione uma das seguintes:

  • Only 1 is true

  • Only 2 is true

  • Both 1 and 2 are true

  • Both 1 and 2 are false

Explicação

Questão 58 de 75

1

Which project management team role can authorise the premature closure of a project?

Selecione uma das seguintes:

  • Project Manager

  • Project Board

  • Project Suuport

  • Project Assurance

Explicação

Questão 59 de 75

1

Which is a purpose of the Organisation Theme?

Selecione uma das seguintes:

  • Set the tolerance on the cost of resources

  • Provide project management training to those working within the project

  • Define the structure of accountability and responsibilities on the project

  • Implement the controls required to permit management by exception

Explicação

Questão 60 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 61 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 62 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 63 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 64 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 65 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 66 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 67 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 68 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 69 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 70 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 71 de 75

1

Which process enables the Project Board to exercise overall control of a project?

Selecione uma das seguintes:

  • Directing a Project

  • Controlling a Stage

  • Starting up a Project

  • Initiating a Project

Explicação

Questão 72 de 75

1

Which is the first plan to be created?

Selecione uma das seguintes:

  • Project Plan

  • Initiation Stage Plan

  • Team Plan

  • Exception Plan

Explicação

Questão 73 de 75

1

What is a PRINCE2 definition of a project?

Selecione uma das seguintes:

  • A number of Projects managed as a unit

  • A unique undertaking that requires organisation and resources

  • An element of work that a Project Manager agrees to deliver

  • A temporary organisation created for the purpose of delivering business products.

Explicação

Questão 74 de 75

1

Which is NOT an objective of the Managing Product Delivery process?

Selecione uma das seguintes:

  • Ensure suppliers understand what is expected of them

  • Ensure products of appropriate quality are delivered

  • Ensure the Project Board is kept informed of progress on the products

  • Ensure work for the team is agreed with the Project Manager

Explicação

Questão 75 de 75

1

Which is an objective of the quality review technique?

Selecione uma das seguintes:

  • Involve key interested parties to promote wider acceptance of the product

  • Develop and improve the specification of a product through continuous assessment

  • Agree any changes to the base-lined product

  • Update the status information in the Configuration Item Record when a product is signed-off

Explicação