John is the Product Owner, during the Daily he realized that the work is delayed. What should he do?
Responda
-
Nothing
-
Notify the CEO
-
Negotiate a reduction of the scope, guiding the team to focus on the goal
-
Cancel the sprint and change the team of developers
Questão 2
Questão
Frank is the Scrum Master and decided to cancel the Sprint. What should be the PO response?
Questão 3
Questão
Peter is a developer, tested in the user story and noticed a problem. Which action should Peter
Questão 4
Questão
Is Product owner and Scrum master possible in the same person for the same project?
Questão 5
Questão
According to the Scrum guide, can we use parts of Scrum?
Questão 6
Questão
Can we change the size of the sprint during its execution?
Questão 7
Questão
The best scenario for using Scrum is?
Questão 8
Questão
The maximum length of the Sprint Retrospective(its time box) is:
Responda
-
3 hours for a monthly Sprint, proportionally less for shorter Sprints
-
4 hours for a monthly Sprint, proportionally less for shorter Sprints
-
As long as needed
-
1 day
Questão 9
Questão
How many meetings are defined in Scrum?
Questão 10
Questão
What is the purpose of the daily meeting?
Responda
-
Team meeting for inspection and adaptation
-
A formality of Scrum
-
To inform the Product Owner
-
None of the given answers
Questão 11
Questão
When does the development team create the sprint backlog?
Responda
-
daily
-
planning
-
review
-
retrospective
Questão 12
Questão
At the end of the sprint is a product increment that will go into production?
Questão 13
Questão
After the start of the sprint, what product owner will do?
Questão 14
Questão
Is it true that the Scrum Master is responsible for the ROI of the product?
Questão 15
Questão
What is the role of the project manager in the Scrum framework?
Questão 16
Questão
When to cancel a sprint?
Questão 17
Questão
Scrum master ensures that Scrum is being applied correctly?
Questão 18
Questão
How does the product owner help the development team?
Responda
-
Detailed all product backlog
-
Clearing up doubts about backlog items
-
With the help of requirements analyst
-
He does not help the team.
Questão 19
Questão
When a backlog item was set to high priority, for what situation should it be considered?
Responda
-
Definition of done
-
Definition of Timebox
-
Definition of ready
-
None of the answers
Questão 20
Questão
Does the development team need to be multifunctional?