Screeding Quiz

Descrição

Quiz sobre Screeding Quiz, criado por Steve Lockwood em 05-11-2014.
Steve Lockwood
Quiz por Steve Lockwood, atualizado more than 1 year ago
Steve Lockwood
Criado por Steve Lockwood aproximadamente 10 anos atrás
428
0

Resumo de Recurso

Questão 1

Questão
1. How much mixed material is needed to complete a floor screed 5.000 m long by 4.000 m wide and 0.050 m thick?
Responda
  • 0.25 m3
  • 0.5 m3
  • 1 m3
  • 1.5 m3

Questão 2

Questão
2. Tools and equipment for floor screeding will generally include:
Responda
  • sweeping brush, trowel, float, mixer, shovel
  • splash brush, small tool, gauger, trowel, float
  • spirit level, trowel, buckets, mixer, float
  • levelling equipment, trowel, float, shovel buckets, mixer

Questão 3

Questão
Plastic sheeting below the structural floor is the:
Responda
  • damp proof membrane
  • vapour barrier
  • moisture trap
  • aid to curing the floor

Questão 4

Questão
The type of cement used in floor screeds is:
Responda
  • Masonry Portland
  • Extra Portland
  • Rapid Portland
  • Ordinary Portland

Questão 5

Questão
Sands used for floor screeding:
Responda
  • should contain a high proportion of fine grains
  • should contain a high proportion of large grains
  • can be any type
  • should be sharp and well graded

Questão 6

Questão
Ready-mixed screeds are:
Responda
  • prepared off site and delivered as required
  • prepared after work for the following day
  • prepared in the morning for use during the day
  • used only for self-levelling floors

Questão 7

Questão
Screed rails or battens are used to:
Responda
  • help delivery of screed material to the workstation
  • assist in forming the main area of floor
  • tamp down the surface of the screed
  • form channels for drainage

Questão 8

Questão
The purpose of a damp proof membrane is to:
Responda
  • assist the passage of moisture
  • assist in the curing process
  • allow the screed to dry out quickly
  • prevent the passage of moisture

Questão 9

Questão
Cracking of large area floors may be reduced by:
Responda
  • use of more cement
  • use of expansion strips
  • adding more sand
  • a self-levelling compound

Questão 10

Questão
Battens used as a guide for screeds may be:
Responda
  • set out from datum lines
  • laid at 50 mm depth
  • set out from base floor
  • laid to form 75 mm depth

Questão 11

Questão
The most accurate proportioning of floor screeding materials:
Responda
  • is by weight
  • is important near heavily trafficked areas
  • can be carried out using shovels
  • can be carried out using buckets

Questão 12

Questão
The correct consistency for floor screeding materials is:
Responda
  • as dry as possible
  • slurry like
  • semi wet
  • semi dry

Questão 13

Questão
Mixing of screed material:
Responda
  • does not have to be thorough as it will be spread by shovel
  • needs to be consistent or wear will take place
  • should be carried out as slowly as possible
  • can take place after water has been added

Questão 14

Questão
Compacting screeds results in a:
Responda
  • lightweight screed
  • quicker set screed
  • more dense screed
  • slower set screed

Questão 15

Questão
Compacting can be carried out with a:
Responda
  • screed rail
  • datum
  • rule or float
  • level

Questão 16

Questão
High volumes of ventilation:
Responda
  • will aid the setting process
  • will not affect the screeds after laying
  • will allow the cement to harden quickly
  • may make the surface of the screed dusty

Questão 17

Questão
The finish on a floor screed:
Responda
  • is not important as it will all be covered up
  • is important as it may show through the final covering
  • can be completed the next day
  • can be completed by the floor layer with the finish

Questão 18

Questão
Laying polythene sheet on the floor screed after laying will:
Responda
  • act as an accelerator to the set
  • produce an even surface
  • allow the cement to set naturally
  • keep the floor soft for the next process

Questão 19

Questão
The purpose of curing is to:
Responda
  • allow the cement to set and harden over a long period
  • produce an even surface
  • produce a lightweight screed
  • aid compaction to take place

Questão 20

Questão
Where drainage outlets are fitted:
Responda
  • the floor must be laid from this point
  • they can be repositioned later
  • the floor can be altered to fit when finish is applied
  • the drainage contractor will alter them to suit

Semelhante

Português - Gramática
Nikita Northman
PESQUISA CIENTÍFICA NA PRÁTICA
profetransmidia
Direito Constitucional - Brutal - Tribunais
Rômulo Campos
Biologia e Geologia - Geologia 10º ano, parte I - Ensino Secundário Português
Heres Oliveira
Artigo Científico X Ensaio Teórico
mayara.sampaio
Simulado de física
Alessandra S.
FATORES NEUROPSICOLÓGICOS (anexo neuropsicologia)
Lorena S. Sousa
Era Napoleônica
Camila Teixeira
FIGURAS DE LINGUAGEM
Gabriela Vianna
Revisão 1 - PROVA DE SARGENTO - MARINHA - EA-HSG - ( Com Verificação )
Nilzeir Reis